Archived decisions

HAMPSHIRE COUNTY COUNCIL

Decision Report:

Decision Maker:

Executive Lead Member for Children's Services (Education)

Date of Decision:

12 March 2009

Decision Title:

Major Projects Status Report

Decision Reference:

563

Report From:

Acting Director of Property, Business and Regulatory Services

Contact name:

Steve Clow

Tel:

01962 847858

Email:

steve. [email protected]

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.

1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Acting Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.

2. Recommendations

2.1 That additional works and funding at the following schools are approved:

Abbott's Ann Primary School

    Elvetham Heath Primary School

    Knights Enham Infant and Junior Schools

    Marnel Infant and Junior Schools

    Park Gate Primary School

    Portchester Secondary School

    Sarisbury Junior School

2.2 That the overall position of the major capital projects being undertaken by the Acting Director of Property, Business and Regulatory Services be approved.

3. Completed Schemes

3.1 Since the last meeting of the Executive Lead Member for Children's Services (Education), schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

    SCHOOL COMPLETION DATE

      Aldworth Science College December 2008

      Marnel Infant and Junior School January 2009

      Mountbatten School and Language College February 2009

      Portchester Community School December 2008

      Sarisbury Junior School March 2009

      Shamblehurst Primary School March 2009

4. Additional Works and Funding Added Post Contract

      The following schemes have had further funding added to the contract for specific additional works.

4.1 Abbott's Ann Primary School - an additional £31,000 has been allocated from the Capital Programme 2008/09 as tenders were returned higher than anticipated.

4.2 Elvetham Heath Primary - the school have contributed £20,000 of devolved capital to fund additional internal alterations.

4.3 Knights Enham Infant and Junior Schools - an additional £203,000 has been allocated from the 2008/09 Capital Programme for post contract variations requested by the client

4.4 Marnel Infant and Junior - approvals for additional works are as follows: £

      Pre-construction design agreement (Education 14.9.07) 214,030

      Direct order for tree/pond works (Education 11.2.08) 4,270

      Smart Metering (NDS Education) 9,073

                      £227,373

4.5 Park Gate Primary School - it was noted in the project appraisal approved by the Executive Member on 18 December 2008 that, subject to school funding, internal refurbishment works including the reconfiguration of four existing classrooms to improve layout and acoustics may be included in the contract. The school has now made an additional contribution to cover the proposed works and the total contract sum is now £710,000.

4.6 Portchester Secondary School - the following additional works were added to the scheme and will be completed during March 2009:

      Re-roofing P&R Capital Repairs 08/09 50,282

Management Partnership Budget 5,500

      Youth Club

      (kitchen refurb) Children's Services Capital Prog 10,000

      Additional external

      repointing works P&R Cap Repairs 7,664

                      73,446

4.7 Sarisbury CE Junior School - the main scheme is now complete, however the school have added an additional £50,000 of their devolved capital for works to upgrade four pupils toilets. It is anticipated that these works will be completed during March 2009.

5. Additional Works and Funding added at Pre Contract Stage

5.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Children's Services and Policy and Resources.

5.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

6. Programme updates

6.1 Abbott's Ann Primary School - due to a delay in signing of the lease agreement, it is now anticipated that the scheme will commence on site in March 2009. The anticipated completion date for the scheme is now February 2010.

6.2 Bentley Primary School - the pre-tender estimate for the project was substantially over the agreed funding (approx 20%). The scheme is currently out to tender and consideration is being given to possible savings and additional funding should the tenders not be returned within the existing budget. It is now anticipated that works will commence on site during April 2009 and complete during October 2009.

6.3 The Bridge Education Centre, Eastleigh - tenders have been returned for this scheme. However, the programme is being revisited in light of a delay in settling the terms of the lease with the NHS. It is now anticipated that works will commence on site during April 2009 and complete during March 2010.

6.4 Knights Enham Infant and Junior Schools - the programme has been extended by eight weeks to carry out post-contract variations requested by the client.

6.5 Robert May's - the programme has been delayed pending the outcome of a grant bid to the Football Foundation.

6.6 Sopley Primary - an ecology survey has revealed possible bat presence in the loft spaces. A full survey will be carried out in May with a view to works commencing on site during November 2009 and being completed at Easter 2010.

LINK(S) TO CORPORATE STRATEGY

 

Yes

No

Hampshire safer and more secure for all

_

 

Maximising well-being

_

 

Enhancing our quality of place

_

 

This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because:

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

Published works.

Documents which disclose exempt or confidential information as defined in the act.

      TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules Project Appraisal

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Abbott's Ann C of E Primary School

Andover -

New School

Tender

March 09

Feb 2010

3,380,000

+ 31,000

3,411,000

Capital Prog 08/09 3,293,000

School devolved capital 62,000

P&R 2008/09 contribution 25,000

              3,380,000

Capital Prog 08/09 31,000

      3,411,000

Aldworth Science College, Basingstoke -

fire precaution and lighting improvement works

Complete

August 08

Dec 08

      *735,000

+ s/f 40,000

      775,000

Capital Prog 08/09 258,000

P&R NDS Fire Precs 07/08 245,000

P&R LL Cap Reps 08/09 100,000

P&R NDS Condition 08/09 90,000

CS Cap Prog 08/09

(14-19 allocation) 42,000

+ additional school d/c 40,000

              775,000

Bentley Primary School -

extension to provide new hall

Tender

April 09

Oct 09

      566,000

Capital Prog 08/09 258,000

School devolved capital 308,000

              566,000

The Bridge Education Centre, Eastleigh

- extension, refurbishment, reclad, reroof

On hold awaiting completion of lease

April 09

March 10

*2,526,885

Capital Programme 07/08 1,415,000

P&R Capital Repairs 07/08 322,000

Devolved capital budget 134,000

CAMHS (tbc) 455,000

2,326,000

Crestwood College for Business and Enterprise

Eastleigh

- landscape improvements

On site

Jan 09

May 09

*450,000

Capital Prog 08/09 450,000

Crestwood College for Business and Enterprise

Eastleigh

- internal refurbishment (food catering)

