HAMPSHIRE COUNTY COUNCIL
Decision Report
Decision Maker: |
Executive Member - Environment | ||
Date of Decision: |
30 April 2009 | ||
Decision Title: |
Capital Programme 2009/10 - Sub Programmes | ||
Decision Reference: |
701 | ||
Report From: |
Director of Environment | ||
Contact Name: |
Helen Ackerman | ||
Telephone: |
01962 857810 |
E-mail: |
|
EXECUTIVE SUMMARY
1) Summary of Decision Area
1.1. This report seeks approval for the proposed Capital Programme sub programmes for 2009/10 to support the County Council's priorities of developing safe communities, ensuring access to services and protecting local distinctiveness and diversity.
2) Issues Covered in Report
2.1. This report sets out the proposed transport, maintenance and bridges, waste and environmental sub programmes. Some elements of the transport sub programmes (minor works and minor traffic management works) were considered at the spring round of Hampshire Action Teams' (HAT) meetings.
2.2. A reduced level of funding available for the Quality of Place Sub Programme in 2010/11 has resulted in a stretched programme between 2008/09 and 2009/10.
3) Recommendations
It is recommended that:
3.1. The following proposed 2009/10 Environment Capital Programme sub programmes schemes and allocations set out in Appendices 1 to 8 of this report be approved:
· Bridge Strengthening and Maintenance Programme, £4,234,000 (Appendix 1a); and · Major Maintenance - Winchester High Street, £1,500,000; |
(ii) Casualty Reduction Programme £3,000,000 (Appendix 2); |
(iii) Safer Routes to School Programme £1,000,000 (Appendix 3); |
(iv) Minor Traffic Management Programme £520,000 (Appendix 4); |
(v) Minor Works (under £25,000 each) total £311,000 (Appendix 5); |
(vi) Environmental programmes £387,000 (Appendix 6); |
(vii) Community Transport Programme £250,000; |
(viii) Quality Bus Partnership Programme £100,000 (Appendix 7); and (ix) Waste Management Programme £5,066,000 (Appendix 8). |
MAIN REPORT
1) Contextual Information
1.1. The Capital Programme 2009/10 to 2011/12 was approved by the Executive Member for Environment on 20 January 2009, which included allocations for sub programmes. This report provides details of these programmes for approval for 2009/10.
2) Key Issues
2.1. This report sets out the proposed transport, maintenance and bridges, waste and quality of place sub programmes.
2.2. Following the impact of the economic downturn and the consequential loss of capital receipts to support the locally resourced capital programme, existing capital approvals for two years have been spread over three years. This has been managed within the Environment Department through reducing funding made available for the Quality of Place, Waste and Transport capital programmes (including some of the sub programmes set out in this paper).
3) Proposed Sub Programmes
Capital Maintenance Programme (£28,402,000)
3.1. The Highway Maintenance programme is funded from the revenue and capital programmes. Revenue funding typically covers reactive repairs, cyclic maintenance, winter salting, etc. The capital element provides structural maintenance of roads and bridges and larger, planned schemes and is funded through the Local Transport Plan (LTP) (Government grant and borrowing) and local resources. Appendix 1 provides more detail of the financially significant elements.
Bridge Strengthening and Maintenance Programme (£4,234,000)
3.2. Included within the capital maintenance programme, bridge strengthening and maintenance and covers the following four key areas:
(i) Structural maintenance;
(ii) Road restraint systems (eg crash barriers);
(iii) Strengthening/replacements; and
(iv) Design, assessment and feasibility.
The proposed programme is set out in more detail in Appendix 1a.
3.3. The Structural maintenance programme is mainly identified and prioritised using bridge inspection data, in accordance with the national Code of Practice. The programme includes ongoing contracts such as painting and expansion joint maintenance and also accident damage remedial works and footbridge maintenance.
3.4. The Road Restraint System schemes are prioritised with national standards and the highest scoring sites are jointly agreed with Network Rail.
3.5. The strengthening/replacement schemes are identified from the assessment programme for 40 tonne vehicles and inspections. There is no nationally agreed prioritisation process, but that followed by the County Council is in line with other local authorities.
3.6. Also included is a programme of Design, Assessment and Feasibility which is generally linked to the above projects. It includes other initiatives instigated by Government, such as assessment for heavy loads, which is a rolling programme prioritised to `A' roads and heavy load routes.
Major Maintenance Scheme £2,200,000 (£1,500,000 Maintenance, £500,000 Winchester City Council, £200,000 Developer Contributions)
3.7. Included within the capital maintenance programme is the Winchester High Street major maintenance project. The proposed refurbishment will include resurfacing the High Street and side streets in a high quality, attractive, safe and durable material and improving the sub-structure where conditions are poor. A project appraisal was approved by the Executive Member for Policy and Resources on 11 September 2008. Work is expected to start in the autumn.
Casualty Reduction Programme (£3,000,000 Local Transport Plan)
3.8. This long established engineering programme has played a major part in improving the safety record on Hampshire's roads over the last decade or more. The programme is completely based on analysis of accident statistics and the site characteristics of locations with poor accident records.
3.9. The Casualty Reduction Programme is orientated to maintaining the good performance to date towards meeting the Local Area Authority (LAA) Casualty Reduction Targets. The Killed and Seriously Injured (KSI) target is also a priority in the Corporate Improvement Plan. The proposed programme will help to prevent an upturn and maintain the current downward trend in KSI numbers. It concentrates on identifying potential savings for the most effective split between the four elements of the programme, eg a weighting on fatal and serious accidents/casualties is given as a priority and the Casualty Reduction Partnership is based on investigating fatal and potential fatal accidents only. This type of casualty has reduced since the programme was formed in April 2003 as a partnership with the Police.
3.10. The breakdown of the Casualty Reduction budget, as proposed, is considered appropriate to maximise the best rates of return and achieve the largest reduction in KSIs possible.
3.11. Appendix 2 provides a summary of the breakdown and sets out the individual schemes for surface dressing (part of Carriageway Surface Treatment programme) and a provisional Low Cost programme, which is currently under consultation.
