Archived decisions

Hampshire County Council

Executive Lead Member for Children's Services (Education)

17 July 2007

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.

1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.

2. Recommendations

2.1 That the additional works and funding for schemes at Cove School, Henry Tyndale School, Pinewood School, Amery Hill Secondary School, Burnham Copse School, Dowd's Farm School, Grayshott Primary School, Kings Copse School and Lantern's Children's Centre be approved.

3. Completed Schemes

3.1 Since the April 2007 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

    SCHOOL COMPLETION DATE

    Cowplain Community School, Waterlooville July 2007

    Curdridge Primary School April 2007

    Hamble Community College April 2007

    Hardley School and Sixth Form, Holbury April 2007

    Hollywater School, Bordon April 2007

    West Tytherley C of E Primary, Salisbury May 2007

    Wildern School, Hedge End April 2007

4. Additional Works and Funding Added Post Contract

4.1 The following schemes have had further funding added to the contract for specific additional works.

4.2 Cove School, Farnborough

      The scheme to provide replacement resourced provision for students with a hearing impairment as well as to relocate the library to provide an ICT suite was approved by the Executive Member for Education on 21 July 2006.

      An additional contribution of £10,000 from P&R NDS 07/08 budget has been added to the scheme for a new electrical supply upgrade.

4.3 Henry Tyndale School, Farnborough

      The scheme to provide a new post 16 provision and site enhancements was approved by the Executive Member for Policy and Resources on 6 December 2006. The tenders were returned higher than anticipated and the funding is now:

        £

      Children's Services Capital Programme 06/07 521,000

      School 172,000

      FF&E budget 25,862

      P&R capital repairs 25,392

          744,254

4.4 Pinewood School, Farnborough

      The scheme to provide a new one form entry infant school was approved by the Executive Member for Policy and Resources on 16 June 2006. An additional contribution of £20,000 has been made from the P&R external works budget to replace poor quality, worn-out tarmac playcourt finishes.

5.0 Additional Works and Funding added at Pre Contract Stage

5.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Education and Policy and Resources.

5.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

5.3 Amery Hill Secondary School, Alton

      A scheme to undertake improvement works in readiness for the arrival of pupils with physical disabilities in the autumn term of 2007 was agreed by the Executive Member for Policy and Resources on 5 April 2007. Additional funding of £57,000 was provided by the school for extra storage and office space for the sports block and a small faculty extension elsewhere on the site.

6.0 Current Position

6.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.

6.2 Burnham Copse Primary School, Basingstoke

      The major scheme to provide a new one form entry primary school in Basingstoke was approved by the Executive Member for Policy and Resources on 5 April 2007. An ecological survey has confirmed the presence of bats on site and a licence will be applied for and the necessary actions taken. The scheme was due to start on site in August 2007 but will now be delayed until October 2007.

6.3 Cove School, Farnborough

      The scheme to provide replacement resourced provision for students with hearing impairment as well as to relocate the library for a new ICT suite was approved by the Executive Member for Education on 21 July 2006.

      The works were due to complete in June 2006 but is currently running six weeks behind schedule due to issues with the demolition works. The scheme is now anticipated to complete in August 2007.

6.4 Dowd's Farm Primary School, Hedge End

      The scheme to provide a new one form entry primary school was approved by the Executive Member for Policy and Resources on 5 April 2007. Negotiations to form a contract are underway with the framework contractor HBG and are due to be finalised shortly. To set up the site and commence enabling works, an early contract of £75,000 has been issued..

6.5 Grayshott Primary School

      The scheme to provide permanent teaching accommodation and multi purpose community rooms was approved by the Executive Member and the works were completed during July 2006.

      In settling the final accounts, there is an overspend of £8,594. This is due to the school requesting additional works - creation of new toilets and the refurbishment of their shared area and existing toilets to create tutorial facilities. The works were in the original feasibility but omitted on cost grounds before tender.

      The school have confirmed £52,153 funding to achieve the above additional work, but there is a shortfall of £8,594 that Children's Services has confirmed will be met from within the capital programme.

6.6 Kings Copse Primary School, Hedge End

      The scheme to provide a new one form entry primary school with a visual impairment resource provision unit to replace the existing school was approved by the Executive Member for Policy and Resources on 5 April 2007. Negotiations to form a contract are underway with our framework contractor HBG and are due to be finalised shortly. To set up the site and commence enabling works, an early contract order of£75,000 has been issued.

6.7 Lantern's Children's Centre, Winchester

      The major project to provide an innovative new Early Years Centre in Winchester was successfully completed in September 2005. Since that time, negotiations with the main contractor have been ongoing to conclude the final account. This has recently been settled. The project was overspent by under 5% of the contract sum (just under £100,000). This was principally due to three issues:

      - unforeseen services infrastructure in the pavement which had to be diverted to satisfy the statutory authorities

      - additional spoil being taken off site due to particular local ground conditions discovered during excavations

      - additional specialist fitting-out to suit the specialist nature of the facility.

      It should be noted that none of the above were apparent at the time of tender.

