Executive Lead Member for Children's Services (Education) 17 July 2007 Major Projects Status Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.
1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.
2. Recommendations
2.1 That the additional works and funding for schemes at Cove School, Henry Tyndale School, Pinewood School, Amery Hill Secondary School, Burnham Copse School, Dowd's Farm School, Grayshott Primary School, Kings Copse School and Lantern's Children's Centre be approved.
3. Completed Schemes
3.1 Since the April 2007 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Cowplain Community School, Waterlooville July 2007
Curdridge Primary School April 2007
Hamble Community College April 2007
Hardley School and Sixth Form, Holbury April 2007
Hollywater School, Bordon April 2007
West Tytherley C of E Primary, Salisbury May 2007
Wildern School, Hedge End April 2007
4. Additional Works and Funding Added Post Contract
4.1 The following schemes have had further funding added to the contract for specific additional works.
4.2 Cove School, Farnborough
The scheme to provide replacement resourced provision for students with a hearing impairment as well as to relocate the library to provide an ICT suite was approved by the Executive Member for Education on 21 July 2006.
An additional contribution of £10,000 from P&R NDS 07/08 budget has been added to the scheme for a new electrical supply upgrade.
4.3 Henry Tyndale School, Farnborough
The scheme to provide a new post 16 provision and site enhancements was approved by the Executive Member for Policy and Resources on 6 December 2006. The tenders were returned higher than anticipated and the funding is now:
£
Children's Services Capital Programme 06/07 521,000
School 172,000
FF&E budget 25,862
P&R capital repairs 25,392
744,254
4.4 Pinewood School, Farnborough
The scheme to provide a new one form entry infant school was approved by the Executive Member for Policy and Resources on 16 June 2006. An additional contribution of £20,000 has been made from the P&R external works budget to replace poor quality, worn-out tarmac playcourt finishes.
5.0 Additional Works and Funding added at Pre Contract Stage
5.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Education and Policy and Resources.
5.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
5.3 Amery Hill Secondary School, Alton
A scheme to undertake improvement works in readiness for the arrival of pupils with physical disabilities in the autumn term of 2007 was agreed by the Executive Member for Policy and Resources on 5 April 2007. Additional funding of £57,000 was provided by the school for extra storage and office space for the sports block and a small faculty extension elsewhere on the site.
6.0 Current Position
6.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.
6.2 Burnham Copse Primary School, Basingstoke
The major scheme to provide a new one form entry primary school in Basingstoke was approved by the Executive Member for Policy and Resources on 5 April 2007. An ecological survey has confirmed the presence of bats on site and a licence will be applied for and the necessary actions taken. The scheme was due to start on site in August 2007 but will now be delayed until October 2007.
6.3 Cove School, Farnborough
The scheme to provide replacement resourced provision for students with hearing impairment as well as to relocate the library for a new ICT suite was approved by the Executive Member for Education on 21 July 2006.
The works were due to complete in June 2006 but is currently running six weeks behind schedule due to issues with the demolition works. The scheme is now anticipated to complete in August 2007.
6.4 Dowd's Farm Primary School, Hedge End
The scheme to provide a new one form entry primary school was approved by the Executive Member for Policy and Resources on 5 April 2007. Negotiations to form a contract are underway with the framework contractor HBG and are due to be finalised shortly. To set up the site and commence enabling works, an early contract of £75,000 has been issued..
6.5 Grayshott Primary School
The scheme to provide permanent teaching accommodation and multi purpose community rooms was approved by the Executive Member and the works were completed during July 2006.
In settling the final accounts, there is an overspend of £8,594. This is due to the school requesting additional works - creation of new toilets and the refurbishment of their shared area and existing toilets to create tutorial facilities. The works were in the original feasibility but omitted on cost grounds before tender.
The school have confirmed £52,153 funding to achieve the above additional work, but there is a shortfall of £8,594 that Children's Services has confirmed will be met from within the capital programme.
