Hampshire County Council Executive Member - Education Item 25 May 2006 Minor Projects - Progress Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1. Summary
1.1 The purpose of this report is to provide an update of the progress made in implementing those schemes in the Children's Services Capital Programme with a value of between £43,000 and £216,000 (exclusive of fees).
2. Current Position
2.1 The attached tables summarise the current position in relation to schemes funded by the Children's Service 2005/06 and 2006/07 Capital Programme including Minor Works, Seed Challenge, William Price Trust, Schools Access Initiative (SAI), New Opportunities Fund (NOF) and Staff Workplaces budget. The tables provide details of the funding, a brief description of the works and a summary of the current position.
3. Minor Works Capital Programme 2006/07
3.1 Baycroft Special School, Fareham
An allocation of £51,724, excluding fees, has been made in the Children's Services Capital Programme 2006/07 Block Vote for Secondary specialist facilities, for works to refurbish the original school house to provide two areas as an environment for pupils to learn domestic skills. Some external groundworks will also be carried out to protect the dampproof course.
It is proposed to invited tenders during May 2006, with expected start on site during July and completion during September 2006.
3.2 Froxfield CE Infant School, Petersfield
An allocation of £4,310, excluding fees, has been made in the Children's Services 2006/07 Capital Programme contingency which, together with School devolved capital of £131,897, excluding fees, will fund the erection of a Homelodge building to be used as a multi-use space.
Tenders are due to be invited during June 2006, with an anticipated start on site date during September 2006 and completion during December 2006.
3.3 Hamble Primary School
Tenders for this scheme were returned higher than anticipated and since reporting this scheme in May 2005, the following additional funding has been added:
£ (excl. fees)
P&R Fire Budget (for new fire alarm panel) 5,000
P&R Landscape Budget 12,000
P&R Asbestos Budget (asbestos removal in lobby and other areas) 11,000
Children's Services Capital Programme 06/07 13,793
School - devolved capital 3,000
This scheme is currently on site and it is anticipated that completion will take place during September 2006.
3.4 Oak Meadow Primary School/Early Years Centre, Fareham
It is proposed to relocate the Nurture Unit currently located within the Early Years Centre to the Primary School building. The resulting space within the EYC will be refurbished as part of a major scheme to refurbish the EYC as a Children's Centre( see report elsewhere on the agenda).
An allocation of £50,000, excluding fees, has been made in the Children's Services Capital Programme 2006/07 Block Vote for the Management of Falling Rolls, for this scheme
Tenders will be sought during May 2006, with anticipated start on site during July 2006 and completion during August 2006.
3.5 Staunton Park Community School
An allocation of £18,000, excluding fees, has been made in the Children's Services Capital Programme 2006/07 and the School is contributing £188,450 towards the construction of 4/5 floodlit tennis courts. The number of courts will be dependent on favourable tender returns.
Tenders are due to be invited during May/June 2006, with an anticipated start on site during August 2006 and completion during November 2006.
3.6 St Luke's Primary School, Sway
An allocation of £21,000, excluding fees, has been made in the Children's Services Capital Programme (Security Budget) 06/07, £43,000, excluding fees, from the Workforce Reform Budget and £67,000 from the School's devolved capital, to construct a staff room extension plus entrance alterations.
It is anticipated that works will commence on site during July 2006, with completion during October 2006.
3.7 St Michael's Junior School, Aldershot
An allocation of £25,862 (excluding fees) has been made in the Children's Services Capital Programme 2006/07 Block Vote for Staff Facilities, together with an allocation of £17,000 (excluding fees) from the Local Management of Schools budget and a school contribution of £73,000 (excluding fees) for internal alteration and refurbishment works to form a staff workspace from the existing oversized school hall.
It is anticipated that tenders will be sought during May 2006, with start on site in July 2006 and completion during October 2006.
