Archived decisions

    Hampshire County Council

    Executive Member for Education Item

    21 July 2006

    Cove School, Farnborough

    Report by the Director of Property, Business and Regulatory Services

      How the conclusion in this report fits with the Corporate Strategy

      This scheme will impact on the delivery of all Corporate Aims, focusing most immediately on:

      Aim 1 - maximising life opportunities
      : the proposal to provide a Hearing Impaired Unit and ICT suite will have an immediate benefit for the school and local community.

      Aim 5 - improving services: all users of the proposed new facilities will benefit from these proposals.

    1

    Summary

    1.1

    This reports seeks approval to a scheme to provide replacement resourced provision for pupils with a hearing impairment, comprising of a teaching room, testing rooms and associated support rooms at Cove School, Farnborough. It is also proposed to relocate the library to provide an ICT suite for pupil and community use and to provide a corridor to link the school buildings located on either side of the courtyard. The total estimated cost of the works is £672,000, excluding fees.

    1.2

    The school is located within a residential area of Cove, off Broomhill Road. There are currently 985 pupils (aged 11-16 years) on roll. The original school dates from the 1930s and the campus now consists of a mix of traditional and system built buildings which have been added over the years.

    1.3

    The Director of Property, Business and Regulatory Services has progressed the design of the proposed additional accommodation and the purpose of this report is to outline the design proposals and seek approval to the attached design project appraisal.

    2

    Scope of the Works

    2.1

    The resourced provision will include teaching rooms, testing rooms and associated support rooms. It will occupy the length of the courtyard and will be 6m deep overall. The rooms within the resourced provision will have direct views into the quiet and secluded courtyard.

    2.2

    It is proposed to locate the library at the end of the courtyard. This will be fronted by a link corridor through the courtyard, thus improving the existing circulation through the area.

    2.3

    The existing library will be converted into an ICT suite, with easy access to the front of the school for community access.

    3

    Funding and Timing

    3.1

    The funding for the scheme (exclusive of fees) is as follows:

                        £

    Capital Programme (SAI) 340

    Capital Programme (Specialist Schools Status) 87

    School - devolved capital 193

    School - sponsorship 43

    P&R Maintenance Budget 9

                        672

    3.2

    Subject to the necessary approvals it is anticipated that tenders will be invited during July 2006, work will commence on site during November 2006 and be completed during July 2007.

    4

    Consultation with Local Member

    4.1

    Councillor Carol Leversha, the local Member for this area, has been consulted on the proposals and fully supports the scheme.

    Conclusion

    The scheme will provide resourced provision for pupils with a hearing impairment, relocated library and new ICT suite for pupil and community use.

    Recommendation

    That the Executive Member for Education advises the Executive Member for Policy and Resources that the design project appraisal for Cove School, at an estimated cost of £672,000, excluding fees, be approved.

      Section 100 D - Local Government Act 1972 - background papers

      The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

      NB the list excludes:

      1 Published works

      2 Documents which disclose exempt or confidential information as defined in the Act.

        Title Location

        Architect's plans PMIS file

        Building Profile Reports TMH

      Hampshire County Council

    Building Design Project Appraisal

      Buildings, Land and Procurement Panel

      11 July 2006

      Executive Member - Policy and Resources

      19 July 2006

      Executive Member - Education

      21 July 2006

    Project:

    Cove School, Farnborough

    Resourced provision for pupils with a hearing impairement and Library relocation/extension

    Commencement date:

    November 2006

    Completion date:

    July 2007

    Planned year of start in accordance with Capital Programme:

    2006/07

      Recommendation:

      That the building design project appraisal for the Cove School scheme be approved.

      1 Finance

    Capital Expenditure

    Current Estimate

    £'000

    Capital Programme

    £'000

    Buildings

    672

    427

    Fees

    95

    64

    Land to be purchased

    _

    _

    Total

    *767

    491

      * The means by which the difference between the Current Estimate and the Capital Programme

        allocation is to be met is shown in the table below.

    Financial Provision for Total Scheme

    Buildings

    £'000

    Fees

    £'000

    Total cost

    £'000

    1 From own Resources:

    a) Capital Programme (SAI)

    b) Capital Programme (Specialist School Status)

    340

    87

    51

    13

    391

    100

    c) School - devolved capital

    193

    23

    216

    School - sponsorship

    43

    7

    50

    2 From Other Resources:

    a) Policy and Resources Maintenance budget

    9

    1

    10

    Total

    672

    95

    767

Building Cost - Net Cost (including abnormals) = £1,410 per m2

      - Gross Cost = £1,551 per m2

Devolved Capital allocations £'000

                2005/06 88

            2006/07 92

          2007/08 94

        Total 274

Landlord funded work connected with this scheme

A contribution of £9,000, excluding fees, has been made from the Policy and Resources Maintenance Budget towards improvements to the electrical services.

