Archived decisions
Hampshire County Council Executive Member - Environment 13 November 2007 Capital Programme 2007/08 - Progress and Amendments Report of the Director of Environment |
Item 3 |
Contact: Helen Ackerman, tel 01962 857806
email:[email protected]
1. Summary
1.1 This report provides a further update on the Environment Department capital programme position for 2007/08. Details are correct to the end of September. The following elements are covered:
(i) Waste Management Programme;
(ii) Environmental Improvement Programmes;
(iii) Structural Maintenance of Principal and Non-Principal Roads Programmes;
(iv) Bridge Strengthening and Maintenance Programme; and
(v) Local Transport Plan (LTP) Integrated Transport Programme (including developer funded projects).
1.2 The programme monitoring shows a generally satisfactory position for this stage in the year. Good progress has been made since the previous report on catching up with the delayed surface dressing programme following the wet weather over the summer but, conversely, delivery of the integrated transport programme is beginning to slow. A review of the programme is currently underway to determine the effect on, and affordability of, subsequent programme years.
1.3 The Environment capital programme includes many diverse projects that are designed to enhance safety or improve access to services. Many of these also aim to manage congestion and contribute to improved air quality, and all projects are designed to respect local distinctiveness while meeting the technical standards required. Decisions made in relation to the capital programme will therefore support the Council's priorities.
2. Recommendations
2.1 That the revised transport capital programme, as set out in Appendix 5 of this report, be approved.
2.2 That the rescheduling of schemes identified in section 7.2 of this report be approved.
3. Waste Management Programme 2007/08
3.1 Progress on the delivery and expenditure of the Waste Management Programme is slower than planned. The revised forecast, a reduction of £117,000, is £194,000. A summary overview of the programme and expenditure profile is attached as Appendix 1.
3.2 Fencing improvements at Bramshill and Somerley closed landfill sites that will enable essential grazing of existing and developing heathland have been delayed, in part, by the need to reschedule essential works that were also delayed by the poor summer weather. The works are now planned to start early in 2008/09. Redundant leachate wells at Bramshill and Somerley and decommissioning of gas wells at Casbrook were also delayed. This work will commence early summer 2008.
3.4 The Household Waste Recycling Centre (HWRC) project in Andover is progressing well and remains on target to be operational by autumn 2008.
3.5 Other HWRC expansion and improvement assessments are underway at Casbrook, Marchwood, Aldershot, Hartley Wintney and Fair Oak. Speed of progress depends on a number of factors, the most significant being land acquisition.
4. Environmental Improvements Programme 2007/08
4.1 This programme comprises the Regeneration of Older Urban Areas initiative (ROUA), the Country Towns Initiative (CTI) and Hampshire Villages Initiative (HVI). The programme is progressing satisfactorily overall and within existing approvals. An overview of the programme is attached as Appendix 2.
4.2 The CTI programme has experienced some delays, the most significant being Titchfield Square which, pending completion of resurfacing elements, should be completed by March 2008.
4.3 The HVI programme is progressing very well. Most projects are either complete or underway, with the exception of Binsted which is now withdrawn following lengthy consultation with the Parish Council and St Mary Bourne which is on hold while further funding opportunities are explored.
5. Structural Maintenance of Principal and Non-Principal Roads Programme 2007/08
5.1 The capital budget for highway maintenance is £28.864 million.
LTP Allocation |
£14.845m |
Local Resources |
£13.974m |
LPSA Grant |
£0.45m |
£28.864m |
5.2 This programme funds structural maintenance on all of Hampshire's highway assets, including those on roads, pavements, bridges, drainage, safety fencing, etc. The programme is diverse and extensive, being delivered by the Area Teams mainly through the Term Maintenance Contract. The larger maintenance schemes (over £100,000) are listed in Appendix 3 for information.
5.3 Programme monitoring shows that delivery and expenditure is progressing well and is on target to achieve a full spend by March 2008. Below is an overview of the type, number and progress made to September this year.
Road Maintenance
5.4 Of the 130 resurfacing and reconstruction schemes, averaging £50,000 per scheme, 79 have been completed. The surface dressing programme was reduced by approximately 7% in order to accommodate increased costs associated with the bad weather. This reduced programme is now complete.