3.8 West Meon Primary School, Petersfield
An allocation of £146,400, excluding fees, has been made in the Children's Services Capital Programme 2006/07 and the school is contributing £40,000 for a first floor extension over the existing administration office to form additional classroom space, thereby freeing up an existing area for use as a main hall.
The scheme will be negotiated with a preferred contractor and it is anticipated that work will commence on site during August 2006. This is dependent on the planning process, the school being a Grade II Listed Building within a Conservation Area.
4. Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2006/07
4.1 Kings School, Winchester
An allocation of £27,000, excluding fees, has been made in the Children's Services Capital Programme 2006/07 (SAI), together with a school contribution of £23,000, for refurbishment works to an existing therapy room and the creation of a foyer area.
This work will be procured through a framework contractor and it is anticipated that works will commence on site during August 2006, with completion during September 2006.
4.2 Otterbourne CE Primary School, Winchester
An allocation of £47,826, excluding fees, has been made from the Children's Services Capital Programme 06/07 (SAI) and the school is contributing £75,000, excluding fees, for internal adaptation works to improve staff facilities.
It is proposed to invite tenders during July 2006. It is anticipated that works will commence on site during September 2006 and be completed during February 2007.
4.3 Wildern Secondary School, Hedge End
An allocation of £58,522, excluding fees, has been made in the Children's Services Capital Programme 06/07 (SAI) for a scheme to install an alarm system for hearing impaired, together with modifications to existing toilets and level access works.
It is anticipated that tenders will be invited during May 2006, with start on site during July 2006 and completion during September 2006.
4.4 Wyvern Technology College, Fair Oak
It is proposed to install a hygiene room and accessible wc and to refurbish existing toilet accommodation. Funding of £39,130, excluding fees, has been made available from the Children's Services Capital Programme 2006/07 (SAI), the school is contributing £120,560, excluding fees, and a P&R Capital Repairs contribution of £10,000, has been made available for these works.
The scheme will be negotiated with a contractor during April 2006, with an anticipated start on site during June 2006 and completion during July 2006.
5. William Price Trust
5.1 Heathfield School, Fareham
The scheme to improve and extend the existing Early Years playground was originally approved in October 2005. Tenders have now been received and are higher than expected. The school is therefore contributing an additional £12,000, together with a P&R external works budget 06/07 contribution of £7,500. The original funding was for a total of £80,100, excluding fees and the funding is now £99,600, excluding fees.
6. Specialist School College Status Allocations 2006/07
6.1 Mill Chase Community Technology College, Bordon
An allocation of £87,000, excluding fees, has been made in the Children's Services Capital Programme 2006/07 (Specialist School College allocation) and a contribution of £20,000 from the school for the refurbishment of CDT accommodation.
This works will be negotiated through a framework agreement with Nolan Davis Contracting. It is anticipated that works will commence on site during July 2006 with completion during September 2006
7. NDS Modernisation 2006/07
7.1 Shipton Bellinger Primary School, Tidworth
An allocation of £30,000, excluding fees, has been made in the Children's Services Capital Programme 2006/07 and the school is contributing £43,000, excluding fees, devolved capital for works to refurbish toilets and replace the water pipe.
It is anticipated that works will commence on site during July 2006 and complete during September 2006.
7.2 Test Valley School, Stockbridge
An allocation of £43,478, excluding fees, has been made in the Children's Services Capital Programme 2006/07 and £14,500, excluding fees, from the F&E budget for works to upgrade one science laboratory as part of the NDS Modernisation programme.
It is anticipated that the works will be carried out during the summer of 2006 and a programme of work is currently being agreed with the school.
.
