Archived decisions

Hampshire County Council

Executive Member, Policy and Resources

Item 5

19 July 2006

Children's Services capital programme issues

Report of the Director of Children's Services

and County Treasurer

Contact: Bob Eardley, Strategic Planning Manager, 01962 846275. Email: [email protected]

1 Summary

1.1 The following decisions are sought:

    1. That the revised 2006/07 capital programme set out in Appendix 1 be approved together with the following specific variations:

      (a) the addition of resources totalling £22.461m;

      (b) that a major project be added to the 2006/07 capital programme for major improvements to Beaulieu Primary School, at an estimated cost of £0.408m, replacing minor works provision of £0190m for a smaller scheme;

      (c) the addition of resources totalling £0.418m for Sustainable Travel Grant allocations, funded from additional Government grant;

      (d) the addition of resources of £0.468m from the Youth Capital Fund;

      (f) the addition of resources of £0.100m to the provision for secondary school improvements for a grant allocation for specialist school status to Cove Secondary School, Farnborough.

    2. That the application for planning permission for a temporary classroom at The Vyne Community School, Basingstoke be approved until 31 August 2007.

2 Other Options considered and rejected:

    None.

3 Conflicts of Interest declared by the decision maker or other Executive Member consulted

    None

4 Dispensation granted by the Standards Committee -

    Not applicable

5 Reason(s) for the matter being dealt with if urgent -

    Not applicable

Approved by: Date:

Councillor T.K. Thornber 19 July 2006

Executive Member, Policy and Resources