Executive Member - Education Item 23 March 2006 Major Projects Status Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.
1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
2. Completed Schemes
2.1 Since the January 2006 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Staunton Park Community March 2006
Whitchurch CE Primary School February 2006
3. Additional Works and Funding Added Post Contract
3.1 The following schemes have had further funding added to the contract for specific additional works.
3.2 Cove Junior School
The scheme at the above school for a three classroom and music/drama extension commenced on site during October 2005. An additional £10,000 from the Policy and Resources 2005/06 NDS Condition budget has been added to this contract to convert the existing oil fired boilers to gas.
3.3 Grayshott CE (C) Primary School
A major scheme currently on site at this school to construct a single storey extension and undertake internal alterations is progressing well on site, with completion due in May 2006. The school has recently added £32,728 to undertake the refurbishment of an existing toilet block, which will be incorporated into the current contract and will have no effect on the programme
3.4 John Hunt of Everest Community
The major scheme to provide a new school and Youth Facility commenced on site in January 2006 and works are progressing well. Additional school funding of £27,385 has been added, at the request of the school, for revisions to the first floor corridor above the gymnasium, retention of a first floor arts/textiles terrace and retention of fire rated internal screens.
3.5 Netley Marsh Infant School
A scheme for a new classroom, extended classroom and extended hall commenced on site during August 2005. Additional funding of £20,000 has recently been added to this contract from the Policy and Resources 2005/06 NDS Condition fund for a number of building maintenance items associated with the existing building.
3.6 St Lawrence CE (C) Primary School
A scheme currently on site at the above school to provide a new hall, kitchen, link building and internal refurbishment is progressing well on site and is due for completion during April 2006. The school has recently added £43,500 from its Devolved Capital allocations for kitchen and hall equipment, furniture, works to fit out a Resource / Teaching area and partitioning of the existing Caretaker's Room.
3.7 South Baddesley Primary School
The major scheme at this school to provide a new classroom and staff room (phase one) and a new hall and car park (phase two) is progressing well and is due for completion during March 2006. The school has recently added £23,188 to this contract for the provision of a new play court.
3.8 Whitchurch Primary School
At the January 2005 meeting it was reported that the above school had made a contribution of £8,522 towards replacement coping stones for the major scheme currently on site. Since that time, the cost of these works has been finalised and subsequently reduced to £7,000. The Director of Property, Business and Regulatory Services has now made a contribution for the £7,000 from the Policy and Resources NDS Condition fund 2005/06 and the school have been reimbursed their original contribution.
The school has since contributed £22,967 towards this contract for the provision of a new ramp to an existing playground.
4. Additional Works and Funding added at Pre Contract Stage
4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.
4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
4.3 Newtown Soberton Infant School
A design project appraisal for a scheme at this Infant School to provide a new hall and internal adaptations for a Nursery Unit was approved at the July 2005 meeting of the Executive Member for Policy and Resources.
Additional funding of £5,990 from the Education Capital Programme 2005 F&E budget has been added at pre-contract stage for additional furniture requirements.
5. Current Position
5.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.
5.2 Crescent Primary School
A major scheme at this school to construct a two classroom and library extension was agreed at the February 2005 meeting of the Executive Member for Policy and Resources. Work was programmed to complete during March 2006, however, due to the late delivery of glulam beams the work will now complete during April 2006.
5.3 Mountbatten School and Language College
A scheme to provide a new staff room, inclusion room and multi-agency space was approved a the April 2005 meeting of the Executive Member for Policy and Resources. Work was programmed to complete during February 2006, however, the contractor is currently reporting a delay to the contract which will result in a April 2006 completion. The current extension of time claim from the contractor is being investigated to ascertain the reason's for the delay to the agreed programme.
5.4 Netley Marsh Infant School
As detailed above (in 3.5) this major scheme commenced on site during August 2005 and was due for completion during February 2006. Due to the late delivery of steel work it is now anticipated that work will complete during late March 2006, one month later than previously reported.