3.12. The `reactive' casualty reduction partnership element of this programme is implemented during the year on a site by site basis following fatal, or near fatal accidents. Similarly, the `other' and `retexturing' programmes are reactive to skid testing results, and by their nature it is not possible to set out a programme for either in advance.
3.13. The capital safety audit programme will be brought forward for approval in June within the first quarter monitoring report. The pre-patching programme for 2010/11 sites will not be available until November as surveys will be undertaken during this year.
Safer Routes to School Programme (£1,000,000 LTP and £157,700 Developer Contributions)
3.14. In response to Central Government guidance for every school to have a School Travel Plan (STP) by the end of the decade, the Environment Department is striving to meet that target by working closely with the schools and helping them develop and implement their STPs. In March 2009, 398 or 66% of schools (398 out of 601) had approved STPs. A further 42 travel plans are expected to be approved shortly bringing the total to 73% (440 schools).
3.15. The proposed programme is set out in Appendix 3. This programme will deliver 33 improvement schemes, plus a further 20-30 small-scale minor projects, such as cycle racks or lockers which have proven popular in the past. A further eight schemes will be designed this year for delivery in 2010/11. All of these sites are schools with approved STPs.
Minor Traffic Management Programme (£520,000 LTP)
3.16. This programme relates to schemes that are small in value, often related to Traffic Regulation Orders, speed limits and signing/lining, which may be undertaken directly by the County Council or by districts under the Traffic Management Agency arrangements.
3.17. Appendix 4 sets out the list of schemes that are complete and ready for implementation as well as those to be investigated during the year. Within the overall budget, an allocation of £100,000 for fees associated with this sub programme has been top-sliced to cover staff time.
Minor Works Programme (£311,000 LTP funding and potentially £100,000 Developer Contributions)
3.18. This programme relates to schemes that are generally small highway improvements, such as missing footway links, pedestrian refuges or sightline improvements, etc, that cost below £25,000. As demand for these schemes greatly exceeds the available funding each year each HAT has been asked to identify their top priority.
3.19. Appendix 5 sets out the list of schemes to be implemented this year. Not included, at present, is the list of small value developer funded schemes that have been identified for delivery during the year. Work is ongoing to prepare a programme for the first quarter monitoring report in June.
Quality of Place Programme (£387,000 Local Resources)
3.20. When setting the 2008/09 budget, the indicative allocation for 2009/10 for Quality of Place was £1,630,000 including £200,000 from within Highways Maintenance, £1,043,000 from local resources for the former Environmental Improvements programme and £387,000 carried forward from 2007/08. The highways maintenance element has been earmarked towards the A3 overspend, and all bar the carry forward from 2007/08 has been removed from the programme in response to the reduction in local resources. There are no new resources available in 2010/11, but in 2011/12 there is an indicative allocation of £720,000. This will need to be reviewed following a reassessment of the financial situation as the economy recovers.
3.21. The programme proposed in Appendix 6 includes schemes that are either well advanced, or where external funding has been secured, or where commitments have been made. In addition to this allocation of £387,000, the Quality of Place Programme is forecast to carry forward £1,973,000 of prior year approvals into 2009/10 which is committed to existing projects.
Community Transport Programme (£250,000 LTP)
3.22. This county-wide programme supports and develops a number of community transport schemes around Hampshire that in recent years has included the provision of new and replacement minibuses. Through the provision of grants to voluntary organisations, buying vehicles and equipment, etc the County Council supports the network of existing community groups and stakeholders in Hampshire to provide specialised or focused transport to ensure that everyone can access important services and local amenities.
3.23. The County Council has commissioned consultants to undertake a review of community transport services in Hampshire to recommend options for the future delivery of services. This will evaluate the County Council's existing approach, highlight good practice and examine alternative methods of delivery elsewhere around the country. The completed review is expected in the spring and will help to determine how the 2009/10 allocation can best be used. A programme is scheduled to be submitted for approval in September 2009.
Quality Bus Partnership Programme (£100,000 LTP)
3.24. Since 1999 this programme has supported a number of Quality Bus Partnerships that enable the County Council to work in partnership with the county's bus operators to improve and promote local bus services in Hampshire.
3.25. The budget has been reduced by £200,000 in order to provide resources towards the A3 Major Scheme overspend.
3.26. The programme in Appendix 7 seeks to `fill in the gaps' in previously implemented partnership routes, in Havant and Basingstoke, aiming at individual stops where raised kerbs, new shelters and improved passenger information will be beneficial. Additionally, within the county-wide QBP heading, bus stops will be improved in Winchester, Rushmoor and Andover.
Waste Management Programme (£5,066,000 Local Resources/Grant)
3.27. The overall sum available for waste management capital expenditure during 2009/10 is £7.956 million. This comprises new approvals of £4.860 million included in the 2009/10 capital programme, together with £2.490 million from forecast unused approvals carried forward from previous years and a £0.606 million Department for the Environment, Food and Rural Affairs contribution towards household waste recycling centre improvements.
3.28. The proposals in Appendix 8 set out a programme for 2009/10 totalling £5.066 million, although only some £2 million of this is expected to be spent during the current financial year.
3.29. A balance of £2.890 million approvals remains unallocated in 2009/10 which, together with the capital programme provision of £0.840 million for 2010/11, gives a total of £3.730 million approvals currently unallocated across 2009/10-2010/11 for future years' schemes.
4) Conclusions
4.1 This report is the final stage of preparing the department's capital programme. Apart from the community transport programme, which will be brought forward in September, and the low cost safety programme, amendments to the minor traffic management and minor works programme, which will form part of the first quarter monitoring report in June, this completes the sub programme plans for the year.
4.2 Expenditure and programme delivery will be carefully monitored throughout the year and progress will be reported as part of regular Capital Programme quarterly monitoring.
5) Recommendations
Please see Executive Summary for recommendations.
