Archived decisions

Hampshire County Council

Executive Member, Policy and Resources

6 April 2006

Children's Services capital programme issues

Report of the Director of Children's Services

and County Treasurer

Item 5

Contact: Bob Eardley, Strategic Planning Manager, 01962 846275. Email: [email protected]

1. Summary

1.1 This report sets out proposed changes to the 2005/06 and 2006/07Children's Services capital programmes.

1.2 The proposals in this report support the following corporate aims:

    · Aim 1 (Maximising life opportunities) by proposing allocations of funding to improve the learning environments of Hampshire schools.

    · Aim 5 - (Improving services) by considering solutions which will contribute to the raising of educational standards.

1.3 Race and equality impact assessment has been considered in the development of this report and no adverse impact has been identified.

2. Amendments to the 2005/06 capital programme

      Projects to be carried forward to 2006/07

2.1 The projects listed in Table 1 will not start in 2005/06 and need to be carried forward with their resources to 2006/07. Starts in the first quarter of the new financial year are expected.

      Table 1

     

    Current budget

    £'m

    Curdridge Primary School

    0.711

    Micheldever Primary School

    1.847

    Trospacc Children's Centre, Havant

    0.700

3. Amendments to the capital programme 2006/07

    Health and safety issues - Wyvern campus, Fair Oak

3.1 Wyvern College, Fair Oak Junior and Fair Oak Infant Schools share a campus. As a result of a number of expansion projects over several years, the campus is now at capacity, resulting in significant congestion and car parking difficulties. As Wyvern College has a number of successful community activities, there are vehicle and pedestrian movements throughout the day, which are at their maximum at the start and end of the school day. Arrangements for segregation of vehicles and pedestrians would benefit from significant changes to the layout of the site entrances and car parking to improve safety and vehicle flow.

3.2 A project to address these issues has been developed and is reported for approval elsewhere on this agenda. The total cost of the project is estimated at £0.505m and can be funded as shown in Table 2.

      Table 2

    Funding source

    £'m

    Schools' contributions

    0.145

    Safer Routes to School

    0.050

    Policy and Resources

    0.155

    Proposed contribution from Children's Services capital programme

    0.155

    Total

    0.505

3.3 There is provision in the Health and Safety block vote in the 2006/07 capital programme for a contribution to this project. It is recommended that a contribution of £0.155m is made from that source.

      Crofton Hammond Junior School

3.4 Crofton Hammond Junior School is a 2fe community school located within the Stubbington area of Fareham. It currently has 242 pupils on roll and is forecast to remain at full capacity over the coming years. Housing development at HMS Daedalus will generate demand for additional primary school places in the area and Crofton Hammond Junior School is one those likely to accommodate children from the development.

3.5 Part of the school's accommodation is in a double temporary classroom. A recent structural survey of the unit by Property Services revealed that its condition is now considered to be `very poor'. It is proposed that this unit should now be replaced with a permanent structure therefore, ensuring that the school has suitable accommodation in which to deliver the curriculum. The work envisaged will also improve the flexibility of available accommodation and allow the school to take more pupils.

3.6 The estimated cost of the proposed scheme is £0.449m. The County Council has recently received a developer's contributions of £0.400m linked to the housing development on the HMS Daedalus site. It is therefore proposed that this contribution should be used fund the project, together with £0.049m of the school's devolved formula capital.

3.7 It is recommended that the developer's contribution of £0.400m should be added to the resources for 2006/07 and that a major project to replace the double temporary classroom at Crofton Hammond Junior School at an estimated cost of £0.400m should be added to the 2006/07 programme.

4. Early years capital funding and projects

      Early years capital funding in 2005/06

4.1 As part of the overall funding regime for early years provision, the DfES made available:

    (a) in 2004/05 and 2005/06 capital resources of £0.812m, principally towards the cost of increasing the availability of pre-school education and childcare, but also for investment in Phase 1 children's centres. This is termed sustainability capital by the DfES;

    (b) in 2005/06 a capital allocation of £0.791m for investment in children's centres.

4.2 Both of these are allocations are indicative and need to be claimed against expenditure incurred. Strategies for optimising their use are set out below.

      Sustainability capital

4.3 Phase 2 of the children's centres programme was announced by the DfES in June 2005 and an indicative capital allocation to the County Council of £9.515m was announced at the same time; this funding would be available over two financial years from April 2006. It was clear that this funding would be inadequate to provide the 53 children's centres required under Phase 2. The view was taken that further commitments from early years capital funding available from the DfES in the current financial year should not be made until the capital resourcing issues relating to the children's centre programme as a whole were clearer. As a result, although some projects to improve provision at Phase 1 centres have been worked up, resources have not yet been committed to contracts. Other high priority early years projects were committed using separate funding in the capital programme block vote for early years provision and other sources within the Children's Services capital programme.

