HAMPSHIRE COUNTY COUNCIL
Decision Report:
Decision Maker: |
Executive Lead Member for Children's Services (Education) |
Date of Decision: |
12 March 2009 |
Decision Title: |
Major Projects Status Report |
Decision Reference: |
563 |
Report From: |
Acting Director of Property, Business and Regulatory Services |
Contact name: |
Steve Clow | ||
Tel: |
01962 847858 |
Email: |
steve. [email protected] |
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.
1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Acting Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.
2. Recommendations
2.1 That additional works and funding at the following schools are approved:
Abbott's Ann Primary School
Elvetham Heath Primary School
Knights Enham Infant and Junior Schools
Marnel Infant and Junior Schools
Park Gate Primary School
Portchester Secondary School
Sarisbury Junior School
2.2 That the overall position of the major capital projects being undertaken by the Acting Director of Property, Business and Regulatory Services be approved.
3. Completed Schemes
3.1 Since the last meeting of the Executive Lead Member for Children's Services (Education), schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Aldworth Science College December 2008
Marnel Infant and Junior School January 2009
Mountbatten School and Language College February 2009
Portchester Community School December 2008
Sarisbury Junior School March 2009
Shamblehurst Primary School March 2009
4. Additional Works and Funding Added Post Contract
The following schemes have had further funding added to the contract for specific additional works.
4.1 Abbott's Ann Primary School - an additional £31,000 has been allocated from the Capital Programme 2008/09 as tenders were returned higher than anticipated.
4.2 Elvetham Heath Primary - the school have contributed £20,000 of devolved capital to fund additional internal alterations.
4.3 Knights Enham Infant and Junior Schools - an additional £203,000 has been allocated from the 2008/09 Capital Programme for post contract variations requested by the client
4.4 Marnel Infant and Junior - approvals for additional works are as follows: £
Pre-construction design agreement (Education 14.9.07) 214,030
Direct order for tree/pond works (Education 11.2.08) 4,270
Smart Metering (NDS Education) 9,073
£227,373
4.5 Park Gate Primary School - it was noted in the project appraisal approved by the Executive Member on 18 December 2008 that, subject to school funding, internal refurbishment works including the reconfiguration of four existing classrooms to improve layout and acoustics may be included in the contract. The school has now made an additional contribution to cover the proposed works and the total contract sum is now £710,000.
4.6 Portchester Secondary School - the following additional works were added to the scheme and will be completed during March 2009:
Re-roofing P&R Capital Repairs 08/09 50,282
Management Partnership Budget 5,500
Youth Club
(kitchen refurb) Children's Services Capital Prog 10,000
Additional external
repointing works P&R Cap Repairs 7,664
73,446
4.7 Sarisbury CE Junior School - the main scheme is now complete, however the school have added an additional £50,000 of their devolved capital for works to upgrade four pupils toilets. It is anticipated that these works will be completed during March 2009.
5. Additional Works and Funding added at Pre Contract Stage
5.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Children's Services and Policy and Resources.
5.2 Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
6. Programme updates
6.1 Abbott's Ann Primary School - due to a delay in signing of the lease agreement, it is now anticipated that the scheme will commence on site in March 2009. The anticipated completion date for the scheme is now February 2010.
6.2 Bentley Primary School - the pre-tender estimate for the project was substantially over the agreed funding (approx 20%). The scheme is currently out to tender and consideration is being given to possible savings and additional funding should the tenders not be returned within the existing budget. It is now anticipated that works will commence on site during April 2009 and complete during October 2009.
6.3 The Bridge Education Centre, Eastleigh - tenders have been returned for this scheme. However, the programme is being revisited in light of a delay in settling the terms of the lease with the NHS. It is now anticipated that works will commence on site during April 2009 and complete during March 2010.
6.4 Knights Enham Infant and Junior Schools - the programme has been extended by eight weeks to carry out post-contract variations requested by the client.
