Major Projects Status Report

Report of the Acting Director of Property, Business and

Regulatory Services

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.

1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Acting Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.

2. Recommendations

2.1 That additional works and funding at the following schools are approved:

Amery Hill Secondary School

    Durley Primary School

    Hale Primary School

    Henry Tyndale School

    Kings Worthy Primary School

2.2 That the overall position of the major capital projects being undertaken by the Acting Director of Property, Business and Regulatory Services be approved.

3. Completed Schemes

3.1 Since the last meeting of the Executive Lead Member for Children's Services (Education), schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

    SCHOOL COMPLETION DATE

    Baycroft School, Fareham June 2008

    Breamore Primary School, Fordingbridge June 2008

    Cherrywood Community Primary School, Farnborough May 2008

    The Clere School, Burghclere March 2008

    Romsey Primary School April 2008

    Toynbee School, Chandler's Ford June 2008

    Warren Park Primary Schoo, Havant June 2008

    Woodlands Education Centre, Havant May 2008

4. Additional Works and Funding Added Post Contract

4.1 The following schemes have had further funding added to the contract for specific additional works.

4.2 Amery Hill Secondary School

Two further devolved formula capital contributions have been made by the school:

£27,000 (incl. £3,800 fee contribution) for works to form larger client offices and associated alterations

      £20,970 (incl.£2,970 fee contribution) for additional science lab works.

4.3 Durley Primary School, Durley

      Contracts were returned slightly higher than anticipated and as a result an additional contribution of £10,000 has been made from the Capital Programme 2008/09 plus an additional £10,000 from the School's devolved capital allocation.

4.4 Hale Primary School, Fordingbridge

The school have contributed an additional £15,000 from PTA funds for works to develop a soft play area, to include some outdoor equipment.

The works to the pupil toilets will be carried out over the summer holiday period and as a result the scheme is now expected to complete on site during August 2008.

4.5 Henry Tyndale School, Farnborough

The school are contributing up to £13,000 additional funding (devolved capital) towards works to provide a soft play area.

4.6 Kings Worthy Primary School

An additional allocation of up to £35,000 has been made from the Capital Programme 2008/09, together with a contribution of £20,000 from P&R Asbestos funding for works to remove previously undetected asbestos from the corridor area.

5. Additional Works and Funding added at Pre Contract Stage

5.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Children's Services and Policy and Resources.

5.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

6. Programme updates

6.1 Amery Hill Secondary School, Alton

      The original anticipated completion date of March 2008 has been extended to July due to a delay with the supply of the evacuation lift.

6.2 Henry Tyndale School, Farnborough

It was originally anticipated that the scheme would complete in March 2008, but due to problems with the upgrade to the mains gas supply it is now due to complete in July 2008.

6.3 Kings Worthy Primary School

Due to the presence of previously undetected asbestos within the corridor area, asbestos removal works will be carried out during the summer holiday period by a specialist contractor, following which the main contractor will return to site to complete the scheme. The original anticipated completion date of May 2008 will therefore be extended to October 2008.

6.4 Wellstead Primary School, Hedge End (formerly Dowd's Farm)

Partial possession of the school was achieved on 21 April 2008. It is anticipated that final completion will take place at the end of the summer when the remaining landscaping works are complete.

LINK(S) TO CORPORATE STRATEGY

Yes

No

Hampshire safer and more secure for all

_

Maximising well-being

_

Enhancing our quality of place

_

This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because:

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules Project Appraisal

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Abbott's Ann C of E Primary School

Andover

Design

Sept 2008

June 2009

3,380,000

Capital Prog 08/09 3,293,000

School devolved capital 62,000

P&R 2008/09 contribution 25,000

              3,380,000

Amery Hill Secondary School, Alton

- improvement works for pupils with physical disabilities

On site

Oct 07

July 08

* 616,364

Capital Prog (SAI) 07/08 521,500

School devolved capital 56,035

P&R Capital Repairs 07/08

(Landlord's Fire Precautions) 50,000
+ School devolved capital 41,200

668,735

Andover Education Centre (formerly Shepherd's Spring Junior School)

- provision of Education Centre

On site

Phase 1: April 08

Phase 2:

Aug 08

Phase 1:

Aug 08

Phase 2

Dec 08

      1,716,000

Capital Prog 08/09 1,716,000

Baycroft School, Fareham

- extension to the two storey building for purpose built space

Complete

Sept 07

June 08

* 562,000

Capital Prog 07/08 380,000

School devolved capital 150,000

P&R Capital Repair 07/08 42,000

              572,000

Bordon Infant School

- reconfiguration of existing space to form classroom areas

On site

March 08

Sept 08

500,000

Capital Prog 07/08 394,000

Sure Start Capital 07/08 86,000

SAI funding 07/08 20,000

              500,000

Breamore C of E Primary School, Fordingbridge

- extension and refurbishment to provide hall, kitchen, library/resources space and associated access and improvement works

