Archived decisions
Hampshire County Council Executive Member - Environment: South Hampshire and Resource Management 27 June 2006 Capital Programme - Progress and Amendments Report of the Director of Environment |
Item 2 |
Contact: John Buckett, ext 6599 email: [email protected]
1. Summary
1.1 The following decisions are sought:
(i) That progress on the 2005/06 capital programme be noted and that amendments set out in attached Appendices 1 and 2 be approved.
(ii) That the revised 2006/07 capital programme as set out in attached Appendices 6 to 8 be approved.
2. Reason
2.1 This decision supports the delivery of the County Council's Local Transport Plan which in turn supports Aims 1 to 5 of the Corporate Strategy (Maximising Life Opportunities, Stewardship of the Environment, Achieving Economic Prosperity, Building Strong and Safe Communities and Improving Services). Environment and Waste Management strategy programmes support Corporate Aim 2 (Stewardship of the Environment).
3. Other Options Considered and Rejected
3.1 The amendments have been produced in order to make best use the funding available in the light of changes in funding availability, scheme costs and progress. It is proposed to keep the programmes broadly in line with those previously approved and the options to remove schemes from the programme have not been put forward. However, it is proposed to keep the programme under review.
4. Conflicts of Interest Declared by the Decision Maker or Other Executive Member Consulted - None.
5. Dispensation granted by the Standards Committee - Not applicable.
6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.
Approved by: Date:
Councillor T G Knight
948Decn/JWB