      The Executive Member is asked to approve the additional funding for this successful project from the increased value of the capital receipt from the sale of the adjacent Greenacres site and other disposals in Winchester which were identified to fund the project.

LINK(S) TO CORPORATE STRATEGY

Yes

No

Hampshire safer and more secure for all

_

Maximising well-being

_

Enhancing our quality of place

_

This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because:

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

Project Appraisal

I/PB&R/Committees/MajorMinorSelf-Funded2006/December/MajorProjectsStatusReport

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Amery Hill Secondary School, Alton

- improvement works for pupils with physical disabilities.

Design

Aug 07

Mar 08

576,000

Capital Prog(SAI) 06/07 176,000

(to be carried forward to 07/08 tbc)

Capital Prog (SAI) 07/08 343,000

School devolved capital 57,000

576,000

Baycroft School, Fareham

- extension to the two storey building for purpose built space

Tender

Sept 07

Mar 08

585,000

Capital Prog 07/08 380,000

School devolved capital 150,000

P&R Capital Repair 07/08 42,000

Beaulieu Village Primary School

- extension to provide new music/drama and library and IT space.

- refurbish toilet areas

On site

Jan 07

Aug 07

* 411,380

Capital Programme 06/07 323,065

School devolved capital 33,315

P&R NDS Condition 55,000

411,380

Bridgemary Community Sports College, Gosport

- purpose built suite with separate access for community use

- adjacent courtyard

Tender negotiation

Jul 07

Jan 08

290,000

School devolved capital 290,000

Brookfield Community School, Sarisbury Green

- further accessibility works

Tender negotiation

Jul 07

Oct 07

287,000

Capital Prog 07/08 (SAI) 105,000

Capital Prog 05/06 (NDS) 76,000

School devolved capital (tbc) 106,000

287,000

Burghclere Primary School

- extension and refurbishment

On site

Feb 07

Sep 07

* 604,371

Capital Programme 06/07 439,660

School 89,660

SAI - FE & Demolition 41,379

P&R NDS Capital Projects 20,741

Capital Programme 07/08 12,931

604,371

Burnham Copse Primary School, Basingstoke

- new one form entry school

Tender negotiation

Oct 07

Sept 08

2,424,000

Capital Programme 07/08 2,318,000

School devolved capital 106,000

2,424,000

Cadland Primary School, Holbury

- amalgamation to form a two-form entry primary school and Children's Centre

Tender

Jul 07

Aug 08

2,209,000

Capital Programme 06/07 472,000

Sure Start 696,000

School 179,000

Prudential Borrowing 862,000

2,209,000

Cherrywood Community Primary School, Farnborough

- relocate existing classes to the original building to provide a one form entry school

Tender negotiations

Jul 07

Oct 07

313,000

Capital Programme 07/08 313,000

Cove School, Farnborough

teaching room, testing room and support rooms for pupils with hearing impairment.

On site

Oct 06

Aug 07

* 669,482

SAI 06/07 337,069

School 193, 103

Specialist School funding 129, 310

P&R Capital Repairs 06/07 10,000

669,482

P&R NDS 07/08 10,000

679,482

Cowplain Community School, Waterlooville

- floodlit Synthetic Turf Pitch (STP) and Multi Use Games Area (MUGA)

Completed

Feb 07

Jul 07

* 543,381

Ed Capital 05/06 NOF 147,740

Capital Programme 06/07 40,000

Football Foundation 319,177

School 34,464

543,381

Crofton Hammond Junior School, Fareham

- classroom extension

On site

Apr 07

Sep 07

* 408,150

Capital Programme 06/07 359,150

School 49,000

408,150

Curdridge Primary School,

two classroom, group / special needs room and library extension

Completed

Aug 06

Apr 07

* 711,779

Cap Prog. NDS Mod 06/07 651,787

School 45,000

P&R NDS Condition 05/06 14,992

711,779

Dowd's Farm Primary School, Hedge End

- one form entry primary school

Tender negotiation

May 07

Mar 08

4,367,000

Capital Programme 07/08 4,367,000

Fernhill School and Language College, Farnborough

- refurbishment of CDT accommodation

On site

Jun 07

Aug 07

* 274,118

Capital Programme 06/07 215,718

School 58,400

274,118

Greatham Primary School, Liss

    - provide permanent teaching accommodation to replace the temporary building on site.

On site

Nov 06

Sep 07

* 679,988

Capital Programme 06/07 639,988

School 40,000

679,988

Hamble Community College

- floodlit tennis courts, courtyard improvements & flood relief works

Flood relief works:

Complete

Courtyard:

