Executive Lead Member for Children's Services (Education) 13 March 2008 Major Projects Status Report
Report of the Acting Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.
1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Acting Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.
2. Recommendations
2.1 That the additional works and funding for schemes at Riverside Community School, Waterlooville and The Toynbee School, Chandler's Ford, are approved.
2.2 That the Executive Lead Member for Children's Services (Education) endorses the action taken by the Acting Director of Property, Business and Regulatory Services on the Elvetham Heath Primary School project to ensure progress remains in line with the Target Programme. This includes an order for pre-construction detailed design work up to the value of £100,000 to the appointed Framework Contractor in advance of the approval of the Project Appraisal by the Executive Member for Policy and Resources.
2.3 That the overall position of the major capital projects being undertaken by the Acting Director of Property, Business and Regulatory Services be approved.
3. Completed Schemes
3.1 Since the April 2007 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Bridgemary Community Sports College, Gosport February 2008
Crofton Hammond Junior School, Fareham December 2007
Lee-on-Solent Junior School February 2008
Micheldever Primary School November 2007
4. Additional Works and Funding Added Post Contract
4.1 The following schemes have had further funding added to the contract for specific additional works.
4.1 Riverside Community School, Waterlooville
The School has contributed an additional £97,000 (excluding fees) for works to refurbish pupil toilets, which will be carried out as part of the classroom extension scheme. The total school contribution is now £191,000, excluding fees, from their devolved capital allocation and LMS funds.
The scheme is now on site and it is anticipated that completion will take place during July 2008.
4.2 The Toynbee School, Chandler's Ford
The scheme is now on site. The Contract made up of two orders: £415,471 for Blakedown Sport and Play to construct the STP and floodlighting and £67,000 for Walker Electrical to upgrade the electricity supply to the site. Residual NDS Condition funding from the Courtmoor STP scheme has been transferred to this scheme towards the electrical works.
5. Additional Works and Funding added at Pre Contract Stage
5.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Education and Policy and Resources.
5.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
6. Elvetham Heath Primary School, Fleet - 3FE Extension
This Major Project in the 2008/09 Capital Programme has a particular target programme to start on site in the summer of 2008 to meet rising pupil demand. A contractor has already been appointed through Hampshire's Framework to secure an early start. The method of procurement selected requires a contractor to be involved in pre-construction and detailed design work in order to meet the required timescale. Because of the timing of the Executive Lead Member for Children's Services and Policy and Resources, decision days in the lead-up to the letting of a contract, it is proposed to take a project appraisal straight to the Executive Member Policy and Resources Decision Day on the 9 April 2008. The project is over £1m and is a key decision for the County Council.
In addition, an order will be given to the contractor to commence pre-construction design work, in advance of the project appraisal being approved, by the Acting Director of Property, Business and Regulatory Services. The value of this work is expected to be around £100,000. This will maintain the target programme towards an early start on site in this financial year. The Executive Member is asked to endorse this course of action
7. Andover Education Centre (formerly Shepherd's Spring Junior School, Andover)
The project to convert this school building to accommodate the Education Centre relocating from leased premises elsewhere in Andover is well underway. There is a key deadline to meet because of the termination of the lease by the landlord of the Education Centre's existing accommodation in the summer of 2008. Works are programmed to commence in April 2008. Because of the fast-track programme and limited lead in time available, the project appraisal was approved by the Executive Member Policy and Resources on 6 March 2008. A copy of the appraisal has been given to the Executive Lead Member for Children's Services (Education) for information. The project is over £1m and is a key decision of the County Council.