4.4 The capital funding position for Phase 2 children's centres is now clearer (see paragraphs 4.11 to 4.15 below) and initial desktop costing exercises indicate that even with the enhanced capital resources available from the DfES in 2006/07 and 2007/08, it will be very difficult to fund Phase 2. Consequently, a strategy is proposed to maximise the carry-over of capital funding from the current year to increase the resources available for Phase 2, while allowing a small amount of high priority work at Phase 1 centres to proceed using 2005/06 resources. This approach is seen as providing a prudent balance between investment in Phase 1 and Phase 2 centres.

4.5 Table 3 sets out proposals for allocating this funding to specific projects. Of the £0.812m available:

      · £0.020m has been committed;

      · £0.742m is proposed for allocation to projects already funded by the County Council. This amount could then be carried forward and be available to spend in 2006/07;

      · £0.050m is proposed for allocation to projects at Phase 1 centres, where work will be completed by 31 March 2006.

      Table 3

Project

Committed

County

Council

funded

Proposed commitments

Comments

£'m

Trospacc, Havant

0.020

   

Community building

Aviary, Eastleigh

 

0.122

 

Part cost of major project

Lanterns, Winchester

 

0.473

 

Part cost of major project

Oak Meadow, Fareham

 

0.147

 

Improvements to centre

Oak Meadow, Fareham

   

0.030

Further proposed works

Warren Park, Havant

   

0.020

Further proposed works

Totals

0.020

0.742

0.050

 

4.6 If this strategy is approved £0.742m will be available to increase the resources available for future investment in children's centres. This is subject to:

      · £0.147m of the carry forward being allocated for children's centre developments in Fareham. This is because the expenditure at Oak Meadow Early Years Centre shown in Table 3 was funded from resources made available through the William Price Trust, which can be spent only in Fareham;

      · £0.473m being made available from Policy and Resources. This reflects the fact that this sum could be claimed by Children's Services against the capital receipts from asset sales being used to provide part of the funding for the Lanterns Children's Centre project.

4.7 The following recommendations are proposed:

      · Endorsement of the approach set out in paragraph 4.5 and Table 3;

      · Carry forward of resources totalling £0.269m (i.e. £0.742m - £0.473m) from 2005/06 to 2006/07;

      · an allocation in 2006/07 of £0.473m from capital receipts (when received).

      Children's Centre capital

4.8 The DfES has allocated £0.791m to the County Council in 2005/06 towards the capital costs of Phase 1 children's centres. Of this sum, £0.430m has already been allocated to cover expenditure on specific projects, as shown in Table 4. Of the £0.361m unallocated it is proposed to use £0.249m to fund the project at Links Children's Centre, Cowplain (see paragraph 4.17) and £0.050m as a contribution to Gosport Borough Council for the Sure Start Rowner Centre. This leaves a balance of £0.062m. The DfES has been asked whether it can be carried forward to 2006/07, but the application has been refused. This funding cannot, therefore, be allocated.

      Table 4

Project

£'m

Comments

Links, Waterlooville

0.249

Approval being sought for project funding

Park, Aldershot

0.100

Reimbursement to CS capital programme (26/10/05)

Sharps Copse, Havant

0.330

Reimbursement to CS capital programme (26/10/05)

Sure Start Rowner

0.050

Contribution made to project sponsored by Gosport BC

Total

0.729

 

4.9 In order to maximise the use of the General Sure Start revenue grant, it is proposed to vire £0.354m from GSSG to the 2005/06 capital programme to enhance the funding available for early years capital projects/initiatives. This additional funding can then be used to offset expenditure already incurred for early years projects, thus enhancing resources available for future schemes. The scope to carry forward this capital will ensure that capital programme flexibility is maximised in 2006/07. Once there is a clearer view of forward year priorities, a further report will be bought to Executive Members for consideration. The recommended approach of viring revenue to capital is consistent with guidance from the DfES, but the claim will be subject to submission and audit. It is recommended, therefore, that the £0.354m is allocated to the contingency until the claim has been accepted by the DfES.