6.5 Robert May's - the programme has been delayed pending the outcome of a grant bid to the Football Foundation.
6.6 Sopley Primary - an ecology survey has revealed possible bat presence in the loft spaces. A full survey will be carried out in May with a view to works commencing on site during November 2009 and being completed at Easter 2010.
LINK(S) TO CORPORATE STRATEGY | ||
Yes |
No | |
Hampshire safer and more secure for all |
_ |
|
Maximising well-being |
_ |
|
Enhancing our quality of place |
_ |
|
This proposal does not link to the Corporate Strategy but, nevertheless, requires a decision because: |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
Published works.
Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules Project Appraisal
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Abbott's Ann C of E Primary School Andover - New School |
Tender |
March 09 |
Feb 2010 |
3,380,000 + 31,000 3,411,000 |
Capital Prog 08/09 3,293,000 School devolved capital 62,000 P&R 2008/09 contribution 25,000 3,380,000 Capital Prog 08/09 31,000 3,411,000 |
Aldworth Science College, Basingstoke - fire precaution and lighting improvement works |
Complete |
August 08 |
Dec 08 |
*735,000 + s/f 40,000 775,000 |
Capital Prog 08/09 258,000 P&R NDS Fire Precs 07/08 245,000 P&R LL Cap Reps 08/09 100,000 P&R NDS Condition 08/09 90,000 CS Cap Prog 08/09 (14-19 allocation) 42,000 + additional school d/c 40,000 775,000 |
Bentley Primary School - extension to provide new hall |
Tender |
April 09 |
Oct 09 |
566,000 |
Capital Prog 08/09 258,000 School devolved capital 308,000 566,000 |
The Bridge Education Centre, Eastleigh - extension, refurbishment, reclad, reroof |
On hold awaiting completion of lease |
April 09 |
March 10 |
*2,526,885 |
Capital Programme 07/08 1,415,000 P&R Capital Repairs 07/08 322,000 Devolved capital budget 134,000 CAMHS (tbc) 455,000 2,326,000 |
Crestwood College for Business and Enterprise Eastleigh - landscape improvements |
On site |
Jan 09 |
May 09 |
*450,000 |
Capital Prog 08/09 450,000 |
Crestwood College for Business and Enterprise Eastleigh - internal refurbishment (food catering) |
Design |
April 09 |
June 09 |
260,000 |
14-19 funding (2007/08) 110,000 NDS Modernisation (2007/08) 15,000 School devolved capital 105,000 P&R Landscape fund (2008/09) 30,000 260,000 |
Elvetham Heath Primary School Fleet - classroom extension |
On site |
July 08 |
April 09 |
3,031,000 +20,000 |
Capital Programme 08/09 3,031,000 School devolved capital 20,000 3,051,000 |
Freegrounds Infant School, Hedge End - classroom extension |
On site |
June 08 |
Feb 09 |
*607,892 |
Capital Programme 07/08 515,000 School 93,000 P&R Capital Repairs 08/09 35,000 643,000 |
Hamble Sixth Form College - new school |
Design |
March 09 |
March 10 |
6,837,000 |
Capital Programme 07/08 (LSC) 6,837,000 |
Henry Beaufort School, Winchester - provision of Synthetic Turf Pitch (STP) |
Design |
Summer 09 |
Oct 09 |
550,000 |
School Funding (community funds/ devolved capital) 110,000 Winchester City Council 103,000 Football Foundation Grant funding 337,000 556,000 |
Knights Enham Infant and Junior Schools Andover - extension and refurbishment |
On site |
July 08 |
July 09 |
3,638,000 |
Capital Programme 08/09 3,320,000 Schools - devolved capital 213,000 P&R contributions 08/09 77,000 NDS Condition 08/09 28,000 3,638,000 3,638 |
Marnel Community Infant and Junior Schools, Basingstoke - extension of both schools |
Complete |
March 08 |
Jan 09 |
*3,149,940 |
Capital Programme 07/08 3,149,940 Capital Programme 07/08 227,373 3,377,313 |