6. Pinewood Infant School, Farnborough
6.1 The Cabinet agreed on 13 December 2004 that Pinewood Infant School, which was largely destroyed by fire in March 2003, should be rebuilt as a one-form entry infant school (90 places) with language impairment resource provision. The project is included in the Children's Services Capital Programme 2006/07 at an estimated cost of £3.815m including furniture and equipment. £2.6m of the estimated cost is to be met from the County Council's Insurance Fund. The remaining £1.215m is to be met from the capital receipt due to Children's Services in 2006/07 from the sale of the site of the former Mayfield Infant School, Farnborough.
6.2 The planning application was submitted in January 2006 and the project appraisal will be submitted for approval during June 2006. It is proposed to commence construction of the new school at the end of July 2006.
6.3 Following the fire in March 2003, five temporary buildings, including administration, community spaces and classrooms, have been provided on the site. To enable the construction of the replacement school it is necessary to install a further double temporary classroom during the spring half term week, to allow the existing pre-school to decant from the remaining permanent building prior to the start of construction. The cost of the additional double classroom and associated enabling works is currently being confirmed but is estimated to be a maximum of £75k.
Conclusion
The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.
Recommendations
1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be approved.
2. That the additional funding added to the major capital project at Newtown Soberton Infant School, at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.
3. That the proposal to install an additional double temporary classroom and undertake associated enabling works at Pinewood Infant School, Farnborough, to a maximum cost of £75k, prior to approval of the project appraisal, be approved.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules
Project Appraisal
I/PB&R/Committees/MajorMinorSelf-Funded?2006/March/MajorProjectsStatusReport
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Blackfield Primary School - creation of 2.5fe Primary school by extending and remodelling existing Junior school |
On site |
Dec 05 |
Aug 06 |
* 1,498,208
|
Education Capital 05/06 1,185,345 Edu Early Years 05/06 34,483 Education contingency 46,552 School 231,828 1,498,208 |
Bridgemary Community School, Gosport - new Exercise Space |
Design |
Jul 06 |
Dec 06 |
294,000 |
School 294,000 |
Broughton Primary School, Stockbridge - new kitchen |
On site |
Mar 06 |
July 06 |
* 199,635 |
Education Capital 05/06 179,635 School 20,000 199,635 |
Costello Technology College, Basingstoke - replacement maths / technology teaching block |
On site |
Nov 05 |
Feb 07 |
* 5,200,434 |
P&R Fire Re'statem't 05/06 4,870,434 Education Capital 05/06 250,000 P&R NDS Condition 05/06 80,000 5,200,434 |
Court Moor School, Fleet - refurbish and extend Youth Block |
Tender analysis |
Apr 06 |
Jul 06 |
242,000 |
Edu - Youth Service 05/06 138,000 Edu - Early Years 05/06 59,000 School - Connexions 25,000 P&R NDS Condition 05/06 20,000 242,000 |
Cove Junior School, Farnborough - three classroom extension, Music/Drama and kiln room |
On site |
Oct 05 |
May 06 |
* 804,202 add 10,000 814,202 |
Education Capital 05/06 717,000 School 54,202 P&R NDS Condition 05/06 43,000 814,202 |