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ |
|
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules Project Appraisal
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Amery Hill Secondary School, Alton - improvement works for pupils with physical disabilities |
On site |
Oct 07 |
Mar 08 |
* 616364 |
Capital Prog(SAI) 07/08 521,500 School devolved capital 56,035 P&R Capital Repairs 07/08 (Landlord's Fire Precautions) 50,000 627,535 |
Baycroft School, Fareham - extension to the two storey building for purpose built space |
On site |
Sept 07 |
April 08 |
* 562,000 |
Capital Prog 07/08 380,000 School devolved capital 150,000 P&R Capital Repair 07/08 42,000 572,000 |
Bordon Infant School - reconfiguration of existing space to form classroom areas |
March 08 |
Sept 08 |
500,000 |
Capital Prog 07/08 394,000 Sure Start Capital 07/08 86,000 SAI funding 07/08 20,000 500,000 | |
Breamore C of E Primary School, Fordingbridge - extension and refurbishment to provide hall, kitchen, library/resources space and associated access and improvement works |
On site |
Oct 07 |
June 08 |
* 585,000 |
Capital Programme 07/08 585,000 |
The Bridge Education Centre, Eastleigh - extension, refurbishment, reclad, reroof |
Design |
July 08 |
July 09 |
2,326,000 |
Capital Programme 07/08 1,415,000 P&R Capital Repairs 07/08 322,000 Devolved capital budget 134,000 CAMHS (tbc) 455,000 2,326,000 |
Bridgemary Community Sports College, Gosport - purpose built suite with separate access for community use - adjacent courtyard |
Complete |
Jul 07 |
Feb 08 |
* 290,000 |
School devolved capital 290,000 |
Burnham Copse Primary School, Basingstoke - new one form entry school |
On site |
Nov 07 |
Aug 08 |
2,424,000 |
Capital Programme 07/08 2,318,000 School devolved capital 106,000 2,424,000 |
Cadland Primary School, Holbury - amalgamation to form a two-form entry primary school and Children's Centre |
On Site |
Jul 07 |
Aug 08 |
2,209,000 |
Capital Programme 06/07 472,000 Sure Start 696,000 School 179,000 Prudential Borrowing 862,000 2,209,000 |
Cherrywood Community Primary School, Farnborough - relocate existing classes to the original building to provide a one form entry school |
On site |
Oct 07 |
March 08 |
* 349,800 |
Capital Programme 07/08 313,000 Children's Centre funding 144,000 School devolved capital 50,000 507,000 |
The Clere School and Technology College, Burghclere - extension to form new science laboratory and departmental office DONE |
On site |
Sept 07 |
March 08 |
* 313,175 |
School 313,620 Add 8,000 321,620 |
Court Moor School, Fleet - replacement of existing Redgra pitch |
On site |
Sept 07 |
Nov 08 |
340,000 |
Capital Programme 07/08 135,000 NDS Condition 07/08 70,000 School (devolved capital) 140,000 345,000 345 |
Crofton Hammond Junior School, Fareham - classroom extension |
On site |
Apr 07 |
Dec 07 |
* 408,150 |
Capital Programme 06/07 359,150 School 49,000 408,150 |
Durley C of E Primary School, Durley - new music room, treatment room, SEN room and reconfiguration of an existing classroom area |
Contract |
Oct 07 |
March 08 |
283,000 |
Capital Programme 07/08 258,000 School 25,000 283,000 |
Freegrounds Infant School, Hedge End - classroom extension |
Tender |
March 08 |
Sept 08 |
628,000 |
Capital Programme 07/08 515,000 School 113,000 628,000 |
Glenwood School, Emsworth |
Tender |
March 08 |
Aug 08 |
217,000 |
School 217,000 |
Hale Primary School, Fordingbridge - classroom extension and refurbishment works |
On site |
Oct 07 |
April 08 |
* 619,534 |
Capital Programme 07/08 540,893 School 78,641 619,534 |
Henry Tyndale School, Farnborough - new Post-16 provision and entry enhancements |
On site |
Jul 07 |
Mar 08 |
* 744,254 |
Capital Programme 06/07 521,000 School 172,000 FF&E 25,862 P&R Landlords contribution 25,392 744,254 |
Kings Copse Primary School, Hedge End - new one form entry primary school with visual impairment |
On site |
Jul 07 |
Section 1: May 08 Section 2: August 08 |
* 4,571,030 |
