Archived decisions
Hampshire County Council
Buildings, Land and Procurement Panel Item
4 April 2006
Capital Repairs 2005/06 and 2006/07 Report by the Director of Property, Business and Regulatory Services |
Contact: Karen Murray Ext: 7876 email: [email protected]
How the conclusion in this report fits with the Corporate Strategy Because the activities covered by this report affect the majority of the County Council's services, they contribute to the achievement of all the corporate aims, in particular: Aim 1 - maximising life opportunities - by providing a good quality, safe and well maintained estate for the community to enjoy. Aim 5 - improving services - by providing good quality buildings that enable improved service delivery. |
2 |
2005/06 Position |
2.1 |
The major repair and traditional capital repair allocations were combined with effect from April 2005. The combined capital repairs budget for 2005/06 was £11m - this was augmented by a modest carry forward from 2004/05 of £211,000 and, following a recommendation by the Panel at their meeting on 5 April 2005, by £1.060m from the Advantageous Land programme (this funding was allocated to support four specific projects). The total funding available, including fees, was therefore £12.271m. |
2.2 |
£7.3m of this budget was allocated to support key Corporate Risk Assessment priorities with the balance allocated to support other schemes and landlord strategic requirements. |
2.3 |
The level of commitments against these allocations at the end of February 2006 is shown at Appendix 1. At this stage it is anticipated that the budget will be fully committed by year end but any slippage will be carried forward into 2006/07. |
3 |
2006/07 and beyond |
3.1 |
The capital repairs allocation for 2006/07 of £15.6m will be targeted at continuing to reduce maintenance liabilities and to address the priorities identified in the Corporate Risk Assessment. The proposed allocation is shown at Appendix 2. |
3.2 |
From April 2006 Government funding for schools is to be provided by a separate grant, the Dedicated Schools Grant (DSG). The capital repair allocation previously provided from schools block revenue contributions will in future be funded from the DSG and will need to be spent in full on schools. This will reduce capacity to bring resources together in a way that maximises the impact of the individual funding streams and the change will further constrain the resources available to maintain the non-schools estate. |
3.3 |
Inflation continues to run between 6-7% and this already high level is expected to increase as work on the 2012 Olympics moves ahead. The standard allocation of 2.5% has been added to the locally resourced capital repairs programme available for non-schools work. Following a decision of the Schools' Forum the full 7% has been added to the DSG capital repairs programme for 2006/07 and, provisionally, for 2007/08. |
3.4 |
NDS funding has been confirmed for 2006/07 and 2007/08 but no further allocations will be announced until the Government has completed its Comprehensive Spending Review in 2007. If no further resources are identified the funding available for capital repairs to school buildings will reduce by over 50% in 2008/09 despite the positive impact provided by the DSG funding. The County Council is not expected to receive any funding from the Building Schools for the Future (BSF) programme until 2011 but may benefit from the additional funding from 2008/09 for building projects in primary schools recently announced by the DfES. |
3.5 |
NDS allocations up to 2005/06 have been provided by the Government as 100% capital grant. For 2006/07 this support will be provided as 60% supported borrowing and 40% capital grant - in 2007/08 this moves to 70% supported borrowing and 30% capital grant. Supported borrowing should mean that the Government provides additional revenue grant to meet in full the loan charges incurred in servicing the borrowing. However, the County Council's low grant settlement means it is significantly below the minimum floor level for grant increases and any supported borrowing allocation would only have the effect of moving the County Council closer to the floor level at which grant increases can be received. For 2006/07 the County Council has decided to continue its policy of taking up in full all supported borrowing approvals but the extent to which it can continue to afford to do so without the benefit of the extra grant to fund the borrowing costs will be subject to review in 2007/08. Unless the Government changes the way in which it provides the NDS allocations this is likely to mean the 2007/08 allocation will not be taken up in full. |
3.6 |
The Panel has previously approved a policy of planning resources over a three year timescale and expenditure in 2005/06 was managed tightly to ensure sufficient capacity was available in future years to accommodate a number of pressures including Ashburton Court. A further re-profiling of the locally resourced capital repairs programme is now proposed both to ensure that the agreed contributions to the funding of the Ashburton Court project are in place for 2008/09 and 2009/10 and to retain some capacity in 2007/08 to deal with the uncertainties about levels of NDS funding, the impact of DSG funding on resources for non-schools work and other issues. Details of the proposed profile for locally resourced capital repairs are shown at Appendix 3 and the total level of resources this would provide over the next four years are summarised in the table below: |
3.7 |
2006/07 2007/08 2008/09 2009/10 £'000 £'000 £'000 £'000 Capital Repairs 5,358 7,584 5,666 5,691 DSG 10,194 10,907 10,907 10,907 NDS Condition 12,601 12,784 Total 28,153 31,275 16,573 16,598 |
3.8 3.8.1 |
Advantageous Land Due to the pressures on the non-education capital repairs work, further issues, progress on DDA related work and the final funding for the new offices in the former Intech building, proposals are being made to the Leader to discuss the use of the 2005/6 advantageous land budget vote. |
4 |
Capital Repairs Programme |
4.1 |
Details of the schemes to be added to the programme of capital repairs are contained in Appendix 4. |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act
........................