1988Rpt/701/HA
CORPORATE OR LEGAL INFORMATION:
LINKS TO THE CORPORATE STRATEGY | |||
Yes |
No | ||
Hampshire safer and more secure for all |
|||
Corporate Business plan link no (if appropriate) |
|
||
Maximising well-being |
|||
Corporate Business plan link no (if appropriate) |
|
||
Enhancing our quality of place |
|||
Corporate Business plan link no (if appropriate) |
|
||
OTHER SIGNIFICANT LINKS: | ||
Links to Previous member decisions: | ||
Title |
Ref |
Date |
Proposed Capital Programme 2009 - 2012 |
491 |
20 January 09 |
Section 100 D - Local Government Act 1972 - background documents | |
The following documents discuss facts or matters on which this report, or an important part of it, is based and have been relied upon to a material extent in the preparation of this report. (NB: the list excludes published works and any documents which disclose exempt or confidential information as defined in the Act.) | |
Document |
Location |
None |
|
COMPREHENSIVE RISK & IMPACT ASSESSMENT:
1) Equalities Impact Assessment:
The proposals in this report are derived from the departmental service plans and LTP objectives and are in accordance with the budget strategy and the County Council's financial management policy. An impact assessment of the departmental service plans and the financial management policy has been carried out and the proposals in this report are not considered to be discriminatory.
2) Impact on Crime and Disorder:
a) Some of the schemes within the capital programme may contribute to a reduction in the fear of crime that may have been identified by local communities during consultation or development stages.
3) Climate Change:
The Environment Department will be developing a methodology for measuring the impact of the capital programme on our carbon footprint during 2009.
Appendix 1
Element of programme |
£million |
Bridge - structural maintenance (incl £0.1m S31 Grant A339) |
4.2 |
Major maintenance scheme - Winchester High Street |
1.5 |
Principal (A road) - planned maintenance schemes |
2.8 |
Principal road - performance specifications |
1.5 |
Non principal road (B, C and U) - planned maintenance schemes |
8.0 |
Surface dressing - (roads and footways) |
2.9 |
Minor structural repairs - (footways, carriageways, drainage) |
4.5 |
Pot Hole Repairs - additional funding |
1.0 |
S31 Grant A339 |
0.2 |
New Forest - cattle grids and fencing |
0.2 |
Miscellaneous and contingencies |
1.1 |
Reserves |
0.5 |
Total |
£28.4 million |
Road |
Town/Area |
||||
STRUCTURAL MAINTENANCE |
|||||
Minor works (THC & contract) |
Various |
County wide |
|||
Major works (IWF and contract) |
Various |
County wide |
|||
Paint Contracts |
Various |
County wide |
|||
Major footbridge painting |
Various |
Basingstoke & Fareham |
|||
Expansion joints |
Various |
Basingstoke, Fareham, Eastleigh |
|||
Accident damage |
Various |
County wide |
|||
Footbridges |
Various |
County wide |
|||
Coastal Work |
Various |
County wide |
|||
Principal inspections |
Various |
County wide |
|||
NR Works Agreements |
Various |
County wide |
|||
£1,700,000 | |||||
DESIGN, ASST. & FEASIBILITY |
|||||
County assessments + reviews |
Various |
County wide |
|||
Red Post |
Test Valley |
||||
Malthouse |
Hart |
||||
Holmsley Rail |
New Forest |
||||
Knights |
Basingstoke |
||||
Network Rail |
Various |
County wide |
|||
Rail Property |
Various |
County wide |
|||
Coastal structures |
Various |
County wide |
|||
Slope surveys |
Various |
County wide |
|||
£500,000 | |||||
SAFETY IMPROVEMENTS |
|||||
Road/rail |
Various |
County wide |
|||
Road/road |
Various |
County wide |
|||
Parapet upgrades |
Various |
County wide |
|||
£600,000 | |||||
STRENGTHEN/REPLACE |
|||||
Trevetts Lane |
Stoke Charity, Winchester |
||||
Ship Lane |
Bishops Sutton, Winchester |
||||
Westwood Gardens |
Ch Ford, Eastleigh |
||||
Shawford Mill |
Shawford, Winchester |
||||
Broadwoods Lane |
Wellow, Test Valley |
||||
Wallop Ford |
Middle Wallop, TV |
||||
Network Rail W10 imprvts |
Various |
Winchester |
|||
Retaining walls |
Various |
County wide |
|||
Other strengthenings |
Various |
County wide |
|||
Edge strengthening/protection |
Various |
County wide |
|||
£1,400,000 | |||||
Unallocated contingency |
£34,000 | ||||
TOTAL |
£4,234,000 | ||||
Appendix 2
Carriageway Surface Treatment Programme |
£1,500,000 | |
· Surface Dressing (see below) |
£1,100,000 |
|
· Retexturing (reactive) |
£150,000 |
|
· Pre Patching (on next yr sites) |
£225,000 |
|
· Other works (Skid testing during yr) |
£25,000 |
|
Low Cost Programme |
£750,000 | |
Capital Safety Audit Programme |
£400,000 | |
Reactive Casualty Reduction Partnership |
£350,000 | |
£3,000,000 |
(i) Carriageway Surface Treatment Programme (£1,500,000)
Surface Dressing £1,100,000
Basingstoke |
£estimate |
Bloswood Lane, Whitchurch, from south of A34 bridge to 50m west of Harrow Way junction |
9,000 |
Cufaude Lane, Cufaude, from Silchester Road junction to Lime Tree Way junction |
22,500 |
A339 Kingsclere Road, from anti-skid south of Wolverton to Pitt Hall Farm |
11,000 |
