Archived decisions

Hampshire County Council

Executive Member for Education Item

15 December 2006

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

 

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.

2. Completed Schemes

2.1 Since the October 2006 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

    SCHOOL COMPLETION DATE

    Waterside Primary School August 2006

    Minstead Rural Study Centre October 2006

    Newtown Soberton Infant School October 2006

    Nightingale Primary School October 2006

3. Additional Works and Funding Added Post Contract

3.1 The following schemes have had further funding added to the contract for specific additional works.

3.2 Portchester Community School

      An internal alterations scheme at the above school has recently had additional Policy and Resources funding of £138,300, excluding fees, added to the contract value. This funding will enable landlord repairs to be undertaken during the existing refurbishment contract, to include re-cladding, flat roof and window replacements and chimney repairs. Work commenced on site during July 2006 and was due for completion during November 2006, however, due to the additional works and delays by the Lift contractors, work will now complete during late December 2006.

3.3 Rowner Youth Service

      A scheme to provide a new Youth Facility has recently received additional funding of £123,530, excluding fees, from the Area Investment Framework (AIF). The additional funding will allow for the core activity space to be extended by 50m2. This will support additional use of the Centre during the day and evening and expand its community use. Work commenced on site during May 2006 and was due for completion during November 2006, however, due to the additional works the contract will now complete during March 2007.

3.4 Waterside Primary School

      The major remodelling and refurbishment scheme at the above school was completed during August 2006. Additional funding of £9,800 was added by the school for stage lighting; £24,281 has come from the Policy and Resources NDS Condition Fund - 2006/07 for additional windows; £1,000 from the Hampshire Catering Fund for new flooring.

4. Additional Works and Funding added at Pre Contract Stage

4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Education and Policy and Resources.

4.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

5. Current Position

5.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.

5.2 Woolton Hill Junior School

      A scheme to provide an extension to the school library and a hall store commenced on site during July 2006 and was due for completion during November 2006, however, due to the late delivery of steelwork and inclement weather, the work will now complete one month late in December 2006.

Recommendations

1. That the additional works and funding for schemes at Portchester Community School, Rowner Youth Service and Waterside Primary School be approved.

LINK(S) TO CORPORATE STRATEGY

Yes

No

Hampshire safer and more secure for all

_

Maximising well-being

_

Enhancing our quality of place

_

This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because:

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

Project Appraisal

I/PB&R/Committees/MajorMinorSelf-Funded2006/December/MajorProjectsStatusReport

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Beaulieu Village Primary School

Contract Formation

Jan 07

Jul 07

411,380

Capital Programme 06/07 323,065

School devolved capital 33,315

P&R NDS Condition 55,000

411,380

Bridgemary Community School, Gosport

- new Exercise Space

On site

Aug 06

Feb 07

* 303,448

School 303,448

Burghclere Primary School

- extension and refurbishment

Design

Feb 07

Sep 07

534,000

Capital Programme 06/07 443,000

School 91,000

534,000

Costello Technology College, Basingstoke

- replacement maths / technology teaching block

On site

Nov 05

Feb 07

* 5,271,845

P&R Fire Re'statem't 05/06 4,870,434

Education Capital 05/06 250,000

P&R NDS Condition 05/06 88,674

School 59,137

P&R 3,600

5,271,845

Cove School, Farnborough

teaching room, testing room and support rooms for pupils with hearing impairment.

On site

Oct 06

Jun 07

* 669,482

SAI 06/07 337,069

School 193, 103

Specialist School funding 129, 310

P&R Capital Repairs 06/07 10,000

669,482

Cowplain Community School, Waterlooville

- floodlit Synthetic Turf Pitch (STP) and Multi Use Games Area (MUGA)

Contract Formation

Jan 07

Jun 07

543,381

Ed Capital 05/06 NOF 147,740

Capital Programme 06/07 40,000

Football Foundation 319,177

School 34,464

543,381

Crofton Hammond Junior School, Fareham

- classroom extension

Design

Mar 07

Sep 07

394,000

Capital Programme 06/07 345,000

School 49,000

394,000

Curdridge Primary School,

two classroom, group / special needs room and library extension

On site

Aug 06

Mar 07

* 711,779

Cap Prog. NDS Mod 06/07 651,787

School 45,000

P&R NDS Condition 05/06 14,992

711,779

Fernhill School and Language College, Farnborough

- refurbishment of CDT accommodation

Design

Apr 07

Aug 07

275,000

Capital Programme 06/07 216,000

School 59,000

275,000

Greatham Primary School, Liss

    - provide permanent teaching accommodation to replace the temporary building on site.