Footway Maintenance
5.5 Of the 130 footway resurfacing and reconstruction schemes, averaging £25,000 per scheme and repairing 21 kilometres (0.4% of the county's surfaced footways), 86 have been completed. The footway surface dressing programme, which is made up of over 200 sites, is 25% completed and is expected to be delivered in full by March 2008.
Drainage Schemes
5.6 Of the 35 drainage schemes in the programme, averaging £50,000 per scheme, eight have now been completed. The remaining programme is progressing to schedule.
Major Maintenance
5.7 The A3023 Hayling Island preliminary design, £50,000, is progressing to programme. The latest estimate for A327 Minley is now £1.35 million; an increase of £100,000. Work has commenced and is due to be completed in the autumn.
5.8 The A3 Major Capital Improvement Scheme, Section 4c is the last section of this project to commit to construction. A commitment to fund essential non bus priority maintenance elements has been made, up to a maximum of £350,000, from the capital maintenance budget. £100,000 has been reallocated from rescheduled schemes, such as Lyndhurst Gyratory which was reported in September, and a contingency of £250,000 has been set aside next year.
6. Bridge Strengthening and Maintenance Programmes 2007/08
6.1 The budget for this programme forms part of the overall capital maintenance programme identified in 5.1 above and is funded from the LTP allocations. The 2007/08 budget for this programme is £3.745 million. A summary of the programme is attached as Appendix 4.
6.2 Monitoring indicates there is satisfactory progress towards delivery of the projects and investigations in the programme and a full spend is planned by March 2008.
7. Integrated Transport Programme 2007/08
7.1 The integrated transport programme forms part of the LTP programme, approved in September at £41.088 million. A revised programme, totalling £24.866 million for 2007/08, is set out in Appendix 5. The following table sets out the changes to the Integrated Transport Programme, including external funding, in context to the full LTP programme:
£'000 | |
LTP Programme approved in September |
41,088 |
Add new schemes (growth point funding) |
850 |
Less rescheduled schemes |
-2,321 |
Variations in costs of schemes |
99 |
TOTAL |
39,716 |
7.2 Delivery of the integrated transport programme has slowed over the summer; there are a further four schemes proposed to be rescheduled and the remaining programme is predominantly planned to start in the last quarter. Reduced funding levels next year mean that consideration to stopping any further LTP slipped scheme needs to be made in January to avoid the carry forward of expenditure. Although expenditure levels this year are similar to last year at £4.3 million LTP and £2.3 million from External Funding, the optimistic target for spending £10 million External Funding is unlikely to be reached by March 2008.
Rescheduling of Schemes in the 2007/08 Programme
7.3 Since reporting seven rescheduled schemes in September, there are a further four schemes, all externally funded, that are now not planned to start during 2007/08.
7.4 Southampton Airport Parkway Interchange and Cycle Access (A335 Wide Lane) £221,000 External Funding
This project has been in the programme since 2005/06 and is linked to the construction of a new footbridge being undertaken by South West Trains (SWT). The new covered footbridge complies with DDA requirements, including wheelchair accessible lifts and slotted cycle channel. This cycleway and complete package of works is jointly funded by the County Council, BAA, NR and SWT and has been delayed in the past because of franchise tendering at SWT. SWT has, unfortunately, missed its railway track possession planned for early 2008, and therefore the programme has to be slipped once again.
7.5 Flexford Road Cycle/Footbridge, Knightwood £1,000,000 External Funding
The Wildlife Trust (Flexford Nature Reserve) has objected to the encroachment of an embankment onto its land, and so the option for retaining walls is being investigated. Both the programme and the estimates will need to be revisited as a result, but it is proposed, at this time, to reschedule this scheme to 2008/09 with its current budget.
7.6 Viables Roundabout Subway £100,000 External Funding
Progress of this scheme has been affected by staff shortages in the North Transport Team. A feasibility study into proposed lighting improvements in the subway has been undertaken and the recommendations are being reviewed. It is not expected that this project will make a start during 2007/08, and is therefore proposed to be rescheduled to 2008/09.