Complete

Oct 07

June 08

* 585,000

Capital Programme 07/08 585,000

The Bridge Education Centre, Eastleigh

- extension, refurbishment, reclad, reroof

Tender

Sept 08

Aug 09

      2,326,000

Capital Programme 07/08 1,415,000

P&R Capital Repairs 07/08 322,000

Devolved capital budget 134,000

CAMHS (tbc) 455,000

2,326,000

Brookfield Community School and Language College

Tender

July 08

Sept 08

      446,427

School devolved capital 108,250

NDS Modernisation 07/08 100,000

Children's Services Cap Prog 40,000

P&R Cap Repairs 07/08

NDS Condition funding 103,177

P&R Cap Repairs 08/09 95,000

              446,427

Burnham Copse Primary School, Basingstoke

- new one form entry school

On site

Nov 07

Aug 08

2,424,000

Capital Programme 07/08 2,318,000

School devolved capital 106,000

2,424,000

Cadland Primary School, Holbury

- amalgamation to form a two-form entry primary school and Children's Centre

On Site

Jul 07

Aug 08

2,209,000

Capital Programme 06/07 472,000

Sure Start 696,000

School 179,000

Prudential Borrowing 862,000

2,209,000

Cherrywood Community Primary School, Farnborough

- relocate existing classes to the original building to provide a one form entry school

Complete

Oct 07

May 08

* 349,800

Capital Programme 07/08 313,000

Children's Centre funding 144,000

School devolved capital 50,000

              507,000

The Clere School and Technology College, Burghclere

- extension to form new science laboratory and departmental office

Complete

Sept 07

March 08

* 313,175

School 313,620

Add 8,000

              321,620

Court Moor School, Fleet

- replacement of existing Redgra pitch

On site

Sept 07

Nov 08

      340,000

Capital Programme 07/08 135,000

NDS Condition 07/08 70,000

School (devolved capital) 140,000

          345,000 345

Cranbourne Business and Enterprise College

Basingstoke

- science laboratory refurbishment

On site

May 08

Sept 08

      336,000

Capital Programme 07/08

NDS 139,000

School devolved capital 110,000

Basingstoke Education

Improvement Partnership

(EIP) funding 87,000

                      336,000

Crestwood College for Business and Enterprise

Eastleigh

Design

Sept 08

March 09

      403,000

Capital Prog 08/09 403,000

Durley C of E Primary School, Durley

- new music room, treatment room, SEN room and reconfiguration of an existing classroom area

On site

March 08

Aug 08

*303,332

Capital Programme 07/08 258,000

School 25,000

+ School 10,000

Capital Programme 08/09 10,000

        303,000

10k school

20k capi prog

Elvetham Heath Primary School

Fleet

- classroom extension

Design

July 08

April 09

      3,031,000

Capital Programme 08/09 3,031,000

Freegrounds Infant School, Hedge End

- classroom extension

On site

June 08

Feb 09

      *607,892

Capital Programme 07/08 515,000

School 113,000

              628,000

Glenwood School, Emsworth

On site

March 08

Aug 08

      217,000

School 217,000

Hale Primary School, Fordingbridge

- classroom extension and refurbishment works

On site

Oct 07

Aug 08

      * 619,534

+£15,000 school funding for additional landscaping works

Capital Programme 07/08 540,893

School 78,641

School (PTA funds) 15,000

              634,534

Henry Beaufort School, Winchester

- refurbishment of two science labs

Testbourne School, Whitchurch

- science laboratory refurbishment

Yateley School

    - food design technology refurbishment

Tender

June 08

Sept 08

      759,900

Capital Programme 07/08

(NDS Modernisation) 386,900

School Funding:

Henry Beaufort 60,000

Testbourne 60,000

Yateley 30,000

P&R Cap Repairs 07/08

(Fire Precautions) 19,000

Children's Services (FFE) -

Yateley 7,000

P&R Cap Repairs 07/08

NDS Condition

(£100k + £95k) 195,000

              759,900

Henry Tyndale School, Farnborough

- new Post-16 provision and entry enhancements

On site

Jul 07

July 08

* 744,254

+ **£13,000 school devolved capital for additional landscaping

Capital Programme 06/07 521,000

School 172,000

School **13,000

FF&E 25,862

P&R Landlords contribution 25,392

757,254

Kings Copse Primary School, Hedge End

- new one form entry primary school with visual impairment

On site

Jul 07

Section 1:

May 08

Section 2:

