Hampshire County Council Executive Member - Environment 12 September 2006 Project Appraisal: Sandhurst Road, Yateley - Pedestrian Footway Report of the Director of Environment |
Item 13 |
Contact: Simon Found, ext 6593 email: [email protected]
1. Summary
1.1 The following decision is sought:
That the Project Appraisal for the implementation of a hard-surfaced pedestrian footway along Sandhurst Road, Yateley, from the junction of Weybridge Mead to the Bracknell Forest Borough Council border, to be externally funded at an estimated cost of £114,000, be approved.
2. Reason
2.1 This decision supports Aims 2 and 4 (Stewardship of the Environment and Building Strong and Safe Communities) of the Corporate Strategy by providing sustainable alternatives of transport and by providing safer community facilities for everyone.
3. Other Options Considered and Rejected
3.1 The option to do nothing was considered, but this was rejected due to the need to improve safety and accessibility for the route's users.
4. Conflicts of Interest Declared by the Decision Maker or other Executive Member Consulted - None.
5. Dispensation granted by the Standards Committee - Not applicable.
6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.
Approved by: Date:
Councillor M J Kendal
999Decn/SF