Hampshire County Council Executive Member for Children's Services 17 May 2007 Minor Projects Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1. Summary
1.1 The purpose of this report is to provide an update of the progress made in implementing those Early Years Centre/Children's Centre schemes in the Children's Services Capital Programme with a value of between £43,000 and £216,000 (exclusive of fees).
1.2 The schemes within this report generally reflect the priorities in the Corporate Strategy by maximising the safety and accessibility of all users of the premises and enhancing the quality of place.
2. Current Position
2.1 The attached tables summarise the current position in relation to schemes funded by the Children's Service 2006/07 and 2007/08 Capital Programme. The tables provide details of the funding, a brief description of the works and a summary of the current position.
3. Summary of Schemes for approval
3.1 Aviary Early Years Centre, Eastleigh
An allocation of £212,000, excluding fees, has been made in the Children's Services Capital Programme 2007/08 for internal refurbishment and reconfiguration works to provide a medical and sensory room, a kitchenette, baby-changing facilities and additional storage, all within existing spaces.
Externally, the proposals include improved hard and soft outdoor play areas, the replacement of an existing entrance into the Centre with an electrically powered door and associated ramping, suitable surfacing and areas of shade and shelter for parents and children.
It is anticipated that works will commence on site during July 2007 and be completed during September 2007.
3.2 Colours Youth Centre, Hardley
An allocation of £90,000, excluding fees, has been made in the Children's Services Youth Capital fund 2007/08 for works to provide an adventure play area and multi-use games area (MUGA) within the grounds of the Youth Centre. The MUGA will be located to the south of the main building and incorporate a variety of adventure play equipment, to include safety surfacing.
It is anticipated that the works will commence on site during July 2007 and be completed during September 2007.
3.3 Children's Centre at Park Primary School, Aldershot
An allocation of £212,875, excluding fees, has been made in the Children's Service Capital Programme 2007/08 for an extension scheme to provide additional community accommodation.
The Children's Centre will be extended to form a larger, flexible community space, expanded sleep area and an additional office space, together with expanded and enhanced external play areas and additional parking spaces for staff.
It is anticipated that the proposed works will be carried out over the summer holiday 2007.
Recommendation
1. That the minor works programme be approved.
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ |
|
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information File, PBRS
Children's Services Capital Programme 2007/08
Property |
Funding Position £ |
Summary of works |
Comments |
Aviary Early Years Centre Eastleigh |
Capital Programme 2007/08 212,000 |
Internal refurbishment and external landscaping/ play area works |
It is anticipated that the scheme will commence on site during July 2007 and be completed during September 2007. |
Colours Youth Centre Hardley |
Youth Capital fund 90,000 |
MUGA and adventure play equipment |
It is anticipated that the scheme will commence on site during July 2007 and be completed during September 2007. |
Children's Centre at Park Primary School Aldershot |
Capital Programme 2007/08 212,875 |
Extension |
It is anticipated that the works will be carried out during the summer holiday 2007. |