Value of land already acquired for this project

      The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

      Revenue implications

    (a)

    Employees

    £'000

    (b)

    Other

    £'000

    (a+b)

    Net Current

    Expenditure

    £'000

    (c)

    Capital

    Charges

    £'000

    (a+b+c)

    Total Net

    Expenditure

    £'000

    Revenue

    Implications

    Additional+

    /Reductions

    Nil

    Nil

    Nil

    40

    40

    Unit cost (£)

    (e.g. per place)

    -

    -

    -

    -

    -

    % variation to

    Committee's

    budget

    -

    -

    Number of

    additional

    Staff (fte)

    -

    -

      * The overall level of the revenue budget for funding schools will (from April 2006) be prescribed by central government, and capital projects have no bearing on the level of this budget. Therefore, this proposed project will have no bearing on the overall level of the Children's Services budget, extra costs and savings being met from the same overall schools' funding level.

      Energy costs

      The estimated annual energy consumption for the new accommodation will meet that required by current Building Regulations. It is anticipated that the increase in fuel cost for the school will be in the order of £2,008 per year (£5.40 for each m² of new accommodation). The additional CO² consumption will be 15.6 tonnes per year.

2 Details of site and existing infrastructure

        Location/adjoining land and buildings

        Cove School is located in a residential area of Cove and is bounded by housing.

        Netball courts/playing fields are located to the north of the site, with housing beyond.

        Area including comparison with local/national standards

        The total site area is 15.14 acres (6.12 hectares). The DfES guideline for a school of this size is between 17.14 and 18.63 acres (6.94 to 7.54 hectares).

        Access

        The main vehicular and pedestrian accesses to the school are from St John's Road, to the south of the site. The Contractor's access will also be from St John's Road. Once within the school boundaries, pupils and staff will be clearly separated from construction traffic and activities. Deliveries and movement of plant will be restricted during the school day to ensure the safety of all those involved.

        Existing buildings and temporary buildings

        The school campus is mainly of traditional build, dating from the 1930s, with some Scola system blocks. There are currently two temporary buildings on site. No further temporary buildings are required as part of the proposed scheme.

        Results of trial boreholes

        Trial boreholes were carried out prior to the construction of a science block infill, in close proximity to the proposed building, completed in 1997. These trial pits showed the soil and subsoil to be medium dense clayey fine sand. The current foundation design has been based on these results.

        Mains services position

        The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation. The main distribution board for the courtyard building will be upgraded as part of the works.

      3 Scope of the Project

        Type of project, layout and facilities provided

        The proposed scheme provides resourced provision for pupils with a hearing impairment, new library facility and new ICT suite within the refurbished original library building.

        The following accommodation is provided:

        Resourced provision

        · main group room

        · small group room

        · audiology room

        · resource office

        · associated storage space

        · entrance lobbies

        Relocated spaces

        · main library spaces

        · interview room

        · deputy Headteacher's room

        ICT Suite

        · main room

        · mezzanine area accessed via spiral staircase

        Places provided

        The school will continue to provide 1,000 spaces with 10 places in the resourced provision.

      4 The Proposed Building

        Type of construction, finish and appearance

        The new build will be of steel-frame construction with facing brickwork, aluminium glazing and monopitch standing seam metal roof. Internal construction will be primarily of plastered block walls with some acoustic plasterboard partitions. The resourced provision area will be treated to achieve optimum acoustic performance.

        Accessible facilities

        The scheme has been designed with level thresholds throughout.

        Heating and ventilation systems

        The new-build areas will be heated by hot water radiators connected to the existing heating system. The library formed within the relocated space will be heated by radiators and mechanically ventilated.

        The IT spaces on the ground and first floors will be provided with split heat pumps to provide cooling and heating. Natural ventilation will be provided.

        Fire risk assessment

        In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.

        Health and safety

        A designer's risk assessment and a design health and safety plan, in accordance with Regulation 15 of the Construction Design and Management Regulations 1994, have been undertaken for the proposed scheme

      5 External Works

        Car parking

        No changes will be made to the existing car parking arrangements.

        Landscape proposals

        The proposed scheme seeks to improve and enhance the existing courtyard area. Some existing trees within the courtyard will be removed to allow for the development.

        Situation on site and environmental impact

        The proposed extension has been designed to minimise impact on the environment and where possible to use sustainable materials in construction. Building materials have been chosen to complement the existing building in addition to their longevity and maintenance-free characteristics.

      6 Planning

        A detailed planning application was submitted during April 2006.

      7 Building management

        Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.

      8 Furniture and equipment

        No implications.

      9 Professional resources

        Architectural Services } Property, Business and Regulatory

        Quantity Surveying } Property, Business and Regulatory

        Electrical and Mechanical Engineering } Property, Business and Regulatory

        Structural Engineering } WSP

      10 Consultations

        The following have been consulted during the development of the project: Headteacher and Governors of the school, Children's Services, Environment Department, Access Officer, local County Councillor.