A339 Alton Road, from Winslade Farm Lane to Bagmore Lane junction |
33,000 |
B3400 Worting Road, from Buckskin Lane roundabout to Roman Way junction |
9,500 |
Bidden Road - Bidden Water bend 200m through bend |
19,500 |
Roman Road, from Winklebury Way to A339 roundabout |
15,000 |
Estimated budget for Basingstoke |
£119,500 |
East Hants |
£estimate |
A339, 500m through bend south of Spain Lane junction |
9,000 |
East Meon Road, Clanfield, bend between North Cottages and Dead Woman's Gate |
10,000 |
Estimated budget for East Hants |
£19,000 |
Eastleigh |
£estimate |
B3037 Bishopstoke Road, Eastleigh, from A335 Twyford Road roundabout to Riverside junction |
11,500 |
B3037 Mortimers Lane, Fair Oak, from B3354 Botley Road junction to B2177 Winchester Road junction |
32,500 |
B3397 Hamble Lane, Hamble, from A3025 roundabout to Kings Avenue junction |
34,500 |
Estimated budget for Eastleigh |
£78,500 |
Fareham |
£estimate |
A32 Wickham Road/Hoads Hill, Fareham, from north of Dean Farm entrance to North Hill roundabout |
10,000 |
B3385 Newgate Lane, from B3334 Peel Common roundabout to A32 junction |
27,500 |
Dores Avenue, bend near Buriton Close junction |
5,000 |
Estimated budget for Fareham |
£42,500 |
Gosport |
£estimate |
Forest Way, from A32 junction to Tichborne Way junction |
6,000 |
Gomer Lane, from Privett Road roundabout to Browndown Lane roundabout |
10,000 |
Wych Lane, from A32 junction to Gregson Avenue roundabout |
10,500 |
B3334 Rowner Road, from Grange Road roundabout to surface change west of Gorslands Way |
5,500 |
A32 Brockhurst Road, from Elson Road roundabout to Avery Lane junction |
100,000 |
Estimated budget for Gosport |
£132,500 |
Hart |
£estimate |
B3272 Reading Road, from Cricket Hill Lane roundabout to Derby Green Road roundabout |
13,500 |
Dora's Green Lane, from Heath Lane junction to Crondall Lane |
17,500 |
Estimated budget for Hart |
£31,000 |
Havant |
£estimate |
A259 Havant Road, from Selangor Avenue junction to B2148 roundabout |
19,500 |
Estimated budget for Havant |
£19,500 |
New Forest |
£estimate |
B3053 Fawley Road, from A326 roundabout to HRA 50m south of Calshot Road |
25,500 |
Beaulieu Road, Marchwood, from Twiggs Lane junction to Ipsley crossroads |
19,000 |
Gore Road, New Milton, from Walkford Road Lane junction to Hobart Road junction |
16,500 |
Foxcroft Drive/Holbury Drove, from Redna Road junction to Rollestone Road junction |
12,000 |
C10 Picket Plain Common, Burley, from A31 junction to Tyrell's Lane junction |
25,000 |
C49 Ringwood Road, Bransgore, bends between Harrow Road junction to Lyndhurst Road junction |
4,500 |
B3055 Birchy Hill, from HRA bends to staggered crossroads north of Pitmore Lane |
30,000 |
Estimated budget for New Forest |
£132,500 |
Rushmoor |
£estimate |
A323 High St, Aldershot, from Ordnance Road roundabout to rail bridge |
3,000 |
A323 Fleet Road, 100m through bend, west of Laffan's Road |
45,000 |
Estimated budget for Rushmoor |
£48,000 |
Test Valley |
£estimate |
A343 Salisbury Road, from B3084 Station Road junction to Old Stockbridge Road junction |
13,500 |
B3402 Weyhill Road, from A342 roundabout to Salisbury Road roundabout |
25,000 |
Highwood Lane, Romsey |
7,500 |
A3057 Romsey Road, Michelmersh, from 1k north of Mesh Road junction to New Road junction |
46,000 |
Estimated budget for Test Valley |
£92,000 |
Winchester |
£estimate |
A3051 Botley Road, Curbridge, from A334 to Fareham boundary |
32,000 |
C9 Beeches Hill Bishops Waltham, from Shipcote Lane junction to Ashton Lane junction |
11,000 |
A31 Petersfield Road, from Spitfire link to Percy Hobbs roundabout, Winchester |
100,000 |
B3330 Bar End Road, from B3404 junction to A31 roundabout |
14,000 |
A32 Alton Road, from north of West Meon village to West Meon Hut crossroads |
21,500 |
Estimated budget for Winchester |
£186,000 |
TOTAL NAMED SURFACE DRESSING SCHEMES |
£901,000 |
Programme-wide |
£estimate |
Signing and Lining |
55,000 |
Road Stud replacement |
30,000 |
Fees |
50,000 |
Unallocated |
£64,000 |
TOTAL SURFACE DRESSING PROGRAMME |
£1,100,000 |
£estimate | |
Retexturing |
150,000 |
Pre-Patching |
225,000 |
Other Works |
25,000 |
REMAINING SUB-PROGRAMMES |
£400,000 |
TOTAL CARRIAGEWAY SURFACE TREATMENT PROGRAMME |
£1,500,000 |
(ii) Provisional Low Cost Programme (£750,000)
Basingstoke |
£ estimate |
A340 Pamber End to Salters Heath |
3,500 |
A340 Tadley |
3,500 |
B4640 Newtown Straight |
7,500 |
A30 Winchester Road RBT, Basingstoke |
10,000 |
A33 Turgis Green |
2,500 |
A340 Thorneycroft RBT |
2,500 |
A33 Binfield Rbt, Basingstoke |
7,500 |
C23 Harroway Rail Bridge, Andover |
10,000 |
Popley Way / Abbey Road |
3,500 |
Estimated budget for Basingstoke |
£50,500 |
Hart |
£ estimate |
A30 Cricket Hill RBT, Yateley |
5,000 |
B3013 Beacon Hill Road, Crondall |
15,654 |
Estimated budget for Hart |
20,654 |
Rushmoor |
£ estimate |
A3011 at Albans RBT |
15,000 |
A325 Pedestrian Crossing North of Hawley Lane |
9,000 |
Cove Road / Prospect Road RBT |
7,500 |
A323 High Street - Bend o/s Aldershot FC |
6,000 |
B3272 Hawley Lane / Ley Road |
1,000 |
