Hampshire County Council Buildings Land and Procurement Panel Item 7 2 October 2007 Revenue and Capital Repairs 2007/8 - six monthly review Report by the Director of Property, Business and Regulatory Services |
Contact: Karen Murray Ext: 7876 email: [email protected]
|
|
|
|
|
|
|
1 |
Introduction |
|
|
1.1 |
This report updates Members on the current financial position for revenue and capital repairs and the New Deal for Schools (NDS) condition funding. In particular it: · Confirms changes to the budget provision for 2007/08 · Outlines a change in the way NDS allocations will be made from 2008/09 · Proposes a re-profiling of capital repairs resources between 2007/08 and 2008/09 · Recommends additions to the capital repairs and NDS Condition fund programmes
|
|
Recommendations |
|
That the Buildings, Land and Procurement Panel advise the Executive Member for Policy and Resources that approval be given to: |
|
|
|
1. The proposed re-profiling of the Policy and Resources capital repairs budget between 2007/08 and 2008/09 2. The additions to the capital repairs and NDS Condition Fund programmes as indicated in paragraph 4.1. |
|
|
2 |
Revenue Repairs |
|
|
2.1 |
Appendix 1 shows that the level of commitment to date against the revenue repairs and maintenance budget is 77% of the £15.3m available with 45% of the financial year having elapsed. As in previous years this is explained in part by the inclusion of £3.7m of budgets which are delegated with no buy-back arrangement and therefore treated as 100% committed. The remaining £12m shows a commitment of 69%. This is still a high proportion of the budget but the figure also includes the full-year commitments under the engineering term maintenance contracts of £6.4m. Excluding these figures the remainder of the budget shows a commitment of 52%. |
|
|
2.2 |
The exceptionally wet weather over the summer period has resulted in higher than usual levels of repairs for example to roof leaks and drains and this is the main reason for the commitments to date being ahead of the profiled budget. As always the winter weather will have an impact on the level of spend and to date no calls have been made against the contingency provision in the budget. |
|
|
2.3 |
The new engineering term maintenance contracts for all areas other than Winchester headquarters buildings commenced on 1 August 2007. The financial impact will be monitored as the year progresses but early evidence suggests there is likely to be an efficiency gain resulting from the new arrangements. The current arrangements for the headquarters buildings run until autumn 2008 and their replacement is currently being considered as part of the Facilities Management Modernisation review. |
|
|
2.4 |
The increase to the budget figure reported to the March meeting relates to increased school funding and reflects more accurate data provided by Children's Services that was unavailable at the time the March report was prepared. |
|
|
3 |
Capital Repairs |
3.1 |
New Deal for Schools (NDS) |
|
The County Council's 2006/07 NDS allocation was: 2006/07 £'000 Works 10,957 Fees 1,644 Total 12,601 |
|
|
3.2 |
The conditions of the Government grant require that the 2006/07 programme be completed by 31 August 2007, in effect creating a 17 month financial year. Commitments at this level have been made delivering £12.6m of projects to schools. |
|
|
3.3 3.4 |
As reported to previous meetings the change in the way the Government provides support for the NDS programme meant the original budget for 2007/08 represented only 80% of the full allocation. The allocation has subsequently been increased by an advance allocation totalling £6.392m for NDS Condition which is 100% grant funded. This advance will be reclaimed over the following three financial years. The 2007/08 total budget including the advance is shown below. 2007/08 £'000 Original 10,247 Advance 6,392 Total 16,639 Allocations for 2008/09 to 2010/11 will be determined as part of the Comprehensive Spending Review 2007 (CSR07) the results of which are expected in December. The funding for this three year period is expected to be allocated on a different basis with a move away from the approach driven by asset management data which has seen substantial support for Hampshire schools. The proposed new approach is determined by the extent of modernisation of schools within an authority. It is not clear what impact the change in the distribution calculation will have on the County Council's overall allocation but transitional arrangements for authorities affected are expected to be put in place. |
