Archived decisions

Hampshire County Council

Executive Member - Environment

16 January 2007

Project Appraisal: Normandy Way, Marchwood - Pedestrian Facilities

Report of the Director of Environment

Item 5

Contact: Barry Armstrong, ext 5175 email: [email protected]

1. Summary

1.1 The following decision is sought:

    That the Project Appraisal for the construction of a new footway and uncontrolled pedestrian crossing point on Normandy Way, Marchwood, to be externally funded at an estimated cost of £65,000, be approved.

2. Reason

2.1 This scheme will improve the safety of pedestrians that reside either side of Normandy Way, Marchwood wishing to gain access to Admiralty Quay and Old Magazine Close, Marchwood.

3. Other Options Considered and Rejected

3.1 Due to the alignment of the carriageway there are no other options that will provide a safe pedestrian footway route from Marchwood village centre and the recent housing development at Admiralty Quay.

4. Conflicts of Interest Declared by the Decision Maker or Other Executive Member Consulted - None.

5. Dispensation granted by the Standards Committee - None.

6. Reason(s) for the Matter being dealt with if Urgent - None.

Approved by: Date:

Councillor M J Kendal

Executive Member for Environment

977Decn/BA