The Crescent Primary School, Eastleigh - two classroom and library extension |
On site |
Jul 05 |
Apr 06 |
* 827,050 |
Education Capital 05/06 628,550 School 53,500 HC3S 20,000 P&R NDS Condition 05/06 125,000 827,050 |
Crestwood Community School, Eastleigh - Community Sports Hall, drama studio and Fitness Suite |
On site |
Oct 05 |
Jun 06 |
* 3,132,183 |
Capital Programme 05/06 3,132,183 |
Grayshott CE (C) Primary - single storey extension and internal alterations |
On site |
Oct 05 |
May 06 |
* 525,000 add 32,728 557,728 |
Education Capital 05/06 365,000 School 192,728 557,728 |
Havant BESD School - new BESD Secondary School |
Design |
Jun 06 |
Jul 07 |
4,910,000 |
Education Capital 05/06 712,000 TCF 3,056,000 Rachel Madocks receipt 671,000 Future land sales 471,000 4,910,000 |
The Henry Cort Community College, Fareham - extension to staff room, two new offices, internal remodelling and refurbishment |
On site |
Aug 05 |
Mar 06 |
* 417,886 |
Education Capital 05/06 97,948 School 283,938 P&R NDS Condition 05/06 15,000 P&R Capital Repairs 05/06 2,000 P&R L'lords M. Works 05/06 12,000 P&R Ext. Landscaping 05/06 7,000 417,886 |
Hollywater School, Bordon - new special school |
On site |
May 05 |
Dec 06 |
* 6,088,472 |
Edu Cap / TCF 05/06 4,887,472 P&R Capital Repairs 05/06 629,000 P&R Capital Receipt 572,000 6,088,472 |
John Hunt of Everest Community School, Basingstoke - New School and Youth facility |
Enabling - Complete On site |
Aug 05 Jan 06 |
Nov 05 Apr 07 |
* 1,106,416 * 21,532,336 add 27,385 22,666,137 |
Capital Receipts 13,543,659 Developer's Contribution 2,383,824 B&D Borough Council 2,008,615 County Council 4,702,654 School 27,385 22,666,137 |
Lakeside School, Chandlers Ford - refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation |
Complete Complete Phase 2 |
Jul 04 Nov 04 Jul 05 |
Aug 04 Apr 05 May 06 |
* 196,000 * 568,000 * 1,301,254 * 2,065,254 |
Education Mod'tion 04/05 1,565,000 Education Capital 04/05 261,254 P&R NDS Condition 04/05 49,000 P&R Fire Precautions 04/05 190,000 2,065,254 |
Minstead Rural Study Centre, Lyndhurst - new residential building, extension to schoolhouse and removal of temps |
On site |
Dec 05 |
Jul 06 |
* 1,228,000 |
Education Capital 05/06 519,000 Temp Classroom Hire 05/06 28,000 New Opportunities Fund 487,000 Study Centre 100,000 New Forest District Council 26,000 P&R Landlords contribution 68,000 1,228,000 |
Mountbatten School and Language College - new Staff Room, Inclusion room and Multi-agency space |
On site |
Jul 05 |
Apr 06 |
* 449,000 |
Edu. Capital - SEED 05/06 117,000 School 332,000 449,000 |
Netley Marsh Infant - new classrooms and extended hall |
On site |
Aug 05 |
Mar 06 |
* 678,312 add 20,000 698,312 |
Education Capital 0506 595,381 School 62,931 P&R NDS Condition 05/06 40,000 698,312 |
Newtown Soberton Infant School - new Hall and internal adaptations to create a Nursery Unit |
On site |
Mar 06 |
Hall - Sep 06 Nursery - Oct 06 |
* 546,990 |
NDS Modernisation 05/06 438,000 School 103,000 Education FF&E 05/06 5,990 546,990 |
Nightingale Primary School, Eastleigh - extension to provide permanent classroom accommodation - MUGA |
Complete |
Feb 05 Easter 06 |
Nov 05 Easter 06 |
* 1,201,663 |
NDS Modernisation 04/05 391,304 Contingency 55,173 Capital Receipt 646,552 School 108,634 1,201,663 |
Oak Lodge School, Dibden Purlieu - drama room and music practice room |
Design |
Apr 06 |
Sep 06 |
241,000 |
School 241,000 |
