Archived decisions

Hampshire County Council

Executive Member for Education

12 October 2006

Self-funded and Partially Self-funded schemes

Report of the Director of Property, Business and Regulatory Services

Contact: Steve Clow Ext: 7858 E-mail: [email protected]

1. Introduction

1.1 Self-funded and partially self-funded schemes are developed as a result of a request from the School Governors to provide additional accommodation or facilities, which can be funded from their budget. The Director of Property, Business and Regulatory Services in each case develops designs and specifications to current County Council standards in accordance with the requirements of the Building Regulations and the space guidelines of the DfES notwithstanding the fact that these schemes are not always about satisfying basic need. It should be noted that contracts will not be let without confirmation that funding is available and the County Treasurer and the Director of Children's Services will be consulted regarding the schools having sufficient funding to carry out the works outlined in this project.

1.2 The schemes within this report generally reflect the priorities in the Corporate Strategy by maximising the safety and accessibility of all users of the premises and enhancing the quality of place.

2. The Schemes

2.1 The schemes have been developed in consultation with the Headteacher and Governors of the schools. The attached table summarises the current position in relation to each of these schemes, gives details of the funding, and a brief description of the scheme. Each of the schemes in this report is valued between £43,000 and £216,000 (exclusive of fees).

Recommendation

1. That the projects being reported in the Self-funded and Partially Self funded schemes report be approved.

LINK(S) TO CORPORATE STRATEGY

Yes

No

Hampshire safer and more secure for all

_

Maximising well-being

_

Enhancing our quality of place

_

This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because:

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report and attached appraisal.

NB the list excludes:

1. Published works

2. Documents which disclose exempt or confidential information as defined in the Act.

TITLE FILE

Contract Reconciliation Statements Self-funded

Confirmation of School funding forms Schemes - TMH.

Architects Plans

Planning Statements

School

Funding Position £

Summary of Works

Comments

Fryern Infant School

Chandler's Ford

School - devolved capital 66,626

Internal alterations to provide space for playgroup.

It is anticipated that the scheme will commence on site during September 2006 with completion during November 2006.

St Alban's CE Primary School

School - devolved capital 90,000

Office extension

It is proposed to carry out these works during December 2006.