4.10 The projects which it is proposed to finance from these additional resources are set out in Table 5.

      Table 5

Projects

£'m

Lanterns Early Years Centre, Winchester - purchase of furniture and equipment

0.161

Wallop Primary School - purchase of temporary building for early years group

0.090

Blackfield Primary School - contribution to early years facilities

0.103

Total

0.354

      Early years capital funding in 2006/07 and 2007/8

4.11 As indicated in paragraph 4.3 an initial capital allocation of £9.515m was announced by the DfES in June 2005 towards the cost of providing 53 Phase 2 children's centres. The funding would be made available over two financial years from April 2006 and would be subject to claims being made for individual projects.

4.12 Subsequent announcements from the DfES have confirmed that additional funding will be available to support:

      · Phase 2 of the children's centre initiative;

      · the provision of childcare through extended schools; and

      · the expansion of childcare provision in areas not covered by children's centres (sustainability capital).

4.13 The available funding totals £19.775m over the two years and a proposed split is shown in Table 6. This:

      · allocates most of the resources to Phase 2 children's centre provision;

      · recognises the DfES policy of supporting the provision of childcare in extended schools through the allocation of specific capital resources;

      · allocates funding to support the expansion of existing childcare facilities or provision of new ones, outside the children's centre initiative.

      Table 6

 

2006/07

2007/08

Total

£'m

Children's centre capital

7.783

6.666

14.449

Children's centre capital - rural uplift

0.125

0.125

0.250

Provision of childcare through extended schools

1.718

1.758

3.476

Sustainability capital

0.600

1.000

1.600

 

10.226

9.549

19.775

4.14 This allocation is proposed as a working model at this stage and patterns of actual expenditure will be kept under review. Recommendations will be made to change the balance of the allocations if required. When costings for the first tranche of phase 2 children's centres are clear a further report will be submitted on a more detailed funding model.

4.15 It is recommended that resources for 2006/07 and 2007/08 are increased to reflect additional DfES allocations, as shown in Table 5.

      Early years capital funding 2006/07 - summary

4.16 If the proposals set out in this section are approved, the revised provision for early years capital in 2006/07 would be as shown in Table 7.

      Table 7

 

£'m

Approved 2006/07 provision for EY permanent buildings

0.500

Approved 2006/07 provision for EY temporary buildings

0.300

Children's centre capital allocation 2006/07

7.783

Children's centre capital allocation 2006/07 - rural uplift

0.125

Provision of childcare through extended schools allocation 2006/07

1.718

Sustainability capital 2006/07

0.600

Early years capital to be carried forward from 2005/06

0.269

Early years capital subject to approval by Executive Member, P&R

0.473

Children's Centre capital carried forward from 2005/06 to 2006/07

0.062

General Sure Start capital vired to revenue

0.354

Total

12.184

      Links Children's Centre (formerly Littlefold Family Centre), Cowplain

4.17 On 26 October 2005 the Executive Member for Education approved a major project to extend and adapt the Littlefold Family Centre, Waterlooville as a children's centre. The estimated cost of the project was £0.230m, of which £0.200m was chargeable to the 2005/06 children's centre capital budget and £0.030m to General Sure start Grant.

4.18 Tenders for the project have now been received and the actual cost will be £0.249m. In accordance with the funding strategy set out in paragraph 4.8, it is recommended that the project proceeds and that the full cost is met from the 2005/06 provision for Phase 1 children's centre capital.

5. Temporary Classrooms

Abbotts Ann Primary School

5.1 This school has a capacity of 102 places, including 30 places in an existing temporary classroom, and a number of roll of 94. The temporary classroom at this school has now reached the end of its economic life and will need to be replaced with another temporary building. This is a medium-term measure as there is a longer-term plan to replace the school on a different site. The estimated cost of locating the temporary classroom is £13,000, with an annual rental of £9,000; the cost can be met from the revenue budget for temporary classrooms It is recommended that a planning application is made to replace the existing temporary unit with another to remain on site until August 2011.

      Wildern School, Hedge End

5.2 Wildern School has a net capacity of 1,798, with 1,807 pupils on roll in January 2006. Its Published Admission Number (PAN) is currently 360; however, in September 2005, following appeals, the number admitted was 372. The school is again over-subscribed from within its catchment area for September 2006 admissions and if all in-catchment pupils are admitted to the school, there will be 380 pupils in Year 7. If these pupils are not admitted they are almost certain to win at appeal, as Wildern is their catchment school. Over-subscription will continue for the next four to five years, exacerbated by pupils expected from the new Dowd's Farm housing development, which also lies within the Wildern catchment area.