Ordnance Road RBT, Aldershot |
5,000 |
A323 Ash Road / Blackwater Way |
5,000 |
Estimated budget for Rushmoor |
43,500 |
Test Valley |
£ estimate |
A27 North Baddesley to Chilworth |
15,000 |
A342 Route Study |
45,000 |
A3057 / C20 Rownhams (Drop prov 10/11 Prog) |
5,000 |
A343 o/s Garage, Middle Wallop (CSTP RR to Investigate) |
3,500 |
A343 Folly RBT, Andover |
7,500 |
A343 Enham Arch RBT, Andover |
25,000 |
A3057 / Corunna Main, Andover |
2,500 |
A338 Salisbury Road / Watery Lane, Shipton Bellinger |
15,000 |
A3057 / Old Winton Road, Andover |
5,000 |
Estimated budget for Test Valley |
123,500 |
Winchester |
£ estimate |
C465 Easton Lane jw Winnall Manor Lane |
7,500 |
B3335 Highbridge Road / Church Lane, Brambridge |
5,000 |
Easton Lane approach to M3 Jct 9, Winnall |
5,000 |
A33 / B3047 Cart and Horses PH, Kings Worthy |
7,500 |
B2177 / Tangier Road, Bishop's Waltham |
5,000 |
North Walls / Durngate, Winchester |
5,000 |
New Road, Swanmore |
10,000 |
B2150 Hambledon - A32 |
3,000 |
A334 Botley - Curdridge |
7,500 |
Estimated budget for Winchester |
55,500 |
East Hants |
£ estimate |
C84 / C98 Blacknest Crossroads |
7,500 |
A325 / B3002 Fire Station Crossroads, Bordon |
5,000 |
A339 Bentworth Crossroads |
7,500 |
Chalet Hill / Forest Road, Bordon |
2,500 |
B2148 Comely |
7,500 |
Estimated budget for East Hants |
30,000 |
New Forest |
£ estimate |
A354 Martin Drove End |
5,000 |
A35 Hinton - Garage at The Cat and Fiddle PH (NB HHW SP SCH 09/10) |
7,500 |
C97 Butts Ash Xrds, Hythe |
7,500 |
C163 Calmore Road, Totton |
5,000 |
A326 Staplewood Lane, Marchwood |
45,000 |
A337 / Barton Crt Avenue |
1,000 |
Staplewood Lane / Long Lane, Marchwood |
1,000 |
Jacobs Gutter Lane (POSS CSTP) |
1,500 |
A336 Bartley Crossroads |
25,000 |
A337 Cadnam - Lyndhurst |
5,000 |
C63 Deer Leap lane, Longdown |
2,000 |
B3058 / Osborne Road, New Milton |
1,000 |
A337 / Caird Avenue, new Milton (reserve measures not easy) |
10,000 |
A36 Commercial Road / A35 Totton By Pass (CROP IMP accident rec prov 10/11) |
1,000 |
Estimated budget for New Forest |
117,500 |
Eastleigh |
£ estimate |
A27 / A3024 Windhover Rbt |
7,500 |
C354 Passfield Ave, Eastleigh |
5,000 |
M27 Jct 8 |
7,500 |
A335 / M3 jct 13 slips |
7,000 |
A27 / A334 RBT, West End |
2,500 |
A27 Moorhill Road, Telegraph Road |
2,500 |
A3025 / The Plough PH |
2,500 |
Estimated budget for Eastleigh |
34,500 |
Fareham |
£ estimate |
A27 Bridge Road Sarisbury to Park Gate |
7,500 |
A27 Titchfield Byratory - Bends - B3334 approach only |
15,000 |
A27 Quay Street RBT |
3,000 |
Highlands Road / Catisfield Road Area |
5,000 |
A27 Fire Station RBT |
7,000 |
Longfield Avenue / Peak Avenue Road |
10,000 |
Down End Road and Portsdown Hill Road |
3,000 |
A27 St Margarets RBT |
10,000 |
Estimated budget for Fareham |
60,500 |
Gosport |
£ estimate |
Grange Road, Carless Close |
3,000 |
A32 Forton Road (Ferrol Road - George Street) |
6,000 |
A32 / Texaco Garage |
3,000 |
Anglesea Road / Clayhill Road |
4,000 |
Rowner Road |
5,000 |
Estimated budget for Gosport |
21,000 |
Havant |
£ estimate |
B2150 Hambledon Road jw Milton Road RBT |
1,000 |
Estimated budget for Havant |
1,000 |
Currently Unallocated |
41,846 |
TOTAL LOW COST PROGRAMME |
750,000 |
2008/09 ongoing scheme payments |
£100,000 |
||
Programme management |
£100,000 |
||
District |
School |
BCA £ |
EF £ |
Basingstoke |
Bishopswood Infant and Junior |
25,000 | |
Old Basing |
10,000 |
||
Overton Primary |
19,000 | ||
Rucstall Primary (design only) |
10,000 |
||
Silchester |
12,000 |
3,700 | |
St Mary's |
5,000 |
||
Eastleigh |
Cherbourg Primary |
20,000 |
|
Stoke Park Infant |
20,000 |
||
East Hampshire |
Wootey Infant and Junior |
10,000 |
|
Medstead Primary |
25,000 |
||
Weyhill Infant and Junior |
20,000 |
50,000 | |
Fareham |
Neville Lovett (design only) |
10,000 |
|
Redlands Primary |
25,000 |
||
Whiteley Primary |
10,000 |
10,000 | |
Gosport |
Bridgemary Comprehensive (design only) |
10,000 |
|
Holbrook Primary (design only) |
10,000 |
||
Havant |
Barncroft |
15,000 |
|
Cowplain |
20,000 |
||
Emsworth Primary |
20,000 |
||
Hulbert Junior |
20,000 |
||
Park Community |
20,000 |
||
Warren Park Primary |
20,000 |
||
Hart |
Elvetham Heath |
15,000 |
|
Greenfields Junior |
20,000 |
||
Robert Mays (design only) |
10,000 |
District |
School |
BCA £ |
EF £ |
The Arnewood |
25,000 |
||
Noadswood (design only) |
10,000 |
||
Ringwood |
20,000 |
||
Hazel Wood |
10,000 |
||
Rushmoor |
Grange Community |
20,000 |
|
Test Valley |
Broughton Primary |
15,000 |
|
Harrow Way Community (design only) |
10,000 |
||
Nursling Primary |
20,000 |
||
Portway Infant and Junior |
20,000 |
||
Romsey Primary |
25,000 | ||
Testwood Sports College |
20,000 |
||
Winchester |
Bishops Waltham footways |
25,000 | |
Compton All Saints |
20,000 |
||
Kingsworthy Primary |
23,000 |
||
Otterbourne Primary (design only) |
10,000 |
||
Upham Primary |
20,000 |
||
Minor Works |
200,000 |
||
TOTAL |
£1,000,000 |
£157,700 |
Appendix 4
Proposed 2009/10 Minor Traffic Management Programme (£520,000)
* denotes investigation only this year.