Recommendation
1. That the changes to the minor works programme be approved.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information File, PBRS
Minor Works Capital Programme 2006/07 ( including carry forwards)
School |
Funding Position £ |
Summary of works |
Comments | |
Baycroft Special School Fareham |
Capital Programme 06/07 51,724 51,724 |
Refurbishment of original school house to provide two areas as an environment for pupils to learn domestic skills. Some external groundworks will also be carried out to protect the dampproof course. |
It is proposed to invite tenders during May 2006, with expected start on site during July and completion during September 2006. | |
Bordon Junior School |
Capital Programme 05/06 50,103 School - Devolved Capital 66,000 P&R NDS Condition 05/06 25,000 141,103 |
Entrance lobby, canopy and internal alterations to admin office. |
This scheme was completed during February 2006. | |
Butts Primary School Alton
|
Capital Programme 05/06 77,586 P&R Capital Repairs 20,000 School - Devolved Capital 45,049 162,635 |
Extend existing building to improve administrative/staff accommodation and provide a multi purpose teaching room. |
These works were completed during March 2006. | |
Chase Children's Centre Bordon |
Capital Programme 05/06 47,627 47,627 4 |
Extension to office accommodation and provision of ramped access to the Centre. |
It is proposed to negotiate this scheme with a preferred contractor. This work commenced on site during April 2006 with completion during June 2006. | |
Froxfield CE Infant School Petersfield |
Capital Programme 06/07 4,310 School - devolved capital 131,897 136,207 |
Erection of Homelodge building. |
Tenders will be invited during June 2006, with anticipated start on site during September and completion during December 2006. | |
Hamble Primary School |
Capital Programme 05/06 100,000 Capital Programme 06/07 13,793 P&R 38,000 School - Devolved Capital 58,000 209,793 |
Extension to create additional teaching space, cloak and alterations to lobby/ entrance area. |
These works are currently on site with completion anticipated in September 2006. Tenders were returned high and additional funding has been added to the scheme for a new fire alarm panel, asbestos and landscaping works. | |
Oak Meadow Primary School /Early Years Unit Fareham |
Capital Programme 06/07 - Block allocation surplus place removal 50,000 |
Relocation of Nurture Unit from EYC to Primary School building |
It is proposed to invite tenders during May 2006, with anticipated start on site during July 2006 and completion during August 2006. | |
Staunton Park Community School Havant |
Capital Programme 06/07 18,000 School 188,450 206,450 |
Construction of 4/5 floodlit tennis courts |
It is anticipated that tenders will be invited during May/June 2006, with start on site in August and completion during November 2006. |
|
South View junior School Basingstoke |
Capital Programme 05/06 30,000 School - Devolved Capital 35,000 65,000 |
Extension to library |
It is proposed to invited tenders during May 2006 with works commencing on site in July 2006 and completion anticipated in September 2006. | |
St Luke's CE Primary School Sway |
Education Capital Programme (Security Budget) 05/06 21,000 School - Devolved Capital 67,000 Workforce Reform Budget 43,000 131,000 |
Extension to provide staff room, plus entrance alterations. |
It is anticipated that works will commence on site during July 2006 with completion anticipated in October 2006. | |
St Michael's Junior School Aldershot |
Capital Programme 06/07 Block Vote/Staff Improvements 25,862 Local Management of Schools 17,000 School - Devolved Capital 73,000 115,862 |
Internal alterations and refurbishment works to form a staff workspace |
It is proposed to invite tenders during May 2006, with anticipated start on site during July and completion during October 2006. | |
The Wavell School Farnborough |
Education Capital Programme (Lottery funding) 06/07 43,000 Rushmoor Borough Council 20,000 School - Devolved Capital 34,000 97,000 |
Conversion of existing gymnasium to form a movement space |
It is proposed to invite tenders during May 2006 with works commencing on site in July 2006 and completion anticipated in August 2006. | |
West Meon Primary School Petersfield |
Capital Programme 06/07 146,400 School - Devolved Capital 40,000 186,400 |
