Archived decisions
Hampshire County Council Buildings, Land and Procurement Panel Item 23 January 2007 Romsey Primary School
Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ | |
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
Title Location
Architect's plans PMIS file
Building Profile Reports TMH
Hampshire County Council
Building Design Project Appraisal |
Executive Member for Education
18 January 2007
Buildings, Land and Procurement Panel
23 January 2007
Executive Member for Policy and Resources
25 January 2007
Project: |
Romsey Primary School | |
Extension and remodelling to provide a one-form entry Primary School and a new Children's Centre | ||
Commencement date: |
June 2007 | |
Completion date: |
April 2008 | |
Planned year of start in accordance with Capital Programme: |
2007/08 | |
Recommendation:
That the building design project appraisal for the Romsey Primary School scheme
be approved.
1 Finance
Capital Expenditure |
Current Estimate £'000 |
Capital Programme £'000 |
Buildings |
2,852 |
2,730 |
Fees |
448 |
437 |
Land to be purchased |
_ |
_ |
Total |
*3,300 |
3,167 |
* The means by which the difference between the Current Estimate and the Capital Programme
allocation is to be met is shown in the table below.
Financial Provision for Total Scheme |
Buildings £'000 |
Fees £'000 |
Total cost £'000 |
1 From own Resources: |
|||
a) Capital Programme (as above) |
2,730 |
437 |
3,167 |
b) School - devolved capital |
122 |
11 |
133 |
Total |
2,852 |
448 |
3,300 |
Building Cost - Net Cost = £1,880 per m2 (including abnormals)
- Gross Cost = £2,715 per m2
Devolved Capital allocations £'000
2003/04 6,473
2004/05 19,230
2005/06 22,651
2006/07 49,921
2007/08 34,725
Total 133,000
Landlord funded work connected with this scheme
There are no landlord funded works associated with this scheme.
Value of land already acquired for this project
The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.
Revenue implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) *Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
70 |
0 |
- |
173 |
243 |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
The overall level of the revenue budget for funding schools will (from April 2006) be prescribed by central government, and capital projects have no bearing on the level of this budget. Therefore, this proposed project will have no bearing on the overall level of the Children's Services budget, extra costs and savings being met from the same overall schools' funding level.
Energy costs
The existing school building currently costs £7,257 per year (£6.6 per m2), generating 42 tonnes of CO2 per year. After the proposed improvement to this building, these expected figures will be in the order of £6,850 per year (£6.35 per m2), generating 38 tonnes of CO2 per year.
The new extension energy use, based on the expected generation of the wind generator and the use of the ground source heat pump for heating, will be £2,000 per year (£3.30 per m2), 11.5 tonnes of CO2. This is a saving of £1,300 per year and 6.5 tonnes of CO2, compared to the use of traditional technologies.
Whole Life costs
The development of the project has included an analysis of costs over the whole life-cycle of the building. A Whole Life Cost plan has been prepared for the project and is consistent with similar projects carried out by the County Council.
2 Details of site and existing infrastructure
Location/adjoining land and buildings
Romsey Junior School is located in a residential area at Mercer Way, Romsey. The site is surrounded by housing, with school playing fields to the south and west.
Area including comparison with local/national standards
The total site area is 6.98 acres (2.83 hectares). The DfES guideline for a school of this size is 2.73 acres (1.105 hectares).
Access
The existing vehicular and pedestrian access into the site from Mercer Way is to be retained but restricted to staff and service vehicles only. Staff parking has been re-designated in line with County standards. Congestion will be relieved by additional pedestrian entrances on all four sides of the site.
For the duration of the works, the contractor will access the site from Mercer Way.
Existing buildings and temporary buildings
The main school building is of SCOLA 3 system construction, dating from the 1970s. A library infill extension of traditional construction was added in 1994. There are no temporary buildings on the Junior School site.