Area East Traffic Management Schemes £87,500 (incl. East Hampshire District Council (no TM Agency) Schemes)
· Heath Road East, Petersfield - Pedestrian Facilities | |
· North Stroud Lane, Stroud - waiting restrictions | |
· Blacknest corridor from A31 - A325 - Traffic calming and safety measures | |
· Cherry Way, near Alton College - Parking restrictions | |
· Lovedean Lane, near Waterlooville - Traffic calming and safety measures | |
* |
· Headley Road, Lindford - Priorities at 5-ways junction |
* |
· Village centre, Grayshott - 20mph speed limit |
· Durley Brook Road - 7.5 tonne weight restriction | |
* |
· Stockbridge Road, Sutton Scotney - Road closure to be reconsidered |
* |
· Ladwell, Hursley - 40 mph limit (or a possible 30 mph) |
* |
· Closewood Road, Denmead - Speed limit review |
* |
· Romsey Road near St James Terrace, Winchester - Pedestrian crossing |
Winchester City Council Agency Schemes £17,500
· Wickham. Various restriction of waiting | |
· Kingsworthy, Hookpit Farm lane waiting restriction | |
· Winchester, Dawn Gardens, restriction of waiting | |
· Winchester, Winnal Manor Road restriction of waiting | |
· Winchester, St John's Street contraflow cycling | |
· Winchester, Blue Ball Hill (developer) restriction of waiting | |
· Alresford, Broad Street, Market day order | |
· Winchester, Gt. Minster Street, Prohibition of Driving order | |
· Winchester, Quarry Road, restriction of waiting | |
· Denmead, Park Road, restriction of waiting | |
· Winchester, Lynford Avenue & Lynford Way, restriction of waiting | |
· Bishops Waltham, one way | |
· Colden Common, restriction of waiting (SRTS) | |
· Winchester, Kerrfield, restriction of waiting | |
· Alresford. Various restrictions of waiting | |
· Winchester, Staple Gardens, restriction of waiting | |
· Winchester, Gt. Minster Street, restriction of waiting | |
· Winchester, Hyde Church Lane, One way/No entry/PoD | |
· Winchester, Kilham Lane, restriction of waiting. |
Area North Traffic Management Schemes £27,500
· East Woodhay - All roads in parish to move from a 20 mph to a 40 mph speed limit | |
· Bramley C32 extend eastwards towards Sherfield on Loddon by approx 200m 30 mph | |
· Bramley School and up to the T-junction with the C32 by the rail station 30 mph to 20 mph | |
* |
· Overton parish - various speed limit amendments |
* |
· Old Basing and Lychpit Various speed limit amendments |
* |
· Baughurst - Various speed limit amendments. |
* |
· Old Kempshot Lane - rat running |
· Hackwood Road - Remodelling of mini roundabout | |
* |
· Bramshill, near Hatch Gate PH - Excessive speeds |
* |
· Handford Lane/Hall Lane, Yateley - Excessive speeds |
* |
· 4 Acre Coppice/Holt Lane, Hook - Rat running |
* |
· One of Beaconhill Road or Crondall Road, Church Crookham - Speed reduction measure would be required |
* |
· Avondale Road, Fleet - speed issues |
* |
· Aldershot Town Centre - Review time bands and charging schemes |
* |
· Cranmore Lane - Speed and excessive traffic use |
* |
· Pinewood Park - Various parking obstruction and safety issues |
* |
· Fernhill Road - Further safety measures |
* |
· Tadley speed issues |
* |
· Tadley Junction at Winston Ave / Fairlawan Road. |
Basingstoke and Deane Borough Council Agency Schemes £44,000
· Winchester Road area, Overton. - Development of a Traffic Regulation Order in respect of parking controls, including a residents' parking permit scheme | |
· Various roads in the South Ham and Buckskin Areas - Development of a Traffic Regulation Order to address local safety or congestion issues | |
· Houndmills industrial area - Development of a Traffic Regulation Order to provide permit parking for businesses | |
· Various roads, Norden area - Development of a Traffic Regulation Order to provide residents' permit parking | |
· Various residential roads in Basingstoke & Deane. - Development of a Traffic Regulation Order to provide disabled motorists parking bays in residential areas | |
· Various roads, Whitchurch - Implementation of advertised parking controls | |
· Various roads in Basingstoke & Deane - Amendment of Consolidated Parking Order. | |
· Various roads in Basingstoke & Deane - Small signing schemes | |
· Various roads in Basingstoke & Deane - Small lining schemes |
Rushmoor Borough Council Agency Schemes £28,500
· Farnborough and Aldershot areas - School zig-zags | |
· Farnborough and Aldershot areas - Bus stop clearways | |
· Farnborough and Aldershot areas - Disabled bays | |
· Farnborough area - Parking |
Hart District Council Agency Schemes £5,000
· Hart area - Routine traffic management |
Eastleigh Borough Council Agency Schemes £21,000
· Hut Farm Place (Old Hendy Garage), Chandler's Ford - Restricted parking zone | |
· Chestnut Avenue, B & Q entrance, Chandler's Ford - Revocation of banned turns | |
· South Street, Eastleigh - Waiting restrictions | |
· Falkland Road/Northend Copse(including Holland Close), Eastleigh - Residents parking zone | |
· Old Pirelli site, Eastleigh - Restricted parking zone | |
· Magpie Lane area, Eastleigh - Waiting restrictions (experimental order) | |
· Wells Place, Eastleigh - Loading bay/taxi rank | |
· Passfield Close, Eastleigh - Residents parking | |
· Old Shamblehurst Lane (Hedge End rail station overspill), Hedge End - Waiting restrictions (experimental order) |
Fareham Borough Council Agency Schemes £15,500
* |
· Burnt House Lane/Windermere Avenue - Review parking on junctions and bends as a result of petition to Executive. See Burnt House Lane and Pinewood Close in pool list. |
* |
· Swanwick Lane - Consider prohibition of waiting at all junction of Swanwick Lane as necessary |
* |
· Brook Lane/Heath Road North/Brookfield Gardens - Request for waiting restrictions at the junction. Additional complaint from cleansing. Repeated obstructions to refuse vehicle. Further complaints from residents. |