7.7 Solartron Road/North Mead/West Mead, Farnborough £1,000,000 External Funding
This scheme is subject to complicated land negotiations with various parties, including Rushmoor Borough Council, which is also project managing this scheme. It was hoped that the Borough Council, being one of the landowners, would have a greater impact on negotiations if it was managing the project, but unfortunately this has not been the case. The Borough Council has not been able to gain the required outcome which would enable this project to proceed during 2007, although negotiations are continuing. It is proposed that this scheme be withdrawn from the programme and entered onto the reserve list until such time as the land issues can be resolved. A number of reserve schemes are now in development to use the time limited developer funding that would otherwise have expired. Any remaining contributions will continue to be allocated to Solartron Road though future funding cannot be guaranteed if the land negotiations remain unresolved. The alternative proposals will be subject to the Executive Member for Environment's approval before a firm commitment to the programme is made.
New Schemes Entering the Programme
7.8 Hedge End Transport Improvements £850,000 Growth Point Funding 2007/08
The Hedge End Transportation Package is being funded by the Department for Communities and Local Government through its New Growth Point (NGP) budget. This scheme is a replacement for the Botley Road Bus Link which had been developed as a bid for 2007/08 NGP funding but which is currently deferred while bus operator issues are resolved.
7.9 The proposed package is a set of complementary bus and passenger facility improvements that will increase the overall attractiveness of bus travel, both around Hedge End and to the major retail and recreational destination of Southampton city centre. The main features are integration with the real-time information system operating in Southampton, associated bus tracking equipment, 24 new or upgraded bus shelters with real-time information screens, 20 bus stops flags with real-time information, two public information kiosks, automated bus passenger monitoring and intelligent bus priority built into existing signal controlled junctions.
7.10 Because of the constraints on availability of the NGP funding, this project will be completed by March 2008.
8. Impact Assessments
8.1 The proposals in this report are derived from the departmental service plans and LTP objectives, and are in accordance with the budget strategy and the County Council's financial management policy. The proposals are not considered to be discriminatory.
9. Conclusion
9.1 This report proposes that a number of amendments to the 2007/08 programme be approved.
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ |
|
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None |
483Rpt/HA
APPENDIX 1
WASTE MANAGEMENT PROGRAMME
Start Date |
Completion Date |
Scheme Budget |
Expenditure pre 2007/08 |
Expenditure 2007/08 |
Expenditure post 2007/08 |
Total Expenditure | |
Capital Programme 2005/06 | |||||||
Landfill Remedial Works |
|
|
61,000 |
|
|
|
|
- Other Closed Landfill Site |
01/04/2005 |
31/03/2008 |
|
27,000 |
34,000 |
- |
61,000 |
Household (Waste) Recycling Centres |
|
|
1,000,000 |
|
|
|
|
- Andover |
01/04/2005 |
31/03/2009 |
|
41,000 |
50,000 |
500,000 |
591,000 |
- Casbrook |
01/04/2005 |