First floor extension over existing admin office to form additional classroom to free up existing area for use as main hall. |
This scheme is to be negotiated with a preferred contractor (P&R approval 6.4.04). It is anticipated that the scheme will commence on site during August 06 but this is dependent on the planning process (the school is a Grade II Listed Building within a Conservation Area). | |
Staff Workplaces 2006/07 (including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
Burley Primary School |
Capital Programme 05/06 34,255 Staff Workplaces Remodelling Budget 25,800 School - Devolved Capital 20,000 80,055 |
Small extension to provide additional office accommodation. |
Tenders are due to be sought during May 2006 with an anticipated start on site date during August 2006 and completion during December 2006. |
Castle Hill Junior School Basingstoke |
Capital Programme 05/06 30,000 School - Devolved Capital 35,000 65,000 |
Extension to staff room to provide additional space for staff. |
Tenders are due to be sought during May 2006 with an anticipated start on site date during July 2006 and completion during September 2006. |
Itchen Abbas Primary School Winchester |
Capital Programme 05/06 43,500 Education - School Security 17,400 School - Devolved Capital 73,275 134,175 |
Relocation of admin office and Headteacher's office to first floor to provide improved security and staff office facilities. |
This scheme was completed on site during April 2006. |
Yateley School Yateley |
Education - School Security 97,969 97,969 |
New reception to sports/ performing arts studio |
This scheme will now be included in a larger NDS scheme to reclad the sports hall, to be carried out in the summer of 2006. |
Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2006/07 (including carry forwards)
School |
Funding Position £ |
Summary of Works |
Comments |
Bohunt Community School |
Capital Programme 05/06 57,800 |
Improvements to provide accessibility |
This scheme is currently being undertaken and much of the work has been completed. However, due to difficulties with access to certain operational areas of the school, full completion is likely to be during July 2006. |
Horndean Junior School Waterlooville |
Capital Programme 05/06 63,930 School - Devolved Capital 9,500 73,430 |
Accessible WC and alterations to girls WC and alterations to provide level access. |
This scheme commenced on site during April 2006 and is due to complete during June 2006. |
Kings School Winchester |
Capital Programme 05/06 145,000 Capital Programme 06/07 56,150 201,150 |
Internal lift access. |
Some additional funding has been added to this scheme to fund additional external access works which will be carried out as part of the internal lift contract. It is anticipated that works will commence on site in May 2006 and be completed during August 2006. |
Kings School Winchester |
Capital Programme 06/07 27,000 School 23,000 50,000 |
Refurbishment of existing therapy room and creation of foyer. |
To be procured through a framework contractor. It is anticipated that works will commence on site during August 2006 and complete during September 2006. |
Otterbourne Primary School |
Capital Programme 06/07 47,826 School - Devolved Capital 75,862 123,688 |
Ramps and level access and provision of accessible wc |
It is proposed to tender this work during May 2006, with anticipated start on site during July 2006 and completion during August 2006 |
Ringwood Infant School Ringwood |
Capital Programme 05/06 78,250 School - Devolved Capital 39,750 118,000 |
Internal access and modifications to WCs. |
Work is on site with completion anticipated during May 2006. |
Weyford Infant School |
Capital Programme 05/06 70,174 |
Ramps, accessible WC and platform lift. |
The accessible wc/platform lift works were completed during September 2005. Ramps to form part of framework agreement. These works are now complete. |
Wildern Secondary School Hedge End |
Capital Programme 05/06 58,522 |
Alarm system for Hearing Impaired, modifications to WC's and level access. |
Tenders are due to be invited during May 2006, with an anticipated start on site during July and completion during September 2006. |
Wyvern Technology College Fair Oak |
Capital Programme 05/06 39,130 School - devolved capital 110,827 P&R Capital Repairs 10,000 159,957 |
Provision of hygiene room and accessible wc. Toilet refurbishment works. |
This scheme is due to commence on site during June 2006 with completion anticipated during July 2006. |