The Mountbatten School and Language College Romsey - entrance improvements |
Complete |
Nov 08 |
Feb 09 |
200,000 |
Environment Safe Routes to School budget 100,000 Capital Prog 08/09 100,000 200,000 |
Park Gate Primary School - two-class extension and internal refurbishments/ alterations |
On site |
Jan 09 |
Oct 09 |
*710,000 |
Capital Programme 08/09 457,000 School - devolved capital /LMS 204,500 SAI 49,000 710,500 |
Portchester Community School - fire evacuation lift |
Complete |
Aug 08 |
Main scheme: Dec 08 Additional works: March 09 |
*445,100 +73,446 518,546 |
Capital Prog 07/08 (SAI) 309,100 Landlord P&R Capital Repairs budget 7,500 NDS Engineering Fire Precautions budget 21,000 NDS Fire Precaution Budget 2007/08 107,500 445,100 Plus funding for additional works: P&R Capital Repairs 08/09 50,282 Management Partnership Budget 5,500 Children's Services 10,000 P&R Cap Repairs 7,664 73,446 |
Robert May's School, Hook - provision of a Synthetic Turf Pitch (STP) |
Design |
TBC |
TBC |
553,000 |
Children's Services Capital Programme 08/09 146,000 School devolved capital 93,000 Football Foundation grant 314,000 553,000 |
Roman Way Primary School - extension |
Design |
April 09 |
Nov 09 |
1,563,000 |
Children's Services Capital Programme 08/09 1,423,000 School (devolved capital) 117,000 P&R 08/09 23,000 1,563,000 |
Sarisbury C of E Junior School Sarisbury Green - classroom extension |
Complete |
July 08 |
March 09 |
531,611 + 50,000 581,611
|
Capital Programme 08/09 424,611 Children's Services Strategic Workforce 07/08 29,000 School funding (dev cap) 78,000 + School funding (dev cap) 50,000 581,611 |
Shamblehurst Primary School, Hedge End - new permanent classroom and internal refurbishment/reconfiguration works |
Complete |
July 08 |
March 09 |
515,000 |
Capital Programme 07/08 515,000 |
Sopley Primary School - classroom extension |
Design |
Nov 09 |
Easter 2010 |
446,000 |
Capital Programme 2008/09 258,000 School (devolved capital) 93,000 P&R Capital Repairs programme 2008/09 (boiler room) 55,000 P&R Capital Repairs programme 2008/09 (cesspool) 20,000 Capital Programme 2008/09 (cesspool) 20,000 446,000 446 |
Wildern Secondary School Hedge End - dining extension |
On site |
Aug 08 |
April 09 |
780,000 |
Capital Programme 07/08 601,000 School 179,000 780,000 |
Wildern Secondary School - food tech and textile room refurbishment |
Tender |
March 09 |
Sept 09 |
450,000 |
School (Revenue Budget) 450,000 |
Wyvern Technology College Eastleigh - J Track |
On site |
Feb 09 |
Sept 09 |
358,000 |
Capital Programme 08/09 107,000 107 18 125 School devolved capital 94,000 Eastleigh Borough Council 132,000 SITA Trust (Landfill Tax) 8,000 Capital Programme contingency - (subject to tender return) 17,000 358,000 |
Appendix 2
Other Schemes in the Children's Services Capital Programme
The following schemes are included in the Children's Services 2008/09 Capital Programmes and the Acting Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Lead Member for Children's Services (Education) or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
East Anton Primary School |
7,000 |
Meadowlands Primary School |
2,258 |
Picket Twenty Primary School |
6,000 |
West of Waterlooville |
tbc |
SECONDARY
Crofton Secondary School |
830 |
Ringwood Secondary School |
tbc |
Wildern Secondary School |
tbc |
SPECIAL
Dove House East New Forest Special School |
400 11,200 |
EDUCATION OTHER THAN AT SCHOOLS
Children's Centres Stage III |
TBC |
NDS MODERNISATION
Stanmore Primary |
250 |