Archived decisions

Children's Services

 

 

 

Capital Programme - 2008/09

 

 

 

 

 

 

 

 

Total

Revenue Effect in

 

 

 

 

 

 

 

 

Construct-

 

Furniture

Cost

Full Year

 

Site

Contract

 

Ref

Project

ion

Fees

Equipment

(excluding

Running

Capital

 

Position

Start

 

Remarks

Ref

 

 

Works

 

Vehicles

sites)

Costs

Charges

 

 

Date

Duration

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

£'000

£'000

£'000

£'000

£'000

£'000

 

 

Qtr

Months

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

All Schemes support Corporate Aim 1:

 

 

2008/09 Schemes (continued)

 

 

 

 

 

 

 

 

 

 

 

Maximising Life Opportunities

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

65

Staff Facilities

86

14

-

100

-

5

 

 

Owned

Various

Various

Improvements to workforce accommodation.

65

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

66

Schools' Devolved Capital

21,723

-

-

21,723

-

1130

 

 

N/A

Various

Various

Allocations to schools through devolved capital.

66

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

67

Fees to progress land sales

-

150

-

150

-

8

 

 

N/A

-

-

 

67

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

68

Schools Access Initiative #

1,373

227

-

1,600

-

83

 

 

N/A

Various

Various

Improvements to school buildings to improve accessibility.

68

 

 

 

 

 

 

 

 

 

 

 

 

 

 

69

Furniture and Equipment #

-

-

500

500

-

68

 

 

N/A

-

-

Provision of furniture and equipment for capital schemes.

69

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

70

Interest on Borrowing

-

1,842

 

1,842

-

-

 

 

N/A

-

-

 

70

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency

428

-

-

428

-

22

 

 

N/A

-

-

Provision for cost increases arising from inflation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Programme Supported by

40,447

4,927

503

45,877

140

2,332

 

 

 

 

 

 

 

 

the Government and other bodies

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

External Contributions to

 

 

 

-

-

-

 

 

 

 

 

 

 

 

Programme

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Programme Supported by

 

 

 

45,877

140

2,332

 

 

 

 

 

 

 

 

the Government

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total excluding land

 

 

 

46,077

140

2,342

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cost of land to be purchased for

 

 

 

100

-

4

 

 

 

 

 

 

 

 

this programme

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Programme

 

 

 

46,177

140

2,346

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

# controlled on an accrued

 

 

 

 

 

 

 

 

 

 

 

 

 

 

expenditure basis

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

C32

C33