On site

Nov 06

Sep 07

* 679,988

Capital Programme 06/07 639,988

School 40,000

679,988

Hamble Community College

- floodlit tennis courts, courtyard improvements & flood relief works

Flood relief works:

Complete

Courtyard:

Tender Analysis

Sept 06

Dec 06

Nov 06

Feb 07

* 70,000

60,000

P&R Capital Prog 05/06 70,000

Hamble College 45, 000

P&R External Works 06/07 15,000

60,000

Hardley School and Sixth Form, Holbury

- four court sports hall

On site

Aug 06

Apr 07

* 2,130,886

Children's Services

NDS Mod 06/07 1,913,886

School 217,000

2,130,886

Henry Tyndale School, Farnborough

- new Post-16 provision and entry enhancements

Design

Apr 07

Dec 07

658,000

Capital Programme 06/07 486,000

School 172,000

658,000

Hollywater School, Bordon

- new special school

On site

May 05

Dec 06

* 6,127,722

Edu Cap / TCF 05/06 4,887,472

P&R Capital Repairs 05/06 629,000

P&R Capital Receipt 572,000

School 39,250

6,127,722

John Hunt of Everest Community School, Basingstoke

- New School and Youth facility

Enabling -

Complete

On site

Aug 05

Jan 06

Nov 05

Apr 07

* 1,106,416

* 22,766,137

Capital Receipts 13,543,659

Developer's Contribution 2,383,824

B&D Borough Council 2,008,615

County Council 4,702,654

School 127,385

22,766,137

Micheldever CE Primary School

- Hall and classroom extension

On site

Jul 06

Nov 07

* 1,898,357

Cap Prog NDS Mod 06/07 1,686,460

School 131,897

P&R Cap Repairs 06/07 10,000

P&R NDS Condition 05/06 30,000

P&R NDS Condition 06/07 40,000

1,898,357

Mill Hill Early Years Centre, Waterlooville

- refurbishment works to the administration area, new secure lobby and extension to reception area

On site

Sept 06

Feb 07

* 252,144

Children's Cap Prog 06/07 224,064

Mill Hill Early Years Centre 28,080

252,144

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

Complete

Dec 05

Oct 06

* 1,245,600

Education Capital 05/06 519,000

Temp Classroom Hire 05/06 28,000

New Opportunities Fund 487,000

Study Centre 100,000

New Forest District Council 26,000

P&R Landlords contribution 68,000

P&R External Works 15,000

P&R Capital 2,600

1,245,600

Newtown Soberton Infant School

- new Hall and internal adaptations to create a Nursery Unit

Complete

Mar 06

Oct 06

* 546,990

NDS Modernisation 05/06 438,000

School 103,000

Education FF&E 05/06 5,990

546,990

Nightingale Primary School, Eastleigh

- MUGA

Complete

Jul 06

Oct 06

* 74,000

Education capital programme 74,000

Oak Lodge School, Dibden Purlieu

- drama room and music practice room and a sculpture room

On site

Jul 06

Dec 06

* 288,149

School 288,149

Oak Meadow Early Years Centre, Fareham

- reconfigure existing space to create a self contained nursery unit, new garden, community room, parents/children's room, store and kitchen

Phase I

Complete

Phase II

On site

Jul 06

Sep 06

Sep 06

Dec 06

Phase I

    *154,000

Phase II

*249,883

Phase I

Children's Services

Capital Programme 06/07 122,000

School 32,000

154,000

Phase II

Children's Services

Capital Programme 06/07 249,883

Pinewood School, Farnborough

- new one form entry infant school with speech, language and communication needs provision

On site

Jul 06

Jul 07

* 3,220,103

Children's Services

Capital Programme 06/07 3,107,000

Rushmoor BC 43,103

School devolved capital 70,000

3,220,103

Portchester Community School, Fareham

- improved fire evacuation; refurbished science labs; new performance space; improved accessibility and car parking

