Archived decisions
Report of the Director of Children's Services and County Treasurer | |||
Contact: Bob Eardley, Strategic Planning Manager, 01962 846275. Email: [email protected]
1 Summary
1.1 The following decisions are sought:
1. That, subject to the approval of the Executive Member, Policy and Resources, the following variations to the 2006/07capital programme be approved:
(a) an allocation of £0.250m to a major project at Fernhill Secondary School, Farnborough to be funded from the provision for improvement of CDT facilities;
(b) the addition of resources of £0.200m to the provision for secondary school improvements for grant allocations for specialist school status to Testbourne Community School and Warblington School.
2. That the following variations to the 2006/07 capital programme be approved:
(a) allocations from the provision for staff workforce projects to the projects listed in Appendix 1;
(b) an allocation of £0.050m from the block allocation for secondary school sports halls for a project at Cams Hill School, Fareham;
(c) an allocation of £0.058m from the block allocation for the management of falling rolls for a minor works project at Oak Meadow Primary School, Fareham;
(d) an allocation of £0.078m from the block vote for health and safety to fund hot surface remedial projects at the schools listed in Appendix 2;
(e) an annual allocation of £0.025m for fire prevention measures from the block allocation for health and safety at schools to be identified;
(f) allocations from the provision for science and food technology projects to the projects listed in Appendix 3;
(g) an allocation of £0.050m from the provision for health and safety towards the cost of a minor works project at Droxford Junior School;
(h) the following allocations from the capital programme contingency:
(i) £0.156m to meet the costs of providing temporary accommodation for the Hampshire County Wardrobe at Chilcomb, Winchester;
(ii) £0.004m towards the cost of a school funded project to provide a multi-use space at Froxfield Infant School;
(iii) £0.007m towards the cost of a school funded project to provide a dance/drama studio at Oak Lodge Special School, Dibden;
(iv) £0.016m to reflect additional tender costs of a major project at Hamble Primary School;
(v) £0.021m towards the cost of replacing electrical switchgear, associated with an externally funded project to provide floodlit tennis courts at Staunton Park Community School, Havant.
3. That a response along the lines set out in Appendix 4 is made to the DfES consultation document "Every Child Matters: Primary Capital Programme".
4. That it be a recommendation to the Executive Member for Policy and Resources that temporary classrooms are located on the following sites until August 2011:
Elvetham Heath Primary School Fleet - one single unit
Basingstoke School Plus, Ashwood site - one double and one single unit
Samuel Cody School, Farnborough - one double unit
Hook Infant School - one double unit
Durley Primary School - one single unit
and that renewals of temporary classroom planning consents are sought for those locations listed in Appendix 5.
2 Reason
This decision supports Aim 1 of the Corporate Strategy (Maximising life opportunities) by proposing allocations of funding to improve the learning environments of Hampshire schools.
3 Other Options considered and rejected:
None.
4 Conflicts of Interest declared by the decision maker or other Executive Member consulted
None
5 Dispensation granted by the Standards Committee -
6 Reason(s) for the matter being dealt with if urgent -
Not applicable
Approved by: Date:
Councillor D A Kirk
Executive Member for Education