Rachel Maddocks School, Waterlooville - extension, internal alterations, refurbishment and repair |
On site |
Feb 05 |
Jun 06 |
* 346,963 |
Education Capital 05/06 204,000 School 136,259 P&R Capital Repairs 05/06 6,704 346,963 |
Rowner Youth Services, Gosport - new Youth Facility |
Tender analysis |
Apr 06 |
Oct 06 |
346,027 |
Education Capital 06/07 88,027 P&R Capital Prog. 06/07 129,000 SRB 129,000 346,027 |
Saint Lawrence CE (C) Primary - new hall, kitchen, link building and internal refurbishment |
On site |
Oct 05 |
Apr 06 |
* 599,485 add 43,500 642,985 |
Education Capital 05/06 599,485 School 43,500 642,985 |
South Baddesley CE (C) Primary - phase 1 - new classroom and staffroom - phase 2 - new hall and car park |
Complete On site |
May 05 Sep 05 |
Oct 05 Mar 06 |
* 424,722 * 516,793 add 23,188 964,703 |
Education Capital 04/05 391,828 Education contingency 11,207 School 148,841 NDS Condition 05/06 65,000 P&R Capital Repairs 05/06 87,827 P&R Capital 05/06 260,000 964,703 |
Staunton Park Community - Healthy Living Centre |
Complete |
Jul 05 |
Mar 06 |
* 546,812 |
NDS Modernisation 04/05 70,862 School 53,950 Sport England 422,000 546,812 |
The Toynbee Community College, Chandlers Ford - new Multi-Purpose Suite |
On site |
Nov 05 |
May 06 |
* 508,620 |
School 265,517 P&R Capital 05/06 200,000 Eastleigh Borough Council 43,103 508,620 |
Trosnant Infant and Junior Schools, Leigh Park - Trospac full day-care provision |
Negotiation |
Apr 06 |
Aug 06 |
585,000 |
Education Capital 05/06 237,000 Sure Start (Children's Centre) 87,000 DfES general Sure Start 261,000 585,000 |
Waterside Primary School, Hythe - remodel and refurbish existing school; construct classroom block and early years unit |
On site |
Nov 05 |
Jul 06 |
* 1,913,815 |
Education Capital 05/06 1,539,462 School 125,000 P&R Capital Repairs 05/06 25,246 P&R NDS Condition 05/06 224,107 1,913,815 |
West Tytherley C of E Primary, Salisbury - classroom extension to replace temporary accommodation |
Tender Analysis |
Apr 06 |
Nov 06 |
906,473 |
Education Capital 05/06 866,473 School 40,000 906,473 |
Whitchurch CE (C) Primary - two new classrooms, ICT Suite and corridor |
Complete |
Jul 05 |
Feb 06 |
* 515,000 add 29,967 544,967 |
Education Capital 04/05 431,000 School 106,967 P&R NDS Condition 05/06 7,000 544,967 |
Wildern School, Hedge End - new Learning Centre |
Tender Analysis |
May 06 |
Dec 06 |
702,000 |
School 463,000 P&R Capital Repairs 06/07 50,000 Remainder tbc 702,000 |
Woolton Hill Junior School - extension to library and hall store |
Design |
Jul 06 |
Nov 06 |
231,000 |
Education Capital 05/06 43,000 School 119,000 P&R Capital Repairs 06/07 69,000 231,000 |
Appendix 2
Other Schemes in the Education Capital Programme
The following schemes are included in the Education 2005/ 06 and 2006/07 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
Dowd's Farm Primary |
3,695 |
Freegrounds Infant |
517 |
New Whiteley Primary |
1,240 |
King's Copse Primary |
3,579 |
Pinewood Infant |
3,182 |
Shamblehurst Primary |
517 |
SECONDARY
Wildern School |
216 |
SPECIAL
Baycroft School |
261 |
Henry Tyndale School |
486 |
Sundridge School |
4,823 |
EDUCATION OTHER THAN AT SCHOOLS
Basingstoke School Plus |
2,391 |
Woodlands Education Centre |
3,967 |
NDS MODERNISATION
Burghclere Primary |
443 |
Curdridge Primary 05/06 |
618 |
Greatham Primary |
652 |
Hardley School |
1,721 |
Micheldever Primary 05/06 |
1,240 |
Stanmore Primary 05/06 |
217 |
The Bridge Centre 05/06 |
830 |
TOTAL |
30,595 |