· West Street Fareham pedestrianised area - Amendment to pedestrianisation orders regarding parking/cycling | |
· West Street Fareham - Revise three disabled and coach bays | |
· Gull Coppice Congestion/obstruction/safety to schoolchildren | |
· Westbury Road No loading ban - BBH's parked prevent loading access for Woolworths | |
· Swivelton Lane Prohibit access for HGVs except for loading | |
· Hill View Road/Dore Avenue Parking | |
· Lockswood Road Amend speed limit from 30 mph to 40 mph |
Havant Borough Council Agency Schemes £17,000
· Woodbury Ave etc (North Langstone area) - Waiting restrictions/limited waiting | |
· Stockheath Lane (West of Purbrook Way roundabout) - Waiting restrictions | |
· Havant town centre east (HBC funded) - Residents parking | |
· Bedhampton Road, Brunswick Gardens and Chadwell Meadow - Waiting restrictions/limited waiting/residents parking | |
· Centenary Gardens - Waiting restrictions | |
· London Road, Purbrook o/s 32/34 - Change no loading to limited waiting | |
· London Road, Purbrook , 56 to 74 - Limited waiting/residents parking | |
· London Road, Purbrook · (Shops west of Penjar Avenue) Limited waiting | |
· St Thomas More's School, Hooks Lane, Bedhampton No stopping on school entrance/waiting restrictions | |
· Apollo Drive Waiting restrictions | |
· Solent Road Permanent prohibition of waiting | |
· Chidham Park Waiting restrictions/residents parking | |
· Central Retail Park Weight restrictions | |
· Havant town centre west (HBC funded) Residents parking | |
* |
· Trosnant Road, Nicholson Way, Stockheath Lane, The Drive, Compton Close |
Area South Traffic Management schemes £39,000 and Gosport Borough Council (no TM Agency) Schemes £12,500
· A&B road speed limit review - resulting amendments that are required to existing limits. | |
· Contingencies for essential traffic management measures identified throughout the year. | |
· Hamble Lane speed limit reduction (between Hound Road and Hamble Primary School). | |
· Grove Avenue/Spring Garden Lane Waiting restrictions | |
· Walpole Road taxi rank Permanent order for taxi rank | |
· Heritage Way speed limit. Priddy's Hard Access Road Revision of speed limit to 40 mph | |
· 1-7 Rowallan Avenue Developer funded Traffic Regulation Order | |
· Mumby Road/Minnitt Road East junction Waiting restrictions | |
· Broom Way/Fell Drive Waiting restrictions | |
· Cherque Farm Phases 6 and 7 Home Zones - waiting restrictions | |
· Aerodrome Road Waiting restrictions | |
· Rowan Close/Cherry Close Waiting restrictions relating to S106 agreement | |
· Rowallen Avenue (No 3) - Waiting restrictions | |
· Rowner Road (No 35) Waiting restrictions | |
· Aerodrome Road Waiting restrictions in the vicinity of the site (Site A Frater Gate units 2-6) | |
· Heritage Business Park Waiting restrictions | |
· Rowner Road, (Brune) Medical Centre - Waiting restrictions | |
· Spring Garden Lane (No 5) Waiting restrictions | |
· Crescent Road (Anglesey Hotel) Waiting restrictions | |
· Aerodrome Road (land at Frater Gate) Waiting restrictions | |
· Spring Garden Lane Waiting restrictions |
New Forest District Council Agency Schemes £18,000
· Ashurst, Foxhills - waiting/loading restrictions to control school parking (concerns raised at HAT meeting 19 February 2008) | |
· Barton - tourist signing for Visitor Information Point. | |
· Brockenhurst - waiting restrictions Brookley Road/Balmer Lawn Road (Linked to Brookley Road casualty reduction scheme) | |
· Brockenhurst Station signing improvements | |
· Holbury, Lime Kiln Lane - Heavy Goods Vehicle restriction - Make experimental order permanent | |
· Hythe, Fairview Parade - prohibition/limited waiting | |
· Lymington town - Station signing improvements. Additional costs to be externally funded. | |
· Lymington, various roads - Waiting restrictions (High Street by steps and Daniels Walk). | |
· Lymington, various roads - Waiting restrictions including Old Farm Walk, New Street, Kings Road, Queens Elizabeth Avenue and Marsh Lane. Consider including similar proposals included in scheme assessment list. | |
· Lymington - Waiting restrictions consolidation order. Administrative measure to assist enforcement without changing marked restrictions. | |
· Lymington/southern New Forest - TRO to make existing advisory school zig zag markings legally enforceable. Part of phased programme started in 2008/09. | |
· Marchwood, Hythe Rd - Low cost measures to address pedestrian safety issues. Proposals identified. | |
· Marchwood industrial park - signing to Marchwood industrial park/Cracknore Hard from Jacobs Gutter Lane traffic signals. Scheme for industrial park signing to be prepared subject to developer funding being secured. | |
· Marchwood Mulberry Road - Retrospective 20 mph and one-way. Will be progressed to at least public advertisement when external funding agreed subject to local Members, police, parish's and Hampshire County Council's comments. | |
· Minstead, Running Hill - closure adjacent to A31 (currently northern section one-way) Progress if and when additional Highways Agency and/or Hampshire County Council partnership funding available (works cost approx. £12,000) | |
· New Milton, various roads - Waiting restrictions including Church Lane/Christchurch Road Service Road/Southern Lane. Consider including similar proposals included in scheme assessment list. | |
· Ringwood, Kings Arms Lane one-way southbound. Referred to in Local Plan. Experimental order to be prepared for implementation when nearby gas works completed later in 2009/10. | |
· Various towns - new cycle route signs and markings - Lymington and Totton (Focus on on-road routes within settlements) | |
· Various towns residents parking schemes - Order to apply approved fees and charges in a consistent way across all schemes irrespective of when scheme introduced | |