31/03/2008 |
|
17,000 |
50,000 |
- |
67,000 |
- Others |
01/04/2005 |
31/03/2009 |
|
265,000 |
50,000 |
27,000 |
342,000 |
Total: |
1,061,000 |
350,000 |
184,000 |
527,000 |
1,061,000 | ||
Start Date |
Completion Date |
Scheme Budget |
Expenditure pre 2007/08 |
Expenditure 2007/08 |
Expenditure post 2007/08 |
Total Expenditure | |
Capital Programme 2006/07 | |||||||
Landfill Remedial Works |
|
|
63,000 |
|
|
|
|
- Other Closed Landfill Site |
01/04/2006 |
31/03/2008 |
|
- |
10,000 |
53,000 |
63,000 |
Household (Waste) Recycling Centres |
|
|
1,025,000 |
|
|
|
|
- Andover |
01/04/2005 |
31/03/2009 |
|
- |
- |
569,000 |
569,000 |
- Others |
01/04/2005 |
31/03/2009 |
|
- |
- |
456,000 |
456,000 |
Total: |
1,088,000 |
- |
10,000 |
1,785,000 |
1,088,000 | ||
Start Date |
Completion Date |
Scheme Budget |
Expenditure pre 07/08 |
Expenditure 07/08 |
Expenditure post 07/08 |
Total Expenditure | |
Capital Programme 2007/08 | |||||||
Landfill Remedial Works |
|
|
64,000 |
|
|
|
|
- Casbrook Closed Landfill Site |
01/04/2006 |
31/03/2008 |
|
- |
- |
64,000 |
64,000 |
Household (Waste) Recycling Centres |
|
|
1,048,000 |
|
|
|
|
- Others |
01/04/2005 |
31/03/2009 |
|
- |
- |
1,048,000 |
1,048,000 |
Total: |
1,112,000 |
- |
- |
1,112,000 |
1,112,000 | ||
APPENDIX 2
Environmental Improvements Programme Overview
Country Towns Initiative Schemes |
Start Year |
CTI |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Andover High Street |
2005/06 |
50 |
15.5 |
65.5 | |
Hythe Promenade |
2005/06 |
286 |
503.5 |
789.5 | |
Romsey Church Place |
2003/04 |
373 |
46 |
419 | |
Odiham Town Centre |
2006/07 |
233 |
70 |
303 | |
Swanmore Town Centre |
2006/07 |
55 |
136 |
191 | |
Fordingbridge |
2003/04 |
5 |
3.5 |
8.5 | |
New Milton - stage one |
2006/07 |
208 |
100 |
308 | |
Titchfield Square |
2006/07 |
55 |
133 |
188 | |
Bordon - Forest Centre |
2007/08 |
220 |
344 |
564 | |
Whitchurch Town Centre |
2007/08 |
53 |
110 |
163 | |
|
|
|
| ||
Total CTI Schemes |
1,538 |
1,461.5 |
2,999.5 | ||
Hampshire Village Initiatives Schemes |
Start Year |
HVI |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Ongoing Projects - from previous years |
|||||
Bishopstoke |
2005/06 |
9 |
6.5 |
15.5 | |
Ibsley, Moyles Court |
2005/06 |
5 |
7.5 |
12.5 | |
West Liss |
2006/07 |
26.5 |
38.5 |
65 | |
|
|
|
| ||
Total |
40.5 |
52.5 |
93 | ||
Current programme |
|||||
West Wellow |
2006/08 |
16 |
2.5 |
18.5 | |
Milford-on-Sea* |
2006/08 |
45 |
34.7 |
79.7 | |
Binsted Village |
2006/08 |
10 |
0.5 |
10.5 | |
Hook |
2006/08 |
25 |
1.5 |
26.5 | |
St Mary Bourne |
2006/08 |
20 |
24 |
44 | |
|
|
|
| ||
Total |
116 |
63.2 |
179.2 | ||
*on hold pending additional funding identification
Hampshire Village Initiatives Schemes (continued) |
Start Year |
HVI |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Minor Projects |
|||||
North Waltham Village |
2006/08 |
2 |
2.6 |
4.6 | |
Crondall Parish Council |
2006/08 |
8 |
8.8 |
16.8 | |
Headley |
2006/08 |
1.6 |
2 |
3.6 | |
Upper Wield |
2006/08 |
3 |
1.75 |
4.75 | |
Kingsclere |
2006/08 |
1 |
1 |
2 | |
Olivers Battery |
2006/08 |
1.5 |
1.5 |
3 | |
Monk Sherborne |
2006/08 |
.65 |
0.1 |
.75 | |
Four Marks |
2006/08 |
3 |
4 |
7 | |
Brockenhurst Splash |
2006/08 |
5 |
0 |
5 | |
Lyndford |
2006/08 |
1 |
0.3 |
1.3 | |
Mottisfont |
2006/08 |
1.25 |
0.5 |
1.75 | |
Minor projects to be allocated in 2006/08 programme |
2006/08 |
1 |
0 |
1 | |
|
|
|
| ||
Total |