5.3 There is, however, an underlying reduction in the number of pupils currently attending Wildern's feeder primary schools and the over-subscription is, therefore, likely to begin to reduce by approximately 2011 to within the current PAN. Plans are also in hand to make changes to the school's infrastructure to cater for additional pupils and financial provision has been made for this work in the 2006/07 capital programme. The estimated cost of locating the temporary classrooms is £17,000, with an annual rental of £14,000; the cost can be met from the revenue budget for temporary classrooms. To meet the additional in catchment demand for places at Wildern, it is recommended that a double temporary classroom is placed on site from September 2006.

6. County Council Policy Requirements

6.1 Legal implications - The proposals support the County Council's statutory duty to provide school places and comply with central government accommodation requirements and guidance.

6.2 Financial implications - These are set out in the report.

6.3 Personnel implications - None directly arising from this report.

6.4 Community cohesion, inclusiveness and partnership working - Most of the capital projects proposed in this report support these aims.

6.5 Crime prevention issues - None directly arising from this report.

Recommendations

    1. That the following variations to the 2005/06 capital programme be approved:

      (a) that resources totalling £0.812m from DfES grant be added to the 2005/06 capital programme as sustainability capital for early years and childcare projects;

      (b) that resources totalling £0.361m from DfES grant be added to the 2005/06 capital programme for the development of children's centres;

      (c) that the following major projects in the 2005/06 Children's Services capital programme be carried forward to 2006/07:

      (i) Curdridge Primary School, at a revised estimated cost of £0.711m;

      (ii) Micheldever Primary School, at a revised estimated cost of £1.847m;

      (iii) Trospacc Children's Centre, Havant, at an estimated cost of £0.700m.

      (d) that expenditure on the following projects be charged to the block vote for early years sustainability capital:

      (i) a contribution of £0.122m for Aviary (Nightingale) Early Years Centre, Eastleigh, originally charged to the 2005/06 capital programme contingency;

      (ii) a contribution of £0.473m for Lanterns Children's Centre, Winchester, originally charged to the 2004/05 capital programme contingency;

      (iii) a contribution of £0.147m for Oak Meadow Early Years Centre, Fareham, originally charged to the 2005/06 capital programme, minor works funded through grant from the William Price Trust;

      (iv) £0.020m for provision of a community building at the Trospacc Early years Centre, Havant.

      (e) that expenditure on the following projects be charged to the block vote for the development of children's centres:

      (i) a grant of £0.050m to Gosport Borough Council towards the cost of the Sure Start Rowner facility, Gosport;

      (ii) an allocation of £0.249m to fund a project to develop the Links Children's Centre, Waterlooville.

      (f) that funding of £0.354m be vired from General Sure Start Grant as an addition to the capital programme contingency to reflect contributions made to the cost of early years projects.

    2.
    That the following variations to the 2006/07 capital programme be approved:

      (a) the addition of resources of £0.400m from a developer's contribution to the provision for new pupil places in Gosport;

      (b) that a major project at Wyvern College, Fair Oak be added to the capital programme at a total estimated cost of £0.505m, with a contribution of £0.155m from the block vote for health and safety measures;

      (c) that a major project at Crofton Hammond Junior School, Gosport be added to the capital programme at a total estimated cost of £0.049m, with a contribution of £0.400m from the provision for new pupil places;

      (d) that a contribution of £0.473m be made to the Children's Services capital programme from the capital receipt, when received, from the sale of the former Greenacres School, Winchester;

      (e) that resources totalling £10.266m from DfES grant be added to the 2006/07 capital programme for the provision of early years facilities, to be split as follows:

      (i) £7.908m for the provision of children's centres;

      (ii) £1.718m for the provision of childcare through extended schools;

      (iii) £0.600m for sustainability capital.

    3.
    That the following variations to the 2007/08 capital programme be approved:

      (a) that resources totalling £9.549m from DfES grant be added to the 2007/08 capital programme for the provision of early years facilities, to be split as follows:

      (i) £6.791m for the provision of children's centres;

      (ii) £1.758m for the provision of childcare through extended schools;

      (iii) £1.000m for sustainability capital.

    4.
    That the following applications for planning permission for temporary classrooms be approved until 31 March 2010:

      (a) a single temporary classroom at Abbotts Ann Primary School;

      (b) a double temporary classroom at Wildern School, Hedge End.

      Section 100D - Local Government Act 1972 - Background papers

    The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

      NB: the list excludes:

      1. Published works

      2. Documents which disclose exempt or confidential information as defined in the Act.

      None.