Hampshire County Council Executive Member - Policy and Resources 6 April 2006 Wyvern Technology College, Fair Oak Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1 |
Summary |
|
|
1.1 |
The following decision is sought: |
|
|
1.2 |
That the project to remodel the school frontage to improve access and provide additional parking at an estimated cost of up to £533,599, excluding fees be approved. |
|
|
2 |
Reason |
|
|
2.1 |
To provide enhanced vehicular and pedestrian circulation thus improving site safe and accessibility, whilst increasing the car parking provision on this shared school site. |
2.2 |
This decision supports Aim 1 and 5 of the Corporate Strategy by providing improved facilities which will benefit all users of the school. |
|
|
3 |
Other options considered and rejected |
|
|
3.1 |
The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need. |
|
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
|
|
4.1 |
None. |
|
|
5 |
Dispensation granted by the Standards Committee |
|
|
5.1 |
Not applicable. |
|
|
6 |
Reason(s) for the matter being dealt with if urgent |
|
|
6.1 |
Not applicable |
|
|
|
|
Approved by: |
.......................... |
Date of decision: |
................... |
Councillor T K Thornber, Executive Member for Policy and Resources |