Archived decisions
Hampshire County Council Executive Member for Education 2 April 2007
Baycroft School, Fareham
Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ | |
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
Title Location
Architect's plans PMIS file
Building Profile Reports TMH
Hampshire County Council
Building Design Project Appraisal |
Buildings, Land and Procurement Panel
20 March 2007
Executive Member for Education
2 April 2007
Executive Member for Policy and Resources
5 April 2007
Project: |
Baycroft School, Fareham | |
Classroom extension | ||
Commencement date: |
August 2007 | |
Completion date: |
March 2008 | |
Planned year of start in accordance with Capital Programme: |
2007/08 | |
Recommendation:
That the building design project appraisal for the Baycroft School scheme be approved.
1 Finance
Capital Expenditure |
Current Estimate £'000 |
Capital Programme £'000 |
Buildings |
585 |
**380 |
Fees |
80 |
60 |
Land to be purchased |
_ |
_ |
Total |
*665 |
440 |
* The means by which the difference between the Current Estimate and the Capital Programme
allocation is to be met is shown in the table below.
** The £380,000 excluding fees quoted as being from the Children's Services Capital Programme includes the £300,000 including fees which will be proposed to be carried forward from 2006/07 into 2007/08. The remainder is to come from the capital contingency.
Financial Provision for Total Scheme |
Buildings £'000 |
Fees £'000 |
Total cost £'000 |
1 From own Resources: |
|||
a) Capital Programme (as above) |
380 |
60 |
440 |
b) School - devolved capital |
130 |
20 |
150 |
2 From Other Resources: |
|||
a) Policy and Resources Capital Repairs budget |
42 |
- |
42 |
Total |
552 |
80 |
***632 |
*** Any remaining shortfall at receipt of tenders will be addressed by identifying appropriate savings on the scheme.
Building Cost - Net Cost = £1,887 per m2 excluding abnormals
- Gross Cost = £3,005 per m2
Devolved Capital allocations £'000
2004/05 38,478
2005/06 39,678
2006/07 50,123
2007/08 50,819
Total 179,098
Landlord funded work connected with this scheme
A contribution is being made for replacement windows to the ground floor south façade of the existing building and for the replacement of ground floor external doors.
Value of land already acquired for this project
The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.
Revenue implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) *Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
Nil |
12 |
12 |
33 |
45 |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
The overall level of the revenue budget for funding schools will (from April 2006) be prescribed by central government, and capital projects have no bearing on the level of this budget. Therefore, this proposed project will have no bearing on the overall level of the Children's Services budget, extra costs and savings being met from the same overall schools' funding level.
Energy costs
The estimated annual energy consumption for the new accommodation will meet that required by current Building Regulations. It is anticipated that the increase in fuel cost for the school will be in the order of £1,197 per year (£7.30 for each m² of new accommodation) and 7 tonnes of CO2 per year.
2 Details of site and existing infrastructure
Location/adjoining land and buildings
Baycroft School is located on the eastern edge of Stubbington, a residential area to the south of Fareham. The site fronts onto Gosport Road, which is largely residential. Opposite the school are the decommissioned HMS Daedalus airfields.
Area including comparison with local/national standards
The total site area is 4.003 acres (1.62 hectares). The DfES guideline for a school of this size is 5.98 acres (2.42 hectares).
Access
The site shares its access road (a one-way system off Marks Road) with Crofton Secondary School, which abuts Baycroft School to the north. The contractor's access during construction will be directly off Gosport Road, avoiding conflict with the main pedestrian access to the School.
Existing buildings and temporary buildings
The original school building is of two-storey SCOLA construction, built in 1975. There are no temporary buildings on site and none are required for this scheme.
Results of trial boreholes
Site investigations for adjacent sites indicate the natural subsoils to be predominantly clay. The presence of adjacent trees indicates that deeper foundations are required to avoid seasonal moisture-related movements. The foundations have been designed assuming highly shrinkable clay. Ground slabs are to be suspended. A site investigation has been commissioned to confirm these conditions.
Mains services position
The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.
3 Scope of the Project
Type of project, layout and facilities provided
This project will provide the additional accommodation required for the number of pupils currently attending the School.
The extended areas will be located to the east and west of the southern portion of the existing School building, enabling suiting of the new and existing science spaces in the east wing and the suiting of the autism rooms in the west wing. Additionally, a replacement medical inspection room is contained within the east wing, replacing the existing room which is displaced to provide the corridor access.
Thus, the additional accommodation provided by the scheme is as follows:
· Science classroom
· Science Prep room
· Autism classroom
· Speech and language room
· Therapy room
· Medical inspection room to replace existing
Places provided
No additional places are provided as a result of the proposed scheme.
4 The Proposed Building
Type of construction, finish and appearance
The proposed extension at Baycroft School comprises 220m2 of new accommodation, contained within two single storey low-pitched wings that are to be constructed to the east and west of the southern portion of the existing building. These wings project southwards from the existing SCOLA 3 building and form an open courtyard space onto which the new and existing teaching spaces will face. It is proposed that this space will also be utilised for outdoor teaching whilst giving a sense of enclosure especially to the pupils of the Autism Unit.
The new spaces are located to enable suiting of the new and existing science spaces in the east wing and the suiting of the autism rooms in the west wing. Additionally, a replacement Medical Inspection room is contained within the east wing, replacing the existing room that is displaced to provide the corridor access.
Because of the acoustic issues associated with the nearby road, there are no openings in the south elevation of the new extensions which directly face the highway. The external façade provides a new face for the school along the road frontage and is finished in render with supergraphic signage located on the southeast corner. The inner face of the courtyard is to be mainly glazed, this glazing being shaded with a brise soleil to avoid excessive solar gain.
Impact Assessment
A disability access audit has been carried out. The main entrance to the school has level access and level access is available throughout the ground floor of the existing and new accommodation.
Assessment of the Race Relations (Amendment) Act has been considered in the development of this proposal. No adverse impact has been identified in terms of race, creed or gender.
Heating and ventilation systems
The existing heating system will be extended to serve the proposed extensions.
Due to the close proximity of Gosport Road, the classroom spaces will be mechanically ventilated to enable control of the external noise levels, in accordance with current regulations.
Fire risk assessment
In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.
Health and safety
A designer's risk assessment and a design health and safety plan, in accordance with Regulation 15 of the Construction Design and Management Regulations 1994, will been undertaken for the proposed scheme.
5 External Works
Car parking
As the proposed scheme does not increase pupil or staff numbers, no additional car parking spaces are being provided.
Landscape proposals
Landscaping works include the provision of a new paved courtyard adjacent to the extension with low-level planting around the perimeter.
Situation on site and environmental impact
No trees will be removed as part of these proposals. Ecological investigations have concluded that there are no protected species or habitats affected by these proposals.
The scheme will provide an opportunity to enhance the public face of the school along the street frontage.
6 Planning
A detailed planning application was submitted during February 2007.
7 Building management
Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.
8 Furniture and equipment
A furniture and equipment allocation will be made from the Block Vote in the Children's Services Capital Programme 2007/08.
9 Professional resources
Architectural Services } Property, Business and Regulatory
Quantity Surveying } Property, Business and Regulatory
Electrical and Mechanical Engineering } Property, Business and Regulatory
Structural Engineering } R J Watkinson
10 Consultations
The following have been consulted during the development of the project: Headteacher and Governors of the school, Children's Services Department, Environment Department, Access Officer, local County Councillor , Hampshire Fire and Rescue Service and Southern Water.