Hampshire County Council Executive Member for Education 18 January 2007 Minor Projects - Progress Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1. Summary
1.1 The purpose of this report is to provide an update of the progress made in implementing those schemes in the Children's Services Capital Programme with a value of between £43,000 and £216,000 (exclusive of fees).
1.2 The schemes within this report generally reflect the priorities in the Corporate Strategy by maximising the safety and accessibility of all users of the premises and enhancing the quality of place.
2. Current Position
2.1 The attached tables summarise the current position in relation to schemes funded by the Children's Service 2006/07 and 2007/08 Capital Programme including Minor Works, Security Funding, Schools Access Initiative (SAI), Specialist College Status funding, NDS Modernisation and Staff Workplaces budget. The tables provide details of the funding, a brief description of the works and a summary of the current position.
3. Minor Works Capital Programme 2006/07
3.1 Horndean Technology College
An allocation of £146,552, excluding fees, has been allocated from the Children's Services Capital Programme 2006/07. The college have made a contribution of £68,103, excluding fees, giving a total of £214,655 for the proposed refurbishment scheme.
An existing internal area is to be refurbished to form a vocational training facility. It is anticipated that the works will commence on site during March 2007 and be completed during September 2007.
4. NDS Modernisation 2007/08
4.1 Calthorpe Park School, Fleet
An allocation of £140,000, excluding fees, has been made in the Education Capital Programme (NDS Modernisation 07/08) which together with a contribution from the school of £50,000 devolved capital, will fund works to refurbish two science laboratories.
It is proposed to procure the scheme with an SME framework contractor and works are anticipated to commence on site during July 2007 and complete during September 2007.
4.2 Thornden Community School, Chandler's Ford
An allocation of £70,000, excluding fees, has been made in the Education Capital Programme (NDS Modernisation 07/08) which together with a contribution from the school of £78,000, excluding fees, of devolved capital will fund works to refurbish two science laboratories.
It is proposed to procure the scheme with an SME framework contractor and works are anticipated to commence on site during June 2007 and complete during August 2007.
Recommendation
1. That the changes to the minor works programme be approved.
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ |
|
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information File, PBRS
Minor Works Capital Programme 2006/07 ( including carry forwards)
School |
Funding Position £ |
Summary of works |
Comments |
Froxfield CE Infant School Petersfield |
Capital Programme 06/07 4,310 School - devolved capital 131,897 136,207 |
Erection of Homelodge building. |
Tenders were returned over budget and a new programme/funding issues are currently being discussed with the school. |
Horndean Technology College |
Capital Programme 06/07 146,552 School - devolved capital 68,103 214,655 |
Internal refurbishment to existing area to form vocational training facilities |
It is anticipated that the scheme will commence on site during March 2007 and be completed during September 2007. |
South View Junior School Basingstoke |
Capital Programme 06/07 30,000 School - devolved capital 35,000 65,000 |
Extension to library |
Some re-design work has been undertaken and it is now anticipated that the works will be complete during January 2007. |
Staunton Park Community School Havant |
Capital Programme 06/07 18,000 School 188,450 School 6,000 212,450 |
Construction of 4/5 floodlit tennis courts. |
The scheme is currently on site, with completion anticipated during December 2006. |
West Meon Primary School Petersfield |
Capital Programme 06/07 146,400 School - Devolved Capital 40,000 186,400 |
First floor extension over existing admin office to form additional classroom to free up existing area for use as main hall. |
This scheme is to be negotiated with a preferred contractor. The scheme now has Listed Building consent and it is anticipated that works will commence on site during March 2007 and complete during September 2007. |
Various schools in the Basingstoke area |
Landlord's Fire Precaution Capital Programme 06/07 25,000 (£2,500 from each of up to 17 schools) 42,500 92,500 |
Provision of secured bin storage |
It is anticipated that the bins will be installed at up to 17 schools between January 2007 and April 2007. |
Security Funding 2006/07 (*including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
Yateley Secondary School |
Capital Programme 06/07 SEED Challenge 103,500 |
Security improvements to sports hall reception area |
These works are to be negotiated with Nolan Davis. It is now anticipated that work will commence on site during January 2007 and complete during March 2007. |
Staff Workplaces 2006/07 (including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
Burley Primary School |
Staff Workplaces Remodelling Budget 25,800 Capital Programme 06/07 (F&E budget) 1,395 School - Devolved Capital 54,255 81,450 |
