Hampshire County Council Executive Member for Education 2 April 2007 Dowd's Farm Primary School, Hedge End Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1 |
Summary |
|
|
1.1 |
The following decisions are sought: |
|
|
|
1. That the Executive Member for Education advises the Executive Member for Policy and Resources that the design project appraisal for the scheme to provide a one-form entry primary school at Dowd's Farm, Hedge End, at a total estimated cost of £4,367,000, excluding fees, is approved. |
|
2. That the Executive Member for Education approves advance enabling works for the main scheme at Dowd's Farm, Hedge End, at a total estimated cost of £200,000, excluding fees. |
2 |
Reason |
|
|
2.1 |
To provide a one-form entry primary school to serve new homes which are currently being developed at Dowd's Farm, Hedge End. |
2.2 |
The proposed scheme will provide a new primary school which will maximise wellbeing and enhance the quality of place for all users of the facilities. |
|
|
3 |
Other options considered and rejected |
|
|
3.1 |
The need for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need. |
|
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
|
|
4.1 |
None. |
|
|
5 |
Dispensation granted by the Standards Committee |
|
|
5.1 |
Not applicable. |
|
|
6 |
Reason(s) for the matter being dealt with if urgent |
|
|
6.1 |
Not applicable |
|
|
|
|
Approved by: |
.......................... |
Date of decision: |
................... |
Councillor D Kirk Executive Member for Education |
|
|