Completed

Sept 06

Mar 07

Nov 06

Apr 07

* 70,000

* 68,000

P&R Capital Prog 05/06 70,000

Hamble College 45, 000

NDS Residual funding 4,000

P&R External Works 06/07 19,000

68,000

Hardley School and Sixth Form, Holbury

- four court sports hall

Completed

Aug 06

Apr 07

* 2,130,886

Children's Services

NDS Mod 06/07 1,913,886

School 217,000

2,130,886

Henry Tyndale School, Farnborough

- new Post-16 provision and entry enhancements

On site

Jul 07

Mar 08

* 744,254

Capital Programme 06/07 521,000

School 172,000

FF&E 25,862

P&R Landlords contribution 25,392

744,254

Hollywater School, Bordon

- new special school

Completed

May 05

Apr 07

* 6,127,722

Edu Cap / TCF 05/06 4,887,472

P&R Capital Repairs 05/06 629,000

P&R Capital Receipt 572,000

School 39,250

6,127,722

John Hunt of Everest Community School, Basingstoke

- New School and Youth facility

Enabling -

Complete

On site

Aug 05

Jan 06

Nov 05

May 07

* 1,106,416

* 22,766,137
add 30,763
22,796,900

Capital Receipts 13,543,659

Developer's Contribution 2,383,824

B&D Borough Council 2,008,615

County Council 4,702,654

School 143,385

HCC Youth Services 13,063
P&R External works 06/07 1,700

22,796,900

Kings Copse Primary School, Hedge End

- new one form entry primary school with visual impairment

Tender negotiation

Jun 07

Apr 08

4,519,000

Capital Programme 07/08 4,276,000

Eastleigh Borough Council 64,000

School devolved capital 179,000

4,519,000

Kings Worthy Primary School, Winchester

- classroom extension

Tender

Jul 07

May 08

1,380,000

Capital Programme 06/07 323,000

School - devolved capital 136,000

Capital receipt 921,000

1,380,000

Lee on Solent Junior School

- new music/drama space

- change existing space into general classroom

Tender

Jul 07

Dec 07

231,000

Capital Programme 07/08 215,000

School devolved capital 16,000
231,000

Liss Junior School

- additional accommodation for children with Moderate Learning Difficulties

Design

Oct 07

Apr 08

365,000

Capital Programme 07/08 318,000

School devolved capital 16,000

P&R Capital Repairs 07/08 tbc 31,000

365,000

Micheldever CE Primary School

- Hall and classroom extension

On site

Jul 06

Nov 07

* 1,898,357

Cap Prog NDS Mod 06/07 1,686,460

School 131,897

P&R Cap Repairs 06/07 10,000

P&R NDS Condition 05/06 30,000

P&R NDS Condition 06/07 40,000

1,898,357

Pinewood School, Farnborough

- new one form entry infant school with speech, language and communication needs provision

On site

Jul 06

Jul 07

* 3,220,103

Children's Services

Capital Programme 06/07 3,107,000

Rushmoor BC 43,103

School devolved capital 70,000

3,220,103

Add

P&R External works 07/08 20,000

3,240,103

Romsey Primary School

- amalgamation of infant and junior schools to create one-form entry primary school

On site

Jun 07

Apr 08

* 2,898,447

Prudential borrowing 2,200,000

School devolved capital 120,447

Capital Prog 06/07 197,000

DfES Sure Start capital 381,000

2,898,447

Staunton Community Sports College, Havant

- refurbishment of existing sports hall and changing rooms

On site

May 07

Oct 07

* 577, 891

P&R NDS Condition 06/07 190,477

Children's Services

Capital Programme 06/07 215,000

School funding 172,414

577,891

Sundridge BESD School, Havant

- new BESD Secondary School

On site

Aug 06

Aug 07

* 4, 822,919

Education Capital 05/06 718,260

TCF 3,082,609

Rachel Madocks receipt 677,391

Future land sales 344,659

4,822,919

Swanwick Lodge

- demolish redundant buildings and refurbish the Hamble block for new training/family counselling area, laundry suite, office and sleep in staff accommodation

On site

Jan 07

Jul 07

* 677,444

Children's Services

Capital Programme 677,444

West Tytherley C of E Primary, Salisbury

- classroom extension to replace temporary accommodation

Completed

Apr 06

May 07

* 897,500

    Add 6,682

    904,182

Education Capital 05/06 857,500

School 46,682

904,182

Wildern School, Hedge End

- new Learning Centre

Completed

Jul 06

Apr 07

* 614,987

School 514,987

P&R Capital Repairs 06/07 100,000

614,987

Woodlands Education Centre, Havant

- replacement Woodlands Education Centre.

On site

Dec 06

Nov 07

* 4,726,995

Capital Programme 06/07 4,726,995

                      Appendix 2

Other Schemes in the Children's Services Capital Programme

The following schemes are included in the Children's Services 2007/08 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member for Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

Bordon Infant School

343

Breamore Primary School

585

Durley Primary School

258

Elvetham Heath Primary School Phase III

2,661

Freegrounds Infant School

515

Hale Primary School

548

Marnel Schools, Basingstoke

2,897

Shamblehurst Primary School

515

Warren Park Primary School

tbc

SECONDARY

Court Moor Secondary School

tbc

Portchester Community School

tbc

The Toynbee School

tbc

Wildern School

558

SPECIAL

Bay House School

380

Riverside Special School

422

EDUCATION OTHER THAN AT SCHOOLS

Basingstoke School Plus

3,648

NDS MODERNISATION

Stanmore Primary

250

The Bridge Centre

961

TOTAL

14,541