Summary

1.1

The following decision is sought:

That the Executive Member for Education approves the design project appraisal for a two-classroom extension, at an estimated cost of up to £394,000, excluding fees.

2

Reason

2.1

To provide two permanent, purpose-built classrooms for use as music and IT spaces, thus facilitating the removal from site of a double temporary building which is in very poor condition.

2.2

The replacement of a temporary building with purpose-built accommodation will enhance the quality of place for all users of Crofton Hammond Junior School.

3

Other options considered and rejected

3.1

The need for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or other Executive Member consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

...................

Councillor D Kirk

Executive Member for Education