William Price Trust 2006/07 (including carry forwards )
School |
Funding Position £ |
Summary of Works |
Comments |
Heathfield Special School Fareham |
Capital Programme 05/06 56,100 School - Devolved Capital 36,000 External Works budget 06/07 7,500 99,600 |
Improvement and extension of existing Early Years playground. |
The school has contributed an additional £12,000 to the scheme together with a contribution from the P&R external works budget 06/07 of £7,500 to account for tender returns which were higher than anticipated. Works commenced on site during April 2006 and completion is anticipated during July 2006. |
Oak Meadow Early Years Centre Fareham |
Capital Programme 05/06 Phase I 95,000 Phase II 46,400 141,400 |
Internal alterations to form additional meeting areas, creation of new external entrance, provide toilets, and storage areas. Also formation of car park with 17 spaces including some accessible spaces, new footpath, entrance and external storage shed. |
All works are now completed on this scheme. |
Specialist School College Status Allocations 2006/07
School |
Funding Position £ |
Summary of Works |
Comments |
Alderman Quilley Secondary School Eastleigh |
Specialist School Funding 05/06 87,000 P&R Capital Repairs 05/06 20,000 School funding 18,200 NDS Condition Fund 05/06 15,000 43,500 140,200 |
New doors/ramp. Internal refurbishment/decoration, electrical/mechanical works. Enabling package for asbestos removal (£5k) |
The works were completed during May 2006. |
Cowplain Community School |
Capital Programme 05/06 87,000 School - Devolved Capital 57,249 School - fundraising 50,000 194,249 |
Specialist school allocation. Extension and conversion of caretaker's house for use as an IT suite/video conference facilities and offices for school/ community use |
Works commenced on site during April 2006 and it is anticipated that completion will be during September 2006. |
Crestwood College for Business and Enterprise Eastleigh |
Capital Programme 05/06 105,000 School funding tbc |
Specialist school allocation |
Feasibility/design underway and programme being agreed. |
Mill Chase Community Technology College Bordon |
Capital Programme 06/07 87,000 School - Devolved Capital 20,000 107,000 |
Refurbishment of CDT accommodation |
The works will be negotiated through the framework agreement with Nolan Davis Contracting. It is anticipated that works will commence on site during July 2006 with completion during September 2006. |
NDS Modernisation Programme 2006/07 - Schools Specialist Accommodation Programme
School |
Funding Position £ |
Summary of Works |
Comments |
Aldworth Science College Basingstoke |
NDS Modernisation 05/06 85,411 P&R Capital Repairs 05/06 14,651 School 39,423 Contingency 3,136 142,621 |
Refurbishment of CDT classrooms |
Works commenced on site during April 2006 and completion is anticipated during June 2006. |
Brune Park Community College Gosport |
NDS Modernisation 05/06 43,478 School - Devolved Capital 24,239 67,717 |
1 No. Science lab refurbishment |
This scheme was completed on site during April 2006. |
Cowplain Community School Waterlooville |
Capital Programme 05/06 43,478 School 30,979 74,457 |
1 No. Science lab refurbishment at Cowplain. |
This scheme was completed on site during April 2006. |
Fordingbridge Infant School |
Capital Programme 05/06 30,000 30,000 |
Replacement windows and doors |
It is anticipated that works will commence on site during July 06 and complete during September 06. |
Hythe Primary School |
Capital Programme 05/06 30,000 30,000 |
Replacement windows and doors |
It is anticipated that works will commence on site during July 06 and complete during September 06. |
Noadswood School Dibden Purlieu |
NDS Modernisation 05/06 86,956 School - Devolved Capital 34,629 121,585 |
2 No. Science lab refurbishment |
This scheme was completed on site during April 2006. |
Shipton Bellinger Primary School Tidworth |
NDS Modernisation 06/07 30,000 School - Devolved Capital 43,000 73,000 |
Toilet refurbishment and replacement of water pipe |
It is anticipated that works will commence on site during July 2006 and complete during September 2006. |
Test Valley School Stockbridge |
Capital Programme 06/07 43,478 F&E Budget 14,500 57,478 |
1 No. Science lab refurbishment at Test Valley |
It is proposed that this work be undertaken during summer 2006. A programme of work is to be agreed with the school. |