Archived decisions
Hampshire County Council Buildings, Land and Procurement Panel 2 April 2008 Elvetham Heath Primary School, Fleet
Report of the Acting Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ | |
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
Title Location
Architect's plans PMIS file
Building Profile Reports TMH
Hampshire County Council Draft
Building Design Project Appraisal |
Buildings, Land and Procurement Panel
2 April 2008
Executive Member for Policy and Resources
9 April 2008
Project: |
Elvetham Heath Primary School, Fleet | |
One-form entry extension with minor alterations to the existing building. | ||
Commencement date: |
July 2008 | |
Completion date: |
April 2009 | |
Planned year of start in accordance with Capital Programme: |
2008/09 | |
Recommendation:
That the building design project appraisal for the Elvetham Heath Primary School
scheme be approved.
1 Finance
Capital Expenditure |
Current Estimate £'000 |
Capital Programme £'000 |
Buildings |
3,031 |
3,031 |
Furniture & Equipment |
- |
- |
Fees |
500 |
500 |
Land to be purchased |
_ |
* The cost of the land to be acquired is from a separate budget for land purchase within the Children's Services Capital Programme. The land acquisition costs were approved by Executive Member, P&R on 28 January 2008 and amount to: Land Acquisition - £327,000 S106 Planning Contribution - £165,000 _ |
Total |
3,531 |
3,531 |
Financial Provision for Total Scheme |
Buildings and fittings £'000 |
Fees £'000 |
Total cost £'000 |
1 From own Resources: |
|||
a) Capital Programme (as above) |
3,031 |
500 |
3,531 |
Total |
3,031 |
500 |
3,531 |
Building Cost - Net Cost = £2,422 per m2
- Gross Cost = £ 3,259per m2
Devolved Capital allocations
As at 12 March 2008, the school has a devolved capital balance of £43,000.
Furniture and Equipment - £100,000 to be funded from the Executive Lead Member (Children's Services) Block Vote.
Landlord funded work connected with this scheme
There are no landlord funded works associated with this scheme.
Value of land already acquired for this project
The existing school site is not large enough to achieve the building extension. An additional 0.47ha of adjoining land is being acquired and this was approved by the Exec. Member, P&R on 28 January 2008.
Revenue implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) *Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
- |
- |
- |
- |
- |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
The overall level of the revenue budget for funding schools will (from April 2006) be prescribed by central government, and capital projects have no bearing on the level of this budget. Therefore, this proposed project will have no bearing on the overall level of the Children's Services budget, extra costs and savings being met from the same overall schools' funding level.
Energy costs
The estimated annual energy consumption for the new accommodation will meet that required by current Building Regulations. It is anticipated that the increase in fuel cost for the school will be in the order of £5,686 per year or £5.20 m2 of each m2 of new accommodation. (42 tonnes of CO2).
2 Details of site and existing infrastructure
Location/adjoining land and buildings
Elvetham Heath Primary School is located on the Elvetham Heath development, which is a residential area to the north of Fleet. The existing school site is triangular in shape and is bounded to the south by the village green, to the east by residential development and to the northwest by a public car park.
Area including comparison with local/national standards
The total existing site area is (1.6 hectares). The total proposed site area, including the public open space land is 2.4 hectares. The DCSF guideline for a school of this size is (2.8 hectares).
Access
The existing main vehicular and pedestrian access to the site is from The Key. This will remain unchanged.
It is proposed to provide an additional pedestrian access to the northwestern boundary in the location of the current site maintenance access. This will be a gated access and will also provide access for emergency vehicles.
For the duration of the works, the contractor will access the site via the proposed emergency vehicle access route. Once within the school boundaries, pupils and staff will be clearly separated from construction traffic and activities. Deliveries and movement of plant will be restricted during the school day to ensure the safety of all those involved.
Existing buildings and temporary buildings
The original school building was completed in September 2004. There is a double temporary building and one single temporary building located within the existing staff car park which will be removed on completion of the proposed scheme.
Results of trial boreholes
A previous site investigation showed sandy subsoil and therefore there are no onerous design considerations are to be adopted. It is proposed to use a shallow strip foundation with ground-bearing slab.
Mains services position
The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.
3 Scope of the Project
Type of project, layout and facilities provided
The proposed extension will provide the following accommodation:
· 6 classrooms
· hall
· relocated ICT suite
· relocated music/drama room
· administration office
· toilets to include one accessible wc
The proposed internal alterations will provide the following accommodation:
· 1 classroom located in the existing ICT suite inc. cloaks space
· enlarged staffroom located in the existing music /drama room
· staff work room located in the existing staff room
· enlarged glazing to existing head teacher's office
External works will include the provision of:
· junior-sized football pitch
· netball court
· hard and soft play areas
Places provided
On completion of the scheme the school will have capacity for up to 630 pupils.
4 The Proposed Building
Type of construction, finish and appearance
The proposed extension will be of traditional block construction, with facing brickwork and horizontal cedar timber boarding to cladding at low-level. The steeply pitched roofs will be clay tiled, other roofs will have high-performance coverings. The external windows will be polyester powder-coated aluminium. The rainwater goods will be mill finish aluminium All materials have been chosen to match those of the existing building.
Impact Assessment
The proposed single-storey extension will be fully accessible to non-ambulant users throughout. An accessible pupil/staff toilet is provided as part of the scheme.
Due to the existing site levels, it is proposed to provide a ramped connection of not more than 1:20 between the existing school and the proposed extension.
Assessment of the Race Relations (Amendment) Act has been considered in the development of this proposal. No adverse impact has been identified in terms of race, creed or gender.
Heating and ventilation systems
It is proposed to provide a separate plant room for the extension. An under floor heating system similar to that in the main school will be used in the new-build.
The extension will be principally naturally lit and ventilated and many of the rooms will take advantage of the steeply pitched roofs to create high, airy spaces. New sanitary accommodation will be mechanically ventilated.
Fire risk assessment
In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment
concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.
Health and safety
A designer's risk assessment and a design health and safety plan, in accordance with the Construction Design and Management Regulations 2007, have been undertaken for the proposed scheme
5 External Works
Car parking
The existing car parking area will remain unchanged. There is an in principle agreement with Hart District Council to provide an additional 11 staff car parking spaces by use of the public car park to the north of the site.
Landscape proposals
The landscape proposals include the provision of a junior-sized football pitch on land leased by Hart District Council. The land is designated Public Open Space. The school will have access to the pitch during school hours, by agreement, and will be responsible for maintenance. Fencing will be provided between the pitch and the remaining school grounds and to the perimeter of the pitch itself. A formal hard play area is also to be provided, together with other ancillary hard and soft areas.
Situation on site and environmental impact
The project will not have a detrimental effect on the site's existing ecology. The proposed extension is located to have minimal effect on surrounding housing.
6 Planning
A detailed planning application was submitted during February 2008.
7 Building management
Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.
8 Furniture and equipment
An allocation has been made in the Children's Services Block Vote.
9 Professional resources
Architectural Services } Property, Business and Regulatory Quantity Surveying } Property, Business and Regulatory
Electrical and Mechanical Engineering } Property, Business and Regulatory
Structural Engineering } R J Watkinson
10 Consultations
The following have been consulted during the development of the project: Headteacher and Governors of the school, Children's Services Department, Environment Department, Fire Officer, Access Officer, local County Councillor.