Archived decisions

Children's Services

 

 

 

Capital Programme - 2009/10

 

 

 

 

 

 

 

 

Total

Revenue Effect in

 

 

 

 

 

 

 

 

Construct-

 

Furniture

Cost

Full Year

 

Site

Contract

 

Ref

Project

ion

Fees

Equipment

(excluding

Running

Capital

 

Position

Start

 

Remarks

Ref

 

 

Works

 

Vehicles

sites)

Costs

Charges

 

 

Date

Duration

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

£'000

£'000

£'000

£'000

£'000

£'000

 

 

Qtr

Months

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

All Schemes support Corporate Aim 1:

 

 

2009/10 Schemes (continued)

 

 

 

 

 

 

 

 

 

 

 

Maximising Life Opportunities

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

82

Staff Facilities

214

35

1

250

-

13

 

 

Owned

Various

Various

Improvements to workforce accommodation.

82

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

83

Schools' Devolved Capital

21,723

-

-

21,723

-

1130

 

 

N/A

Various

Various

Allocations to schools through devolved capital.

83

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

84

Fees to progress land sales

-

150

-

150

-

8

 

 

N/A

-

-

 

84

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

85

Schools Access Initiative #

1,288

212

-

1,500

-

78

 

 

N/A

Various

Various

Improvements to school buildings to improve accessibility.

85

 

 

 

 

 

 

 

 

 

 

 

 

 

 

86

Furniture and Equipment #

-

-

500

500

-

68

 

 

N/A

-

-

Provision of furniture and equipment for capital schemes.

86

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

87

Interest on Borrowing

-

1,750

 

1,750

-

-

 

 

N/A

-

-

To meet the cost of borrowing

87

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency

929

-

-

929

-

48

 

 

N/A

-

-

Provision for cost increases arising from inflation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Programme Supported by

32,418

3,510

504

36,432

140

1,846

 

 

 

 

 

 

 

 

the Government and other bodies

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

External Contributions to

 

 

 

-

-

-

 

 

 

 

 

 

 

 

Programme

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Programme Supported by

 

 

 

36,432

140

1,846

 

 

 

 

 

 

 

 

the Government

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total excluding land

 

 

 

36,632

140

1,856

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cost of land to be purchased for

 

 

 

100

-

4

 

 

 

 

 

 

 

 

this programme

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Programme

 

 

 

36,732

140

1,860

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

# controlled on an accrued

 

 

 

 

 

 

 

 

 

 

 

 

 

 

expenditure basis

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

C32

C33