Archived decisions
Capital Repairs 2007/08 Appendix 3
Commitment as at 8 February 2008
Area of Work |
Budget |
Commitment |
£'000 |
% | |
Corporate Risk Assessment |
||
Condition of building fabric |
5,544 |
98 |
Mechanical services failure |
1,309 |
96 |
Structural collapse |
2,352 |
27 |
Asbestos |
1,064 |
84 |
Fire including arson |
896 |
104 |
Electrical services failure |
1,120 |
78 |
Legionella |
213 |
16 |
DDA |
168 |
44 |
Lift failure |
448 |
40 |
Other priorities |
477 |
86 |
Other Allocations |
||
Joint funded landlord's minor works |
964 |
22 |
Strategic maintenance |
585 |
17 |
Landlord's contributions |
398 |
44 |
County Farms |
393 |
112 |
External works/landscaping |
282 |
57 |
Other inc. contingency |
3,126 |
31 |
Total |
19,339 |
66 |