On site

Jul 06

Dec 06

      * 696,624

Add 138,300

834,924

Cap Prog - SAI 05/06 257,746

Cap Prog NDS Mod 05/06 86,956

Cap Prog NDS Mod 06/07 69,565

Specialist Schools allocation 86,956

School 151,657

P&R Ext Works 05/06 43,744

P&R L'lord's Cap Repairs 06/07 60,000

P&R Structural Repairs 06/07 8,300

P&R NDS Condition 06/07 70,000

834,924

Rowner Youth Services, Gosport

- new Youth Facility

On site

May 06

Mar 07

    * 345,000

Add 123,530

    468,530

Children's Services

Capital Programme 06/07 87,000

P&R Capital Prog. 06/07 129,000

Single Regeneration Board 129,000

Area Investment Framework 123,530

468,530

Sundridge BESD School

- new BESD Secondary School

On site

Aug 06

Aug 07

* 4, 822,919

Education Capital 05/06 718,260

TCF 3,082,609

Rachel Madocks receipt 677,391

Future land sales 344,659

4,822,919

Swanwick Lodge Secure Unit

- demolish redundant buildings and refurbish the Hamble block for new training/family counselling area, laundry suite, office and sleep in staff accommodation

Tender Analysis

Jan 07

Jun 07

766,000

Children's Services

Capital Programme 766,000

Trosnant Infant and Junior Schools, Leigh Park

- Trospac full day-care provision

On site

Jul 06

Dec 06

    * 601,000

    add 3,000

604,000

Education Capital 05/06 253,000

Sure Start (Children's Centre) 87,000

School 3,000

DfES general Sure Start 261,000

604,000

Waterside Primary School, Hythe

- remodel and refurbish existing school; construct classroom block and early years unit

Complete

Nov 05

Aug 06

    * 1,916,065

add 35,520

      1,951,585

Education Capital 05/06 1,539,462

School 137,050

P&R Capital Repairs 05/06 25,246

P&R NDS Condition 05/06 224,107

P&R NDS Condition 06/07 24,281

Hampshire Catering Fund 1,000

Re-directed funds 439

1,951,585

West Tytherley C of E Primary, Salisbury

- classroom extension to replace temporary accommodation

On site

Apr 06

Jan 07

* 897, 500

Education Capital 05/06 857,500

School 40,000

897,500

Wildern School, Hedge End

- new Learning Centre

On site

Jul 06

Jan 07

* 614,987

School 514,987

P&R Capital Repairs 06/07 100,000

614,987

Woodlands Education Centre, Havant

- replacement Woodlands Education Centre.

On site

Dec 06

Nov 07

* 4,726,995

Capital Programme 06/07 4,726,995

Woolton Hill Junior School

- extension to library and hall store

On site

Jul 06

Dec 06

* 233,496

Education Capital 05/06 43,103

School 118,965

P&R Capital Repairs 06/07 71,428

233,496

Wyvern Technology College, Fair Oak

- improve vehicular and pedestrian external circulation, accessibility and car parking arrangements

On site

Jul 06

Dec 06

* 532,599

Wyvern Technology College 109,483

Fair Oak Infant School 15,000

Fair Oak Junior School 11,000

Cap Prog Minor Works 06/07 133,620

Cap Prog SAI 05/06 68,000

Environment Capital 06/07 43,103

P&R NDS Condition 05/06 15,000

P&R 06/07 138,393

532,599

                      Appendix 2

Other Schemes in the Children's Services Capital Programme

The following schemes are included in the Education 2005/06 and Children's Services 2006/07 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member for Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

Burnham Copse Junior

TBA

Cadland Primary

TBA

Dowd's Farm Primary

3,845

Freegrounds Infant

517

New Whiteley Primary

1,240

King's Copse Primary

3,728

Shamblehurst Primary

517

SECONDARY

Wildern School

216

SPECIAL

Baycroft School

261

EDUCATION OTHER THAN AT SCHOOLS

Basingstoke School Plus

2,391

NDS MODERNISATION

Burghclere Primary

443

Stanmore Primary 05/06

226

The Bridge Centre 05/06

864

TOTAL

14,248