6.6 Kings Copse Primary School, Hedge End
The scheme to provide a new one form entry primary school with a visual impairment resource provision unit to replace the existing school was approved by the Executive Member for Policy and Resources on 5 April 2007. Negotiations to form a contract are underway with our framework contractor HBG and are due to be finalised shortly. To set up the site and commence enabling works, an early contract order of£75,000 has been issued.
6.7 Lantern's Children's Centre, Winchester
The major project to provide an innovative new Early Years Centre in Winchester was successfully completed in September 2005. Since that time, negotiations with the main contractor have been ongoing to conclude the final account. This has recently been settled. The project was overspent by under 5% of the contract sum (just under £100,000). This was principally due to three issues:
- unforeseen services infrastructure in the pavement which had to be diverted to satisfy the statutory authorities
- additional spoil being taken off site due to particular local ground conditions discovered during excavations
- additional specialist fitting-out to suit the specialist nature of the facility.
It should be noted that none of the above were apparent at the time of tender.
The Executive Member is asked to approve the additional funding for this successful project from the increased value of the capital receipt from the sale of the adjacent Greenacres site and other disposals in Winchester which were identified to fund the project.
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ |
|
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules
Project Appraisal
I/PB&R/Committees/MajorMinorSelf-Funded2006/December/MajorProjectsStatusReport
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Amery Hill Secondary School, Alton - improvement works for pupils with physical disabilities. |
Design |
Aug 07 |
Mar 08 |
576,000 |
Capital Prog(SAI) 06/07 176,000 (to be carried forward to 07/08 tbc) Capital Prog (SAI) 07/08 343,000 School devolved capital 57,000 576,000 |
Baycroft School, Fareham - extension to the two storey building for purpose built space |
Tender |
Sept 07 |
Mar 08 |
585,000 |
Capital Prog 07/08 380,000 School devolved capital 150,000 P&R Capital Repair 07/08 42,000 |
Beaulieu Village Primary School - extension to provide new music/drama and library and IT space. - refurbish toilet areas |
On site |
Jan 07 |
Aug 07 |
* 411,380 |
Capital Programme 06/07 323,065 School devolved capital 33,315 P&R NDS Condition 55,000 411,380 |
Bridgemary Community Sports College, Gosport - purpose built suite with separate access for community use - adjacent courtyard |
Tender negotiation |
Jul 07 |
Jan 08 |
290,000 |
School devolved capital 290,000 |
Brookfield Community School, Sarisbury Green - further accessibility works |
Tender negotiation |
Jul 07 |
Oct 07 |
287,000 |
Capital Prog 07/08 (SAI) 105,000 Capital Prog 05/06 (NDS) 76,000 School devolved capital (tbc) 106,000 287,000 |
Burghclere Primary School - extension and refurbishment |
On site |
Feb 07 |
Sep 07 |
* 604,371 |
Capital Programme 06/07 439,660 School 89,660 SAI - FE & Demolition 41,379 P&R NDS Capital Projects 20,741 Capital Programme 07/08 12,931 604,371 |
Burnham Copse Primary School, Basingstoke - new one form entry school |
Tender negotiation |
Oct 07 |
Sept 08 |
2,424,000 |
Capital Programme 07/08 2,318,000 School devolved capital 106,000 2,424,000 |
Cadland Primary School, Holbury - amalgamation to form a two-form entry primary school and Children's Centre |