Extension to provide additional office accommodation. An additional contribution from the F&E budget has been made towards the cost of data transfer to the temporary office |
The scheme is currently on site and it is anticipated the completion will take place during January 2007. |
Castle Hill Junior School Basingstoke |
Capital Programme 06/07 30,000 P&R Landlord's 30,000 School - Devolved Capital 35,000 95,000 |
Extension to staff room to provide additional space for staff. |
The school have requested some redesign and a new programme is to be agreed. It is anticipated that tenders will be invited during December 2006. |
Harrison Primary School Fareham |
School - devolved capital 179,000 Capital Programme 06/07 (Staff Workforce) 13,000 Capital Programme 06/07 (SAI) 13,000 School Security budget 5,000 Policy & Resources Minor Works budget 5,000 Policy & Resources Landlord's budget 6,000 221,000 |
Reconfiguration of existing toilet space/administrative area to provide more secure environment. External works to raise level of existing courtyard area for access by early years pupils. |
It is anticipated that tenders will be sought during October 2006, that works will commence on site during December 2006 and complete during May 2007. |
Lee-on-Solent Infant School |
School - devolved capital 72,500 Capital Programme 06/07 (Staff Workforce) 7,000 79,500 |
Extension and internal adaptation of staff workspace area. |
It is anticipated that the works will commence on site during January 2007 and complete during April 2007. |
Otterbourne Primary School Winchester |
Block Vote Staff Workforce 43,478 School - Devolved Capital 75,862 |
Internal adaptations to improve staff facilities. |
Due to an error on the lowest tender, approval is now being sought to negotiate the contract with a view to commencing works on site in February 2007. |
Westfields Junior School Yateley |
Capital Programme 06/07 (Staff Workforce) 26,000 School - Devolved Capital 65,000 |
Staffroom extension |
To be procured through framework contract. It is anticipated that works will start on site during January 2007 and complete during April 2007. |
Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2006/07 (including carry forwards)
School |
Funding Position £ |
Summary of Works |
Comments |
Eling infant School |
Capital Programme 06/07 SAI 50,000 |
Provision of hygiene room within existing area |
Work commenced on site during December 2006 and completion is anticipated during March 2007. |
Kings School Winchester |
Capital Programme 06/07 145,000 Capital Programme 06/07 56,150 201,150 |
Internal lift access. |
These works are now complete. |
Portchester Community School |
Capital Programme 06/07 (SAI) 190,000 |
Installation of second external fire escape lift |
The scheme is currently under review and additional fire precaution works are being considered. |
Wildern Secondary School Hedge End |
Capital Programme 06/07 58,522 |
Alarm system for Hearing Impaired, modifications to WC's and level access. |
The level access works and alarm system are now complete. Completion for the other works is now anticipated during March 2007. |
Specialist School College Status Allocations 2006/07
School |
Funding Position £ |
Summary of Works |
Comments |
Crestwood College for Business and Enterprise Eastleigh |
Capital Programme 05/06 105,000 School funding tbc |
Specialist school allocation |
On hold. An alternative scheme is currently being discussed with the school. |
NDS Modernisation Programme 2006/07 - Schools Specialist Accommodation Programme
School |
Funding Position £ |
Summary of Works |
Comments |
Brune Park Secondary School Gosport |
NDS Modernisation 07/08 80,000 School - Devolved Capital 30,000 110,000 |
Refurbishment of food technology area |
It is anticipated that works will commence on site during April 2007 and complete during June 2007. |
Calthorpe Park School, Fleet |
NDS Modernisation 07/08 140,000 School - Devolved Capital 50,000 190,000 |
Refurbishment of two science laboratories |
The scheme will be procured with an SME framework contractor. It is anticipated that works will commence on site during July 2007 and be completed during September 2007. |
Connaught School (The) Aldershot |
NDS Modernisation 06/07 80,000 School - Devolved Capital 25,000 105,000 |
Refurbishment of food technology area |
To be procured through framework contractor. It is anticipated that works will commence on site during July 2007 and complete during September 2007. |
Quilley School of Engineering Eastleigh |
NDS Modernisation 06/07 70,000 School - Devolved Capital 25,000 95,000 |
Refurbishment of food technology area |
It is anticipated that the works will be carried out during April 2007. |
Shipton Bellinger Primary School Tidworth
|
School - Devolved Capital 55,000 |
Toilet refurbishment, provision of accessible wc. (The scheme to replace water pipes will now be carried out as a separate contract.) |
Due to the school's requirement for the works to be carried out during a holiday period, it is now anticipated that the scheme will be on site during the summer holiday of 2007. |
Thornden Community School Chandler's Ford |
NDS Modernisation 07/08 70,000 School - devolved capital 78,000 148,000 |
Refurbishment of two science labs |
The scheme will be procured with an SME framework contractor. It is anticipated that the works will commence on site during June 2007 and complete during August 2007. |