29 |
22.59 |
51.55 | ||
|
|
|
| ||
Total HVI Schemes |
185.4 |
138.29 |
323.75 | ||
Regeneration of Older Urban Areas Schemes |
Start Year |
ROUA |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Brookvale, Basingstoke |
2007/08 |
283 |
95 |
378 | |
Forton Road, Gosport |
2007/08 |
396 |
0 |
396 | |
Cove, Farnborough |
2007/08 |
373.5 |
0 |
373.5 | |
Church End Green, Yateley |
2005/06 |
721.5 |
231 |
952.5 | |
Old Totton |
2002/03 |
1,019.6 |
610 |
1,629.6 | |
Town Quay, Fareham |
2004/05 |
213 |
90 |
303 | |
Havant Railway Station |
2004/05 |
87.5 |
0 |
87.5 | |
Minor Projects |
2002/03 |
148.6 |
76 |
224.6 | |
The Square, Hamble |
2003/04 |
396 |
608 |
1,004 | |
Glebe Gardens, Basingstoke |
2005/06 |
151.7 |
85 |
236.7 | |
Stoke Road, Gosport |
2003/04 |
208.9 |
25.5 |
234.4 | |
North Camp, Farnborough |
2003/04 |
249.5 |
0 |
249.5 | |
|
|
|
| ||
Total ROUA Schemes |
4,248.8 |
1,820.5 |
6,069.3 | ||
Strategic Landscape Initiatives |
Start Year |
SLI |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Strategic Landscape Initiatives |
2004/05 |
23 |
0 |
23 | |
Strategic Landscape Initiatives |
2005/06 |
23 |
0.5 |
23.5 | |
Strategic Landscape Initiatives |
2006/07 |
43 |
0 |
43 | |
Strategic Landscape Initiatives |
2007/08 |
53 |
0 |
53 | |
|
|
|
| ||
Total Strategic Landscapes Initiatives |
142 |
0.5 |
142.5 | ||
AONB Land Management |
Start Year |
AONB |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
AONB Land Management |
2006/07 |
26 |
0 |
26 | |
AONB Land Management |
2007/08 |
36 |
0 |
36 | |
|
|
|
| ||
Total AONB Land Management |
62 |
0 |
62 | ||
Historic Parks and Gardens |
Start Year |
HP&G |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Historic Parks and Gardens |
2005/06 |
10 |
1.86 |
11.86 | |
|
|
|
| ||
Total Historic Parks and Gardens |
10 |
1.86 |
11.86 | ||
Schools Landscape Programme |
Start Year |
SLP |
Other |
Total | |
£'000 |
£'000 |
£'000 | |||
Schools Landscape Programme |
2005/06 |
31.5 |
161.5 |
193 | |
Schools Landscape Programme |
2006/07 |
35 |
24 |
59 | |
Schools Landscape Programme |
2007/08 |
45 |
26 |
71 | |
|
|
|
| ||
Total Schools Landscape Programme |
111.5 |
211.5 |
323 | ||
APPENDIX 3
List of the Larger Capital Maintenance Schemes over £100,000
Road and Footway Schemes |
£'000 |
|
Bramshaw, Ornamental Drive - Road edge reconstruction |
150 |
|
Andover, Walworth Road Roundabout - Road resurfacing |
115 |
Complete |
Andover, Vigo Road - Road resurfacing |
100 |
Complete |
Andover, East Portway - Replace slab pavement |
100 |
|
Purbrook, Stakes Road - Road edge reconstruction |
270 |
Complete |
Havant, East Street - Replace slab pavement |
100 |
Complete |
Worldham, Blanket Street - Road resurfacing |
110 |
|
Alton, Mill Lane - Road reconstruction |
170 |
|
Fishers Pond, Portsmouth Road - Road edge repairs |
100 |
Reduced |
Aldershot, Ash Road - Road resurfacing |
156 |
Complete |
Blackwater, London Road - Road edge repairs |
100 |
On hold |
North Warnborough, Lord Derby Roundabout - Road resurfacing |
175 |
Complete |
Fleet, Reading Road North - Road resurfacing |
100 |
Complete |
Blackwater, Hawley Road Roundabout - Road resurfacing |
250 |
Complete |
Fleet, Kings Road - Road resurfacing |
245 |
Start Oct |
Hook, Station Road - Road resurfacing |
150 |
|
Blackwater, Rosemary Lane - Road resurfacing |
130 |
Complete |
Fleet, Clarence Road - Road resurfacing |
100 |
Start Oct |
Major Schemes |
