Archived decisions
Hampshire County Council Executive Lead Member for Children's Services (Education) 17 July 2007 Marnel Community Infant and Junior Schools, Basingstoke
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ | |
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
Title Location
Architect's plans PMIS file
Building Profile Reports TMH
Hampshire County Council
Building Design Project Appraisal |
Executive Lead Member for Children's Services (Education)
17 July 2007
Executive Member for Policy and Resources
18 July 2007
Project: |
Marnel Community Infant and Junior Schools, Basingstoke | |
Extension and refurbishment | ||
Commencement date: |
January 2008 | |
Completion date: |
November 2008 | |
Planned year of start in accordance with Capital Programme: |
2007/08 | |
Recommendation:
That the building design project appraisal for the Marnel Infant and Junior Schools
scheme be approved.
1 Finance
Capital Expenditure |
Current Estimate £'000 |
Capital Programme £'000 |
Buildings |
3,168 |
3,168 |
Fees |
523 |
523 |
Land to be purchased |
_ |
_ |
Total |
*3,691 |
3,691 |
* The means by which the difference between the Current Estimate and the Capital Programme
allocation is to be met is shown in the table below.
Financial Provision for Total Scheme |
Buildings £'000 |
Fees £'000 |
Total cost £'000 |
1 From own Resources: |
|||
a) Capital Programme (as above) |
3,168 |
523 |
3,691 |
Total |
3,168 |
523 |
3,691 |
Building Cost - Net Cost = £l,948 per m2 excluding abnormals
- Gross Cost = £3,228 per m2
Devolved Capital allocations £'000 £'000
Infant Junior
2004/05 22 24
2005/06 22 24
2006/07 29 30
2007/08 29 33
Total 102 111
Landlord funded work connected with this scheme
Consideration is being given to increasing the scope of works for the currently planned re-roofing of the Junior School.
Value of land already acquired for this project
The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.
Revenue implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) *Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
- |
- |
- |
194 |
194 |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
The overall level of the revenue budget for funding schools will (from April 2006) be prescribed by central government, and capital projects have no bearing on the level of this budget. Therefore, this proposed project will have no bearing on the overall level of the Children's Services budget, extra costs and savings being met from the same overall schools' funding level.
Energy costs
The estimated annual energy consumption for the new accommodation will meet that required by current Building Regulations. It is anticipated that the increase in fuel cost for the school will be in the order of £4,349 per year (£5.90 for each m² of new accommodation). The additional CO² consumption will be 23 tonnes per year.
Value for Money
Factors taken into consideration during the development process to ensure that the project is delivering value for money:
· Procurement - the project is being developed through the major projects framework with the aim of achieving some commonality and repetition from other projects to facilitate economies through repeat business and shared learning.
· Buildability/Specification - the early involvement of the contractor in the design development process has enabled them to contribute valuable experience, knowledge and expertise into achieving optimum design solutions in terms of buildability, quality and costs over the life of the building.
· Whole Life Costs - the development of the project has included an analysis of costs over the whole life-cycle of the building. A Whole Life Cost plan has been prepared for the project and benchmarked against similar projects carried out by the County Council. The WLC summary for this project compares favourably with other infant/primary schools being built by the County when adjusted for the extensions and alterations nature of this project.
· Sustainability - the scheme has been designed to comply with all the latest Building Regulation standards incorporating the current sustainability issues and in addition the Junior school boiler plant will be completely replaced using the latest condensing boiler technology to maximise efficiency of heating and hot water provision.
2 Details of site and existing infrastructure
Location/adjoining land and buildings
Marnel Infant and Junior Schools are located on a shared site within a residential area of Popley in North Basingstoke. The site is bounded on three sides by the residential estates that make up Popley. On the opposite side of Popley Way to the southwest of the site is the current John Hunt of Everest School, which is being relocated to a new facility in Merton Rise in September, whereupon the site will be cleared and redeveloped for housing purposes.
Area including comparison with local/national standards
The total site area is 6.55 acres (2.65 hectares). The DfES guideline for a school of this size is 6.35-7.26 acres (2.48-2.77 hectares).
Access
The school campus is accessed from Shetland Road, a feeder road parallel to Popley Way. For the duration of the works, the contractor will use a temporary access formed onto Shetland Road on the east side of the school to avoid conflict with the main school entrance. On completion of the project, this access will be retained in part to form the basis for a new access path onto the site to address concerns regarding the current drop-off arrangements at the school.