Tender |
Jul 07 |
Aug 08 |
2,209,000 |
Capital Programme 06/07 472,000 Sure Start 696,000 School 179,000 Prudential Borrowing 862,000 2,209,000 |
Cherrywood Community Primary School, Farnborough - relocate existing classes to the original building to provide a one form entry school |
Tender negotiations |
Jul 07 |
Oct 07 |
313,000 |
Capital Programme 07/08 313,000 |
Cove School, Farnborough teaching room, testing room and support rooms for pupils with hearing impairment. |
On site |
Oct 06 |
Aug 07 |
* 669,482 |
SAI 06/07 337,069 School 193, 103 Specialist School funding 129, 310 P&R Capital Repairs 06/07 10,000 669,482 P&R NDS 07/08 10,000 679,482 |
Cowplain Community School, Waterlooville - floodlit Synthetic Turf Pitch (STP) and Multi Use Games Area (MUGA) |
Completed |
Feb 07 |
Jul 07 |
* 543,381 |
Ed Capital 05/06 NOF 147,740 Capital Programme 06/07 40,000 Football Foundation 319,177 School 34,464 543,381 |
Crofton Hammond Junior School, Fareham - classroom extension |
On site |
Apr 07 |
Sep 07 |
* 408,150 |
Capital Programme 06/07 359,150 School 49,000 408,150 |
Curdridge Primary School, two classroom, group / special needs room and library extension |
Completed |
Aug 06 |
Apr 07 |
* 711,779 |
Cap Prog. NDS Mod 06/07 651,787 School 45,000 P&R NDS Condition 05/06 14,992 711,779 |
Dowd's Farm Primary School, Hedge End - one form entry primary school |
Tender negotiation |
May 07 |
Mar 08 |
4,367,000 |
Capital Programme 07/08 4,367,000 |
Fernhill School and Language College, Farnborough - refurbishment of CDT accommodation |
On site |
Jun 07 |
Aug 07 |
* 274,118 |
Capital Programme 06/07 215,718 School 58,400 274,118 |
Greatham Primary School, Liss - provide permanent teaching accommodation to replace the temporary building on site. |
On site |
Nov 06 |
Sep 07 |
* 679,988 |
Capital Programme 06/07 639,988 School 40,000 679,988 |
Hamble Community College - floodlit tennis courts, courtyard improvements & flood relief works |
Flood relief works: Complete Courtyard: Completed |
Sept 06 Mar 07 |
Nov 06 Apr 07 |
* 70,000 * 68,000 |
P&R Capital Prog 05/06 70,000 Hamble College 45, 000 NDS Residual funding 4,000 P&R External Works 06/07 19,000 68,000 |
Hardley School and Sixth Form, Holbury - four court sports hall |
Completed |
Aug 06 |
Apr 07 |
* 2,130,886 |
Children's Services NDS Mod 06/07 1,913,886 School 217,000 2,130,886 |
Henry Tyndale School, Farnborough - new Post-16 provision and entry enhancements |
On site |
Jul 07 |
Mar 08 |
* 744,254 |
Capital Programme 06/07 521,000 School 172,000 FF&E 25,862 P&R Landlords contribution 25,392 744,254 |
Hollywater School, Bordon - new special school |
Completed |
May 05 |
Apr 07 |
* 6,127,722 |
Edu Cap / TCF 05/06 4,887,472 P&R Capital Repairs 05/06 629,000 P&R Capital Receipt 572,000 School 39,250 6,127,722 |
John Hunt of Everest Community School, Basingstoke - New School and Youth facility |
Enabling - Complete On site |
Aug 05 Jan 06 |
Nov 05 May 07 |
* 1,106,416 * 22,766,137 |
Capital Receipts 13,543,659 Developer's Contribution 2,383,824 B&D Borough Council 2,008,615 County Council 4,702,654 School 143,385 HCC Youth Services 13,063 22,796,900 |
Kings Copse Primary School, Hedge End - new one form entry primary school with visual impairment |
Tender negotiation |
Jun 07 |
Apr 08 |
4,519,000 |
Capital Programme 07/08 4,276,000 Eastleigh Borough Council 64,000 School devolved capital 179,000 4,519,000 |
Kings Worthy Primary School, Winchester - classroom extension |
Tender |
Jul 07 |
May 08 |
1,380,000 |