Capital Programme 07/08 4,319,313 Eastleigh Borough Council 72,962 School devolved capital 178,755 4,571,030 |
Kings Worthy Primary School, Winchester - classroom extension |
On site |
Jul 07 |
May 08 |
* 1,306,053 |
Capital Programme 06/07 323,000 School devolved capital 136,000 Capital receipt 847,053 1,306,053 |
Lee on Solent Junior School - new music/drama space - change existing space into general classroom |
Complete |
Jul 07 |
Feb 08 |
* 263,858 |
Capital Programme 07/08 235,858 School devolved capital 28,000 |
Liss Junior School - additional accommodation for children with Moderate Learning Difficulties |
Tender |
Dec 07 |
June 08 |
365,000 |
Capital Programme 07/08 318,000 School devolved capital 16,000 P&R Capital Repairs 07/08 tbc 31,000 365,000 |
Marnel Community Infant and Junior Schools, Basingstoke - extension of both schools |
Tender |
Jan 08 |
Oct 08 |
3,168,000 |
Capital Programme 07/08 3,168,000 |
Micheldever CE Primary School - Hall and classroom extension |
On site |
Jul 06 |
Nov 07 |
* 1,898,357 |
Cap Prog NDS Mod 06/07 1,686,460 School 131,897 P&R Cap Repairs 06/07 10,000 P&R NDS Condition 05/06 30,000 P&R NDS Condition 06/07 40,000 1,898,357 |
Portchester Community School - fire evacuation lift |
Tender |
April 08 |
Aug 08 |
345,000 |
Capital Prog 2007/08 (SAI) 80,000 Children's Services 200,000 NDS Fire Precaution Budget 2007/08 65,000 345,000 |
Riverside Special School, Purbrook, Waterlooville - classroom extension and wc refurbishment |
On site |
Jan 08 |
July 08 |
621,000 |
Children's Services Capital Programme 07/08 430,000 School devolved capital 191,000 621,000 |
Romsey Primary School - amalgamation of infant and junior schools to create one-form entry primary school |
On site |
Jun 07 |
Apr 08 |
* 2,898,447 |
Prudential borrowing 2,200,000 School devolved capital 120,447 Capital Prog 06/07 197,000 DfES Sure Start capital 381,000 2,898,447 |
Shamblehurst Primary School, Hedge End - new permanent classroom and internal refurbishment/reconfiguration works |
Design |
June 08 |
Dec 08 |
515,000 |
Capital Programme 07/08 515,000 |
The Toynbee School, Chandler's Ford - new STP |
On site |
Jan 08 |
May 08 |
*415,471 |
School (devolved capital) 149,099 Capital Programme 07/08 144,144 Football Foundation 18,018 Eastleigh Borough Council 45,145 Transfer of residual NDS Condition funding from Courtmoor scheme 46,064 NDS Condition 07/08 80,000 482,470 |
Warren Park Primary School, Leigh Park, Havant - stand-alone outdoor activity classroom |
Tender |
Nov 07 |
Apr 08 |
351,000 |
Capital Programme 07/08 43,000 School (devolved capital) 93,000 Area Investment funding 193,000 Excellence Cluster funding 22,000 351,000 |
Wellstead (formerly known as Dowd's Farm) Primary School, Hedge End - one form entry primary school |
On site |
May 07 |
April 08 |
* 4,367,000 |
Capital Programme 07/08 4,367,000 |
Wildern Secondary School Hedge End - dining extension |
Negotiation |
March 08 |
Aug 08 |
Capital Programme 07/08 601,000 School 179,000 780,000 | |
Woodlands Education Centre, Havant - replacement Woodlands Education Centre. |
On site |
Dec 06 |
April 08 |
* 4,726,995 |
Capital Programme 06/07 4,726,995 |
Appendix 2
Other Schemes in the Children's Services Capital Programme
The following schemes are included in the Children's Services 2008/09 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member for Education or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
Abbott's Ann Primary School |
tbc |
East Anton Primary School |
tbc |
Elvetham Heath Primary School Phase III |
2,661 |
Knight's Enham Infant and Junior Schools |
tbc |
Meadowlands Primary School |
tbc |
Park Gate Primary School |
tbc |
Roman Way Primary School |
SECONDARY
Crestwood Secondary School |
tbc |
Henry Beaufort Secondary School |
tbc |
Mountbatten Secondary School |
tbc |
Robert May's Secondary School |
tbc |
SPECIAL
TBC |
- |
EDUCATION OTHER THAN AT SCHOOLS
TBC |
NDS MODERNISATION
Stanmore Primary |
250 |
TOTAL |
TBC |