August 08

* 4,571,030

Capital Programme 07/08 4,319,313

Eastleigh Borough Council 72,962

School devolved capital 178,755

4,571,030

Kings Worthy Primary School, Winchester

- classroom extension

On site

Jul 07

Oct 08

* 1,306,053

Capital Programme 06/07 323,000

School devolved capital 136,000

Capital receipt 847,053

1,306,053

P&R asbestos removal

funding 20,000

Capital Progamme 08/09 35,000

1,361,053

Knights Enham Infant and Junior Schools

Andover

Tender

July 08

April 09

      3,638,000

Capital Programme 08/09 3,320,000

Schools - devolved capital 213,000 P&R contributions 08/09 77,000

NDS Condition 08/09 28,000

              3,638,000 3,638

Liss Junior School

- additional accommodation for children with Moderate Learning Difficulties

On site

Dec 07

July 08

* 328,000

Capital Programme 07/08 318,000

School devolved capital 16,000

334,000

Marnel Community Infant and Junior Schools, Basingstoke

- extension of both schools

On site

March 08

Phase 1:

Inf School

Aug 08

Phase 2:

Junior School

Dec 08

      3,168,000

Capital Programme 07/08 3,168,000

The Mountbatten School and Language College

Romsey

Tender

Aug 08

Nov 08

      228,000

Environment Safe Routes

to School budget 89,000

Capital Prog 08/09 89,000

School devolved capital 50,000

    228,000

      89

Portchester Community School

- fire evacuation lift

Tender

July 08

Nov 08

      345,000

Capital Prog 07/08 (SAI) 80,000

Children's Services 200,000

NDS Fire Precaution

Budget 2007/08 65,000

            345,000

Riverside Special School, Purbrook, Waterlooville

- classroom extension and wc refurbishment

On site

Jan 08

July 08

      621,000

Children's Services

Capital Programme 07/08 430,000

School devolved capital 191,000

              621,000

Romsey Primary School

- amalgamation of infant and junior schools to create one-form entry primary school

Complete

Jun 07

Apr 08

* 2,898,447

Prudential borrowing 2,200,000

School devolved capital 120,447

Capital Prog 06/07 197,000

DfES Sure Start capital 381,000

2,898,447

Sarisbury C of E Junior School

Sarisbury Green

- classroom extension

Tender

July 08

Feb 09

      531,611

Capital Programme 08/09 424,611

Children's Services

Strategic Workforce 07/08 29,000

School funding (dev cap( 78,000

              531,611

Shamblehurst Primary School, Hedge End

- new permanent classroom and internal refurbishment/reconfiguration works

On site

July 08

Feb 09

      515,000

Capital Programme 07/08 515,000

The Toynbee School, Chandler's Ford

- new STP

Complete

Jan 08

June 08

*415,471

School (devolved capital) 149,099

Capital Programme 07/08 144,144

Football Foundation 18,018

Eastleigh Borough Council 45,145

Transfer of residual NDS

Condition funding

from Courtmoor scheme 46,064

NDS Condition 07/08 80,000

          482,470

Warren Park Primary School, Leigh Park, Havant

- stand-alone outdoor activity classroom

Complete

Jan 08

June 08

      351,000

Capital Programme 07/08 43,000

School (devolved capital) 93,000

Area Investment funding 193,000

Excellence Cluster funding 22,000

                      351,000

Wellstead (formerly known as Dowd's Farm) Primary School, Hedge End

- one form entry primary school

On site

May 07

Sept 08

* 4,367,000

Capital Programme 07/08 4,367,000

Wildern Secondary School

Hedge End

- dining extension

Tender

July 08

March 09

      780,000

Capital Programme 07/08 601,000

School 179,000

        780,000

Woodlands Education Centre, Havant

- replacement Woodlands Education Centre

Complete

Dec 06

May 08

* 4,726,995

Capital Programme 06/07 4,726,995

Wyvern Technology College

Eastleigh

Design

Aug 08

Dec 08

      358,000

Capital Programme 08/09 107,000 107 18 125

School devolved capital 94,000

Eastleigh Borough Council 132,000

SITA Trust (Landfill Tax) 8,000

Capital Programme contingency -

(subject to tender return) 17,000

        358,000

                      Appendix 2

Other Schemes in the Children's Services Capital Programme

The following schemes are included in the Children's Services 2008/09 Capital Programmes and the Acting Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Lead Member for Children's Services (Education) or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

Bentley Primary School

                  258

East Anton Primary School

7,000

Meadowlands Primary School

tbc

Park Gate Primary School

600

Picket Twenty Primary School

6,000

Roman Way Primary School

1,200

Sopley Primary School

400

SECONDARY

Hamble Sixth Form College

6,800

Henry Beaufort Secondary School

489

Robert May's Secondary School

553

SPECIAL

TBC

-

EDUCATION OTHER THAN AT SCHOOLS

TBC

-

NDS MODERNISATION

Stanmore Primary

250