£'000 |
|
A3023 Hayling Island (preliminary design work) |
50 |
|
A35 Lyndhurst Gyratory Phase 1 |
50 |
|
A327 Minley |
1,350 |
|
APPENDIX 4
SUMMARY of BRIDGES PROGRAMME 2007/2008 |
||||||
CAPITAL ALLOCATION |
||||||
LTP (Incl Footbridges & Works Agreements & Coastal Work feasibility) |
£3,745,000 | |||||
CAPITAL SPEND |
Road |
Town/Area |
Estimate |
|||
STRUCTURAL MAINTENANCE |
||||||
Minor works (TMC & contract) |
Various |
County-wide |
£685,000 |
|||
Paint Contracts - 07/08 |
Various |
County-wide |
£140,000 |
|||
Accident damage |
Various |
County-wide |
£70,000 |
|||
Footbridges |
Various |
County-wide |
£95,000 |
|||
NR Works Agreements |
Various |
County-wide |
£65,000 |
|||
Malthouse Bridge embankment |
Hart |
£270,000 |
||||
£1,325,000 | ||||||
DESIGN, ASST. & FEASIBILITY |
||||||
County assessments + reviews |
Various |
County-wide |
£120,000 |
|||
NR assessments |
Various |
County-wide |
£50,000 |
|||
Coastal Work feasibility |
EO |
County-wide |
£75,000 |
|||
£245,000 | ||||||
ROAD RESTRAINT SYSTEMS |
||||||
Norris |
U239 |
Farnborough, Rushmoor |
£140,000 |
|||
Redbridge Rail |
A35 |
Totton, New Forest |
£450,000 |
|||
Elvetham Heath |
C401 |
Fleet, Hart |
£220,000 |
|||
Roeshott Rail |
A35 |
Hinton, New Forest |
£100,000 |
|||
Ashurst Road Rail |
A35 |
Ashurst, New Forest |
£300,000 |
|||
Prioritisation/feasibility |
Various |
County-wide |
£70,000 |
|||
£1,280,000 | ||||||
STRENGTHEN/REPLACE |
||||||
Litchford Hill |
New Milton, New Forest |
£50,000 |
||||
New Lane |
Havant |
£160,000 |
||||
Boars |
Bramley, Basingstoke |
£160,000 |
||||
Wallop Ford |
Over Wallop, Test Valley |
£30,000 |
||||
Westwood Gardens |
Chandlers Ford, Eastleigh |
£10,000 |
||||
Ivel Hayes(Bull Hill) |
Boldre, New Forest |
£30,000 |
||||
Foxcotte Lane |
Andover, Test Valley |
£30,000 |
||||
Aldern (brought fwd from 08/09) |
Newtown, Basingstoke |
£60,000 |
||||
Riverside |
Bishopstoke, Eastleigh |
£10,000 |
||||
Other strengthenings |
Various |
County-wide |
£120,000 |
|||
Edge strengthening/protection |
Various |
County-wide |
£140,000 |
|||
£800,000 | ||||||
Unallocated at present |
£95,000 | |||||
TOTAL |
£3,745,000 | |||||
APPENDIX 5
Integrated Transport Capital Programme for 2007/08
Central Hampshire Transport Strategy |
LTP |
Other |
Total £ | |
£000s |
£000s |
£000s | ||
Andover TC Accessibility - London Street/Bridge Street/Winchester Street |
150 |
365 |
515 | |
Sparkford Road, Traffic Management - Winchester |
22 |
23 |
45 | |
Whitehill/Bordon Market Towns Project - Forest Centre |
123 |
441 |
564 | |
Kings Worthy Access Improvements |
0 |
119 |
119 | |
Monxton Road (John Hanson School), Andover |
0 |
120 |
120 | |
Pulens Lane to Tor Way Cycles, Petersfield |
0 |
100 |
100 | |
Winchester Parking and Variable Message Signing |
0 |
100 |
100 | |
|
|
|
| |
Total |
295 |
1,268 |
1563 | |
New Forest Transport Strategy |
LTP |
Other |
Total | |
£000s |
£000s |
£000s | ||
Lyndhurst Approaches Variable Message Signing |
50 |
0 |
50 | |
Station Road South (Mallard Court) - New Milton |
50 |
671 |
721 | |
Northern New Forest Heavy Goods Vehicle Restrictions |
100 |
0 |
100 | |
|
|
|
| |
Total |
200 |
671 |
871 | |
North Hampshire Transport Strategy |
LTP |
Other |
Total | |
£000s |
£000s |
£000s | ||
A340 Aldermaston Road - Improvements |
2,000 |
2,500 |
4,500 | |
B3272 Eversley (Glaston Hill Road Section) |
100 |
0 |
100 | |
Basingstoke Cycle Network Missing Links |