Capital Programme 06/07 323,000 School - devolved capital 136,000 Capital receipt 921,000 1,380,000 |
Lee on Solent Junior School - new music/drama space - change existing space into general classroom |
Tender |
Jul 07 |
Dec 07 |
231,000 |
Capital Programme 07/08 215,000 School devolved capital 16,000 |
Liss Junior School - additional accommodation for children with Moderate Learning Difficulties |
Design |
Oct 07 |
Apr 08 |
365,000 |
Capital Programme 07/08 318,000 School devolved capital 16,000 P&R Capital Repairs 07/08 tbc 31,000 365,000 |
Micheldever CE Primary School - Hall and classroom extension |
On site |
Jul 06 |
Nov 07 |
* 1,898,357 |
Cap Prog NDS Mod 06/07 1,686,460 School 131,897 P&R Cap Repairs 06/07 10,000 P&R NDS Condition 05/06 30,000 P&R NDS Condition 06/07 40,000 1,898,357 |
Pinewood School, Farnborough - new one form entry infant school with speech, language and communication needs provision |
On site |
Jul 06 |
Jul 07 |
* 3,220,103 |
Children's Services Capital Programme 06/07 3,107,000 Rushmoor BC 43,103 School devolved capital 70,000 3,220,103 Add P&R External works 07/08 20,000 3,240,103 |
Romsey Primary School - amalgamation of infant and junior schools to create one-form entry primary school |
On site |
Jun 07 |
Apr 08 |
* 2,898,447 |
Prudential borrowing 2,200,000 School devolved capital 120,447 Capital Prog 06/07 197,000 DfES Sure Start capital 381,000 2,898,447 |
Staunton Community Sports College, Havant - refurbishment of existing sports hall and changing rooms |
On site |
May 07 |
Oct 07 |
* 577, 891 |
P&R NDS Condition 06/07 190,477 Children's Services Capital Programme 06/07 215,000 School funding 172,414 577,891 |
Sundridge BESD School, Havant - new BESD Secondary School |
On site |
Aug 06 |
Aug 07 |
* 4, 822,919 |
Education Capital 05/06 718,260 TCF 3,082,609 Rachel Madocks receipt 677,391 Future land sales 344,659 4,822,919 |
Swanwick Lodge - demolish redundant buildings and refurbish the Hamble block for new training/family counselling area, laundry suite, office and sleep in staff accommodation |
On site |
Jan 07 |
Jul 07 |
* 677,444 |
Children's Services Capital Programme 677,444 |
West Tytherley C of E Primary, Salisbury - classroom extension to replace temporary accommodation |
Completed |
Apr 06 |
May 07 |
* 897,500 Add 6,682 904,182
|
Education Capital 05/06 857,500 School 46,682 904,182 |
Wildern School, Hedge End - new Learning Centre |
Completed |
Jul 06 |
Apr 07 |
* 614,987 |
School 514,987 P&R Capital Repairs 06/07 100,000 614,987 |
Woodlands Education Centre, Havant - replacement Woodlands Education Centre. |
On site |
Dec 06 |
Nov 07 |
* 4,726,995 |
Capital Programme 06/07 4,726,995 |
Appendix 2
Other Schemes in the Children's Services Capital Programme
The following schemes are included in the Children's Services 2007/08 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member for Education or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
Bordon Infant School |
343 |
Breamore Primary School |
585 |
Durley Primary School |
258 |
Elvetham Heath Primary School Phase III |
2,661 |
Freegrounds Infant School |
515 |
Hale Primary School |
548 |
Marnel Schools, Basingstoke |
2,897 |
Shamblehurst Primary School |
515 |
Warren Park Primary School |
tbc |
SECONDARY
Court Moor Secondary School |
tbc |
Portchester Community School |
tbc |
The Toynbee School |
tbc |
Wildern School |
558 |
SPECIAL
Bay House School |
380 |
Riverside Special School |
422 |
EDUCATION OTHER THAN AT SCHOOLS
Basingstoke School Plus |
3,648 |
NDS MODERNISATION
Stanmore Primary |
250 |
The Bridge Centre |
961 |
TOTAL |
14,541 |