Design

April 09

June 09

      260,000

14-19 funding (2007/08) 110,000

NDS Modernisation (2007/08) 15,000

School devolved capital 105,000

P&R Landscape fund

(2008/09) 30,000

              260,000

Elvetham Heath Primary School

Fleet

- classroom extension

On site

July 08

April 09

      3,031,000

      +20,000

Capital Programme 08/09 3,031,000

School devolved capital 20,000

          3,051,000

Freegrounds Infant School, Hedge End

- classroom extension

On site

June 08

Feb 09

      *607,892

Capital Programme 07/08 515,000

School 93,000

P&R Capital Repairs 08/09 35,000

              643,000

Hamble Sixth Form College - new school

Design

March 09

March 10

      6,837,000

Capital Programme 07/08

(LSC) 6,837,000

Henry Beaufort School, Winchester -

provision of Synthetic Turf Pitch (STP)

Design

Summer 09

Oct 09

      550,000

School Funding

(community funds/

devolved capital) 110,000

Winchester City Council 103,000

Football Foundation

Grant funding 337,000

              556,000

Knights Enham Infant and Junior Schools

Andover

- extension and refurbishment

On site

July 08

July 09

      3,638,000

Capital Programme 08/09 3,320,000

Schools - devolved capital 213,000 P&R contributions 08/09 77,000

NDS Condition 08/09 28,000

              3,638,000 3,638

Marnel Community Infant and Junior Schools, Basingstoke

- extension of both schools

Complete

March 08

Jan 09

*3,149,940

Capital Programme 07/08 3,149,940

Capital Programme 07/08 227,373

              3,377,313

The Mountbatten School and Language College

Romsey

- entrance improvements

Complete

Nov 08

Feb 09

      200,000

Environment Safe Routes

to School budget 100,000

Capital Prog 08/09 100,000

    200,000

Park Gate Primary School - two-class extension and internal refurbishments/ alterations

On site

Jan 09

Oct 09

      *710,000

Capital Programme 08/09 457,000

School - devolved capital

/LMS 204,500

SAI 49,000

    710,500

Portchester Community School

- fire evacuation lift

Complete

Aug 08

Main scheme: Dec 08

Additional works:

March 09

      *445,100

      +73,446

      518,546

Capital Prog 07/08 (SAI) 309,100

Landlord P&R Capital

Repairs budget 7,500

NDS Engineering

Fire Precautions budget 21,000

NDS Fire Precaution

Budget 2007/08 107,500

              445,100

Plus funding for additional works:

P&R Capital Repairs 08/09 50,282

Management Partnership

Budget 5,500

Children's Services 10,000

P&R Cap Repairs 7,664

              73,446

Robert May's School, Hook -

provision of a Synthetic Turf Pitch (STP)

Design

TBC

TBC

      553,000

Children's Services

Capital Programme 08/09 146,000

School devolved capital 93,000

Football Foundation grant 314,000

                      553,000

Roman Way Primary School - extension

Design

April 09

Nov 09

      1,563,000

Children's Services

Capital Programme 08/09 1,423,000

School (devolved capital) 117,000

P&R 08/09 23,000

                      1,563,000

Sarisbury C of E Junior School

Sarisbury Green

- classroom extension

Complete

July 08

March 09

      531,611

+ 50,000

      581,611

Capital Programme 08/09 424,611

Children's Services

Strategic Workforce 07/08 29,000

School funding (dev cap) 78,000

+ School funding (dev cap) 50,000

              581,611

Shamblehurst Primary School, Hedge End

- new permanent classroom and internal refurbishment/reconfiguration works

Complete

July 08

March 09

      515,000

Capital Programme 07/08 515,000

Sopley Primary School - classroom extension

Design

Nov 09

Easter 2010

      446,000

Capital Programme 2008/09 258,000

School (devolved capital) 93,000

P&R Capital Repairs programme 2008/09 (boiler room) 55,000

P&R Capital Repairs programme 2008/09 (cesspool) 20,000

Capital Programme 2008/09 (cesspool) 20,000

        446,000

          446

Wildern Secondary School

Hedge End

- dining extension

On site

Aug 08

April 09

      780,000

Capital Programme 07/08 601,000

School 179,000

        780,000

Wildern Secondary School - food tech and textile room refurbishment

Tender

March 09

Sept 09

      450,000

School (Revenue Budget) 450,000

Wyvern Technology College

Eastleigh - J Track

On site

Feb 09

Sept 09

      358,000

Capital Programme 08/09 107,000 107 18 125

School devolved capital 94,000

Eastleigh Borough Council 132,000

SITA Trust (Landfill Tax) 8,000

Capital Programme contingency -

(subject to tender return) 17,000

        358,000

                      Appendix 2

Other Schemes in the Children's Services Capital Programme

The following schemes are included in the Children's Services 2008/09 Capital Programmes and the Acting Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Lead Member for Children's Services (Education) or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

East Anton Primary School

7,000

Meadowlands Primary School

2,258

Picket Twenty Primary School

6,000

West of Waterlooville

tbc

SECONDARY

Crofton Secondary School

830

Ringwood Secondary School

tbc

Wildern Secondary School

tbc

SPECIAL

Dove House

East New Forest Special School

400

11,200

EDUCATION OTHER THAN AT SCHOOLS

Children's Centres Stage III

TBC

NDS MODERNISATION

Stanmore Primary

250