Summary

1.1

The following decision is sought:

That the Executive Member for Education advises the Executive Member for Policy and Resources that the design project appraisal for extension and relocation/refurbishment works, at an estimated cost of up to £556,000, excluding fees, be approved.

2

Reason

2.1

To provide permanent, purpose-built teaching accommodation, accessible front entrance, head teacher's office, relocated reception and administrative facilities and an ICT suite within an existing space. The scheme facilitates the removal from site of a temporary building which is currently used for teaching purposes.

2.2

This decision reflects the priorities in the Corporate Strategy by replacing a temporary building with purpose-built accommodation that will enhance the quality of place for all users of Burghclere Primary School.

3

Other options considered and rejected

3.1

The need for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or other Executive Member consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

...................

Councillor D Kirk

Executive Member for Education