........................
Capital Repairs 2005/06 Appendix 1
Commitment as at 2 March 2006
Area of Work |
Budget |
Commitment |
£'000 |
% | |
Corporate Risk Assessment |
||
Condition of building fabric |
2,406 |
95 |
Mechanical services failure |
1,310 |
117 |
Structural collapse |
726 |
69 |
Asbestos |
700 |
93 |
Fire including arson |
660 |
97 |
Electrical services failure |
506 |
81 |
Legionella |
254 |
28 |
DDA |
216 |
117 |
Other priorities |
548 |
77 |
Other Allocations |
||
Joint funded landlord's minor works |
737 |
90 |
Strategic maintenance |
406 |
105 |
Landlord's contributions |
350 |
101 |
County Farms |
350 |
90 |
Other inc. contingency |
2,042 |
69 |
Total |
11,211 |
89 |
Virement from Adv. Land |
1,060 |
66 |
12,271 |
87 |
Capital Repairs 2006/07 Appendix 2
Proposed allocations
Area of Work |
Budget |
£'000 | |
Corporate Risk Assessment |
|
Condition of building fabric |
3,631 |
Mechanical services failure |
1,064 |
Structural collapse |
692 |
Asbestos |
692 |
Fire including arson |
1,330 |
Electrical services failure |
851 |
Legionella |
250 |
DDA |
213 |
Other priorities |
789 |
Other Allocations |
|
Joint funded landlord's minor works |
1,372 |
Strategic maintenance |
744 |
Landlord's contributions |
640 |
County Farms |
640 |
Other inc. contingency |
2,644 |
Total |
15,552 |
Budget figures for 2006/07 include fees.
Locally Resourced Capital Repairs Profile Appendix 3
2007/08 |
2008/09 |
2009/10 | |
£'000 |
£'000 |
£'000 | |
Original guideline |
10,399 |
5,503 |
5,503 |
Proposed re-profiling |
-3,000 |
1,000 |
2,000 |
Inflation - 2.5% |
185 |
163 |
188 |
Contribution to Ashburton Court |
-1000 |
-2,000 | |
Revised guideline |
7,584 |
5,666 |
5,691 |
Appendix 4
Additions to Capital Repairs Programme 2006/07
Summary
£50,000 - £100,000
Bedenham Primary School, Gosport - external redecoration and prior repairs
Bickerley Green OPH - internal wall repairs
Bishops Waltham House - fire precaution works
Hampshire Scientific Services - phase of refurbishment to labs/lighting/ceiling
Harrison Primary School, Fareham - external redecoration and prior repairs
Highfield House - fire precaution works
Lee-on-Solent Library - repairs and refurbishment
Merrydale Respite Unit - boiler replacement
Thurlston House OPH - boiler replacement
Three Minsters House - external redecoration and prior repairs
Three Minsters House - phase 1 replacement of chillers with VRV system
Westholme OPH - structural repairs to brickwork and replacement windows
Wildern School, Hedge End - infrastructure works
£100,000 - £250,000
Older Persons' Homes - fire prevention upgrading
Oakridge OPH - door and window replacement
Marlfield OPH - boiler replacement and drainage works
Solent Mead (Older Person's Home) - window replacement
Stubbington Library - repairs and refurbishment
Swanmore School, Swanmore - repairs and refurbishment
Winchester Discovery Centre - contribution to infrastructure works
Wyvern School - contribution to infrastructure works associated with capital scheme for car parking and access
£250,000+
Bickerley Green OPH - boiler, doors and window replacement
lift refurbishment, internal wall repairs
Montgomery House - refurbishment and repairs to offices
Richard Aldworth School,
Basingstoke - external redecoration and prior repairs