0 |
350 |
350 | |
Chineham to Brighton Hill Quality Bus Partnership |
50 |
100 |
150 | |
Dunley's Hill Toucan Crossing, North Warnborough |
0 |
268 |
268 | |
Brighton Hill Pedestrian Access |
0 |
400 |
400 | |
Glebe Gardens, Basingstoke - Cycleway (Part ROUA) |
0 |
68.6 |
68.6 | |
A30 Greywell Road, Old Basing - Street Lighting |
0 |
100 |
100 | |
ITS Basingstoke and County-wide |
42 |
108 |
150 | |
Ship Lane/Rectory Road, Farnborough - Traffic Management |
0 |
40 |
40 | |
Sycamore Road, Farnborough - Traffic Management |
0 |
48 |
48 | |
Timberlake Road, Basingstoke - Subway Improvement |
0 |
300 |
300 | |
|
|
|
| |
Total |
2,192 |
4,282.60 |
6,474.60 | |
Solent Transport Strategy |
LTP |
Other |
Total £ | |
£000s |
£000s |
£000s | ||
Access to Gosport - A32 Peel Common |
1,000 |
0 |
1000 | |
Access to Gosport - Peel Common |
205 |
0 |
200 | |
Fareham-Gosport Quality Bus Partnership |
480 |
20 |
500 | |
Broadmarsh Cycles, Havant |
240 |
5.3 |
245.3 | |
FWW Western Distributor Road (Schooner Way-Warsash Road) |
1,400 |
420 |
1820 | |
Witherbed Lane Link Road and Segensworth Roundabout |
600 |
2,050 |
2650 | |
Hardley to Hythe Cycle Route |
0 |
350 |
350 | |
Havant Quality Bus Partnership (07/08) |
250 |
0 |
250 | |
Hedge End Rail Station Improvements |
0 |
90 |
90 | |
Hedge End to Southampton Quality Bus Partnership |
200 |
0 |
200 | |
Hythe Pier Maintenance |
90 |
0 |
90 | |
Stubbington Accessibility |
50 |
96 |
146 | |
Whiteley to Swanwick Station Pedestrian and Cycle Accessibility |
0 |
260 |
260 | |
Yew Tree Drive |
250 |
250 |
500 | |
Beeches Hill, Bishops Waltham |
25 |
0 |
25 | |
Eastleigh Quality Bus Partnership - Derby Road-Passfield Avenue Junction |
0 |
120 |
120 | |
Swanwick Station Interchange (Whiteley Accessibility) |
50 |
0 |
50 | |
Springles Lane Road Closure (Whiteley Accessibility) |
60 |
0 |
60 | |
Botley Road, Burridge traffic calming |
0 |
34 |
34 | |
Hedge End Transportation Improvements (HETI) |
0 |
850 |
850 | |
|
|
|
| |
Total |
4,900 |
4,545.3 |
9,445.3 | |
Other Integrated Transport |
LTP |
Other |
Total £ | |
£000s |
£000s |
£000s | ||
Access Partnerships |
100 |
0 |
100 | |
Access to Countryside |
200 |
0 |
200 | |
Community Safety (Street Lighting) Initiative |
60 |
0 |
60 | |
Community Transport |
250 |
0 |
250 | |
LTP Monitoring and Initiatives |
30 |
0 |
30 | |
Minor Schemes and Local Priorities |
180 |
65 |
245 | |
Minor Traffic Management |
420 |
0 |
420 | |
Passenger Transport Information (Traveline) |
200 |
0 |
200 | |
Pedestrian Crossings Programme |
140 |
50 |
190 | |
Rail Stations and Interchanges |
75 |
0 |
75 | |
Recreational Cycling (carry forward expenditure) |
4 |
0 |
4 | |
Safe and Secure Communities Programme |
500 |
0 |
500 | |
Safer Routes to School |
1,000 |
243 |
1,243 | |
|
|
|
| |
Total |
3159 |
358 |
3,517 | |
Casualty Reduction Programme |
LTP |
Other |
Total £ | |
£000s |
£000s |
£000s | ||
Casualty Reduction Programme |
3,000 |
0 |
3,000 | |
|
|
|
| |
Total |
3,000 |
0 |
3,000 | |
|
|
|
| |
TOTAL INTEGRATED TRANSPORT PROGRAMME |
13,746 |
11,125 |
24,870.9 | |
Structural Maintenance of Roads and Bridges |
LTP |
Other |
Total £ | |
£000s |
£000s |
£000s | ||
Structural Maintenance (see appendices 3 and 4 for more details) |
14,845 |
0 |
14,845 | |
|
|
|
| |
TOTAL STRUCTURAL MAINTENANCE PROGRAMME |
14,845 |
0 |
14,845 | |
|
|
|
| |
OVERALL LTP PROGRAMME |
28,591 |
11,124.9 |
39,715.9 | |