Existing buildings and temporary buildings
The existing buildings are of SCOLA construction, dating from the early 1970s. Both schools are mainly single-storey with higher roof areas over the kitchen and main hall area, with a two-storey junior teaching block.
There are no temporary buildings on the site and none are required for this scheme.
Results of trial boreholes
A ground investigation revealed made ground on top of stiff clay overlying chalk rock. It is therefore recommended that deep strip foundations are used to take account of an existing mature oak tree to the south with a concrete suspended beam and block floor to the main hall.
Mains services position
The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.
3 Scope of the Project
Type of project, layout and facilities provided
It is proposed to extend and refurbish the existing schools to provide the following accommodation:
Junior School (currently has 8 classrooms)
· 6 new classrooms (plus 6 remaining existing)
· new main hall
· music/drama room
· 4 group rooms to be formed from 2 existing classrooms
· toilets (to include accessible)
· associated storage areas
· link corridor
Infant School
· 3 classroom areas
· library area
· reception area
· community space
· kitchenette
· toilets
· special needs space
Places provided
The proposed scheme will provide an additional 60 places within the infant school and an additional 120 places within the junior school. The schools will, on completion of the works, have 270 and 360 places respectively.
4 The Proposed Building
Type of construction, finish and appearance
Infant School
The courtyard extension to the infant school will be of steel-frame construction with brick panel facing, with materials chosen to complement the existing main building and a high-performance roof covering. Windows and doors will be powder-coated polyester aluminium. The entrance extension will have brick facing with a clerestorey to match the existing and a high-performance roof covering and curtain walling.
Junior School
The proposed two-storey extension to the junior school will be located adjacent to the existing two-storey teaching block, of steel-frame construction with brick panel facing and high-performance roof covering.
The new hall will overlap the existing hall, with a canopy link between the two, and a pitched roof rising to the height of the two-storey block to form a first floor gallery overlooking the hall, with glazing on both elevations.
Impact Assessment
All the new accommodation provided in both schools will have level and accessible external access and the south-facing existing infant school classrooms will also be provided with level access.
The junior school extension will include an accessible toilet and will be built with provision for a future lift, if required.
Assessment of the Race Relations (Amendment) Act has been considered in the development of this proposal. No adverse impact has been identified in terms of race, creed or gender.
Heating and ventilation systems
Infant School
Heating will be by radiators, with natural ventilation.
Junior School
Underfloor heating, with natural ventilation.
Fire risk assessment
In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment
concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.
Health and safety
A designer's risk assessment and a design health and safety plan, in accordance with the Construction Design and Management Regulations 2007, have been undertaken for the proposed scheme
5 External Works
Car parking
No additional parking spaces will be provided, but four spaces which are currently designated for use by the Early Years Centre will be redesignated for school use.
Landscape proposals
The courtyard to the infant school is currently used by the Early Years Centre and will be reduced in size by the siting of the proposed extension. On completion of the extension, this courtyard area will be re-landscaped with paved areas and soft planting.
A retaining wall is to be built along the south side of the school to provide level access to all classrooms and provide an edge to the junior school playground. The retaining wall will continue to form a new reception play area to the east of the school.
The layout of the junior school extension will create three new landscaped courtyard areas which will be visually linked via the glazed link and hall glazing. The rear courtyard will be cut into the bank and form an amphitheatre to the new hall. The existing school pond will be relocated with its newt population to the south of the extension alongside the new pedestrian entrance. Following the removal of the contractor's compound, a new informal hard and soft play area will be provided.
Situation on site and environmental impact
The courtyard extension to the infant school is only visible from inside the school. The entrance extension is more visible and will provide a welcoming point of entry from the car park.
The visual impact of the junior school extension on the adjoining houses and streetscape is limited due to the existence of mature trees along the school's boundary and the distance of the extension from the public highway.
An environmental survey has revealed the existence of newts within the school pond and the relocation of the pond and newts will be carried out to meet all statutory requirements.
6 Planning
A detailed planning application was submitted during June 2007.
7 Building management
Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.
8 Furniture and equipment
Additional requirements will be identified and costed. Suitable funding will be found to purchase any additional furniture and equipment required.
9 Professional resources
Architectural Services } Property, Business and Regulatory
Quantity Surveying } Property, Business and Regulatory
Electrical and Mechanical Engineering } Property, Business and Regulatory
Structural Engineering } WSP
10 Consultations
The following have been consulted during the development of the project: Headteacher and Governors of the school, Children's Services Department, Environment Department, Fire Officer, Access Officer, local County Councillor.