3.5 |
It is also unclear whether the size of the NDS programme nationally will change following CSR07 or whether the Government will move back to providing support through a fully grant-funded approach. |
|
|
|
3.6 |
The table below shows indicative figures assuming the overall programme size remains the same. The grant to borrowing approvals ratio remains at 30:70 and the change in formula allocation has no overall impact. The impact of repaying the advance allocation is included. Basic Allocation Repayment of Advance Budget for Year £'000 £'000 £'000 2008/09 10,247 -2,131 8,116 2009/10 10,247 -2,131 8,116 2010/11 10,247 -2,131 8,116 The position in the table above is by no means a worst case scenario but represents a reduction of over 50% against the 2007/08 budget including the advance (21% against the basic allocation). |
|
|
|
3.7 |
Dedicated Schools Grant (DSG) funded The original capital repairs allocation of £10.908m funded from the DSG has been increased by a £1.692m carry forward from 2006/07 as agreed by the Schools Forum. The total funding for 2007/08 is therefore £12.537m. |
|
|
3.8 |
Policy and Resources funding |
|
|
|
|
|
|
3.8.1 |
The Policy and Resources capital repairs funding for 2007/08 incorporating the re-profiling recommended by the Panel at the March meeting was £5.68m. The approved carry forward from 2006/07 was £2.122m making a total provision in 2007/08 of £7.802m. |
|
|
|
|
3.8.2 |
Progress against both the DSG and Policy and Resources allocations in the year to date is shown at Appendix 2. |
|
|
3.8.3 |
To continue to ensure the strategic impact of resources can be maximised a further re-profiling of the 2007/08 allocation it is proposed to carry forward £1m into 2008/09. This would have the effect of reducing the 2007/08 allocation to £6.802m which would be sufficient to fund the programme already underway for the current year. |
|
|
4. |
Additions to the Capital Repairs and NDS Condition Fund programmes |
|
|
4.1 |
It is proposed to add the following schemes to the capital repairs and NDS Condition fund programmes: Moorside Place, Winnall - fitting out of accommodation for the relocation of the Book processing facility from the North Walls Reference Library - £100,000 (Office accommodation budget) Applemore College - SCOLA recladding Phase 4 - £250,000 Queens Enclosure School, Cowplain - re-roofing - £650,000 (NDS) |
|
|
|
LINK(S) TO CORPORATE STRATEGY |
|
Yes |
No |
Hampshire safer and more secure for all |
|
_ |
Maximising well-being |
|
_ |
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act
........................
........................
BLPP1007D
P&R Revenue Maintenance 2007/08 Appendix 1
Commitment as at 7 September 2007
|
|
|
|
|
Budget £'000 |
Commitment |
£'000 |
% |
|
|
|
|
Non-Education Services |
|
|
|
|
|
|
|
Redecorations |
568 |
87 |
15.3 |
Engineering servicing and repairs |
1758 |
1,758 |
100.0 |
Minor structural repairs |
816 |
632 |
77.5 |
Asbestos testing |
43 |
11 |
25.6 |
Vandalism reinstatement |
114 |
89 |
78.1 |
Sub-total |
3,299 |
2,577 |
78.1 |
|
|
|
|
Contingency |
397 |
7 |
1.8 |
|
|
|
|
Delegated to schools |
|
|
|
|
|
|
|
Delegation under LMS scheme |
2,580 |
2,580 |
100 |
Delegation under fair funding: |
|
|
|
Community Schools |
8,029 |
5,737 |
71.5 |
Foundation Schools |
449 |
449 |
100 |
Sub-total |
11,058 |
8,766 |
79.3 |
|
|
|
|
Other Allocations |
|
|
|
|
|
|
|
Strategic consultants |
411 |
422 |
102.7 |
Non functional buildings |
109 |
0 |
0 |
Gypsy and Traveller Sites |
28 |
5 |
17.9 |
Sub-total |
548 |
427 |
77.9 |
|
|
|
|
Total |
15,302 |
11,777 |
77.0 |
Capital Repairs 2007/08 Appendix 2
Commitment as at 11 September 2007
Area of Work |
Budget |
Commitment |
|
£'000 |
% |
Corporate Risk Assessment |
|
|
Condition of building fabric |
4,648 |
73.5 |
Mechanical services failure |
1,309 |
56.3 |
Structural collapse |
672 |
44.5 |
Asbestos |
1,064 |
31.4 |
Fire including arson |
896 |
55.1 |
Electrical services failure |
1,120 |
35.6 |
Legionella |
213 |
9.5 |
DDA |
168 |
26.7 |
Other priorities |
1,261 |
31.8 |
Other Allocations |
|
|
Joint funded landlord's minor works |
964 |
21.0 |
Strategic maintenance |
528 |
14.6 |
Landlord's contributions |
398 |
28.2 |
County Farms |
393 |
102.0 |
Other inc. contingency |
2,858 |
21.9 |
|
|
|
Total |
16,492 |
46.0 |
Notes:
1. Excludes allocation of sums carried forward from 2006/07.