During the contract period, it will be necessary for the pupils of the Junior School to be temporarily integrated into the Infant School accommodation. Three temporary buildings will be erected on the Infant School site to provide the necessary accommodation to facilitate the temporary move. These will be removed on completion of the scheme.
Results of trial boreholes
The ground conditions are topsoil on slightly gravely clay to 1.2-1.6m below existing ground level. Below this is generally clayey sandy gravel which has fairly good drainage characteristics.
The new ground floor will be a proprietary beam and block system designed to span between mass concrete foundations.
Mains services position
The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.
3 Scope of the Project
Type of project, layout and facilities provided
The proposed extension is located to the south of the existing school building, forming an external courtyard area at the heart of the school. The following accommodation is provided:
· Reception foyer
· Manager's office
· 2 meeting rooms
· Therapy room
· Crèche with associated toilet/storage
· Community room with lobby and toilet area
· 3 classrooms
· Storage/play/toilet areas
· Pre-school space
· Storage/toilet areas
Places provided
On completion of the project there will be 210 places for pupils aged 4-11 years of age, together with a children's centre as well as provision for a 30 place pre-school.
4 The Proposed Building
Type of construction, finish and appearance
The single-storey building will be of brick/block construction with aluminium glazing to maximise daylight into the teaching spaces. The roof will have a high-performance covering. The bricks have been chosen to complement the existing buildings and areas of render will be used to contrast with the window frames. The courtyard will be clad in timber boarding where it can be protected easily.
Impact Assessment
The proposed extension has been designed with level access throughout.
Assessment of the Race Relations (Amendment) Act has been considered in the development of this proposal. No adverse impact has been identified in terms of race, creed or gender.
Heating and ventilation systems
The new accommodation will be heated by underfloor heating served by a ground-source heat pump and will be naturally ventilated wherever possible.
Fire risk assessment
In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.
Health and safety
A designer's risk assessment and a design health and safety plan, in accordance with Regulation 15 of the Construction Design and Management Regulations 1994, have been undertaken for the proposed scheme
5 External Works
Car parking
The existing car parking provision will be reconfigured in line with the county standard.
Landscape proposals
The principal aim of the landscape design is to segregate the public front of the building entrance space from the rest of the learning/play landscape in order to reduce the possibility of unauthorised access to the western side of the site, as well as separating vehicular traffic from play areas. This has been achieved by:
· Creating a separate fenced area for the early years unit which effectively separates the school's main vehicular/pedestrian entrance from the playing fields.
· Fencing between the existing building and the site boundary to separate the vehicular routes from the back playground, thus increasing child safety.
· Fencing between the early years unit and existing school, creating a dual-purpose formal entrance courtyard as well as a supervised play/teaching space.
Situation on site and environmental impact
The proposed extension is single-storey and the site is bounded by tall trees and hedges, thus reducing any impact on surrounding housing. It is proposed to include a wind turbine in the scheme (subject to a separate planning application) which will be mounted in the playing field close to the buildings in the centre of the site. It is anticipated that this will generate savings for the school's energy bill, reduce the school's carbon footprint and also provide an important learning resource for pupils.
6 Planning
The original planning application proposed a new vehicular access from Cupernham Lane, however because of significant local objections this has been withdrawn and a revised planning application detailing access from Mercer Way was resubmitted during December 2006. The wind turbine was submitted as a separate application which it is expected to be approved under delegated powers.
7 Building management
Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.
8 Furniture and equipment
The funding for the provision of furniture and equipment will be made available from the Block Vote in the Children's Services Capital Programme.
9 Professional resources
Architectural Services } Property, Business and Regulatory
Quantity Surveying } Property, Business and Regulatory
Electrical and Mechanical Engineering } Property, Business and Regulatory Structural Engineering } WSP
10 Consultations
The following have been consulted during the development of the project: Headteacher and Governors of the school, Children's Services Department, Environment Department, Access Officer, Fire Officer, local County Councillor.