Hampshire County Council Executive Lead Member for Children's Services (Education) 10 December 2007 Major Projects Status Report Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 email: [email protected]
|
|
|
|
|
|
1 |
Summary |
|
|
|
The following decisions are sought: |
1.1 |
That the additional works and funding for schemes at Amery Hill Secondary School, Cherrywood Primary School, The Clere School, Cove Secondary School and Pinewood School are approved. |
1.2 |
That the overall position of the major capital projects being undertaken by the Director of Property, Business and Regulatory Services be approved. |
|
|
2 |
Reason(s) |
|
|
2.1 |
To provide enhanced school accommodation and facilities. |
|
|
2.2 |
The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises. |
|
|
3 |
Other options considered and rejected |
|
|
3.1 |
The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost-effective way of meeting that need. |
|
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
|
|
4.1 |
Not applicable |
|
|
5 |
Dispensation granted by the Standards Committee |
|
|
5.1 |
Not applicable |
|
|
6 |
Reason(s) for the matter being dealt with if urgent |
|
|
6.1 |
Not applicable |
|
|
|
|
|
Approved by: |
.......................... |
Date of decision: |
......................... |
Councillor D A Kirk Executive Lead Member for Children's Services (Education) |
|
|