· Walhampton, Lisle Court Road - Waiting and/or verge parking restrictions (linked to ferry terminal). | |
· Minor non-programme works - Includes access markings and disabled persons parking spaces | |
* |
· Bashley, 3058 post office reserve scheme - measures to improve access to layby parking area and contribute towards pedestrian safety. Scheme suggested by New Forest Safer Roads Group taking into account police comments. |
* |
· Brockenhurst - Revisions to direction signing (to Beaulieu and from A337 south, sign village centre via Sway Road) Option to revise signing to Beaulieu constrained by low bridge on C53 Balmer Lawn Road |
* |
· Fordingbridge Welcome to Fordingbridge signing (in slip road by 30 mph) |
* |
· Lymington - reserve scheme Review car park signing in Emsworth Road area. Deficiencies identified by Chamber of Commerce. Works to be implemented and funded by NFDC. |
* |
· New Milton - reserve scheme Station signing improvements for pedestrians |
Test Valley Borough Council Agency Schemes £19,000
· A338 Shipton Bellinger Various TM issues - TVBC and Safety Engineering involvement | |
· Nether and Over Wallop* TM issues - possible developer funding - TVBC involvement | |
· Amport - redirected from Village 30 programme - TM issues | |
· Chilworth - redirected from Village 30 programme - TM issues/part of A & B road review - link to SET | |
· Linkenholt - redirected from Village 30 programme - TM issues | |
· Longstock - redirected from Village 30 programme - TM issues | |
· Penton Grafton - redirected from Village 30 programme - TM issues | |
· Upper Clatford - redirected from Village 30 programme - TM issues | |
· Romsey Extra - redirected from Village 30 programme · School Road, Braishfield Road (Woodley) - TM issues | |
· Mottisfont - Hatt Lane | |
* |
· Wherwell* Discussion with parish council on scheme to be developed ongoing either footway of pinch points |
* |
· Upper Clatford* Parish council asked if this is still a priority. Awaiting response. |
Other cross-district traffic management schemes in Area West £68,000
· Review of speed limits on A and B class roads, in accordance with Department for Transport Circular 01/2006. Initial scoping work completed. | |
· Contributions to tranche 2 of the `Village 30' speed limits review. | |
· Contribute to the Casualty Reduction Partnership that investigates all fatal and potential fatal accidents that occur in the district in liaison with the police and Safety Engineering. Ongoing | |
· Marchwood village - lorry issues · Option 1 to be advertised and subject to outcome of consultation implemented | |
· Avenue Road, Lymington. Improvements to pedestrian refuge | |
· Hythe Southampton Road/Fawley Road- redirected from Village 30 programme - Traffic management issues | |
· Ringwood Christchurch Road, Hightown Road, Crow Lane - redirected from Village 30 programme - Traffic management issues | |
· Crow - redirected from Village 30 programme - Traffic management issues | |
· A326 speed limit - follow up temporary speed limit with permanent Traffic Regulation Order | |
· New Forest - trial safety slogan signs on B3054 | |
· Burley - Pound Lane and Ringwood Road - amended trial measures |
* |
· Sopley* - traffic calming - Phase 2 - Scheme proposals to be developed following phase 1 implementation in 2008/09. Likely to be provision of footway along northbound one-way section possibly in sections. |
* |
· A326 at entrance Marchwood Priory Hospital - Traffic management issues |
* |
· Bransgore - Crown Crossroads - Pedestrian issues to be investigated |
* |
· Lymington Gosport Street - pedestrian crossing facility - Community Rail Partnership |
Appendix 5
Proposed 2009/10 Minor Works Programme (£311,000)
Area East £65,000
East Hampshire District £25,000
Scheme name |
Description |
Allocation |
B3004 Forge Road, Kingsley |
Provision of missing footway link to church |
£13,000 |
C120 High Cross Lane, Froxfield |
Extension of missing footway to Southdean Farm |
£12,000 |
Winchester District £40,000
Scheme name |
Description |
Allocation |
B2177 Black Horse Lane, Waltham Chase |
New section of footway to provide safer access to bus stop |
£15,000 |
Footpath by river, Mill Hill, Alresford |
Improvements to existing footpath |
£15,000 |
Durley Brook Road, by primary school (reserve - subject to School Travel Plan) |
New layby for parent parking as existing parking arrangements cause danger on Durley Brook Road |
£10,000 |
Area North £75,000
Basingstoke District £25,000
Scheme name |
Description |
Allocation |
Sherfield on Loddon |
Junction improvements in the centre of Sherfield on Loddon |
£25,000 (part EF) |
Junction of Salters Heath Road |
Footway construction along A340 at junction of Salters Heath Road |
£10,000 |
Hart District £25,000
Scheme name |
Description |
Allocation |
B3349 Hook Road, North Warnborough |
Improved pedestrian facilities to reduce severance effect of the B3349 |
£25,000 |
Rushmoor District £25,000
Scheme name |
Description |
Allocation |
Blackwater Way, Aldershot |
Footway and parking improvements |
£25,000 |
Area South £103,000
Eastleigh District £28,000
Scheme name |
Description |
Allocation |
C358 Winchester Road, Chandlers Ford |
Construction of pedestrian refuge no. 2 by the frontage of no. 179 Winchester Road |
£19,000 |
C194 Allington Lane, West End |
New footway provision between Itchen Valley Country Park and the existing footway near "The Steading" |
£9,000 |
Fareham District £25,000
Scheme Name |
Description |
Allocation |
Duncan Road |
Improvements to footway on southern side to assist access to Swanwick rail station |
£15,000 |
12 to 18 Titchfield Road* |
Additional length of footway |
£10,000 |
*Combined with 2008/09 scheme
Gosport District £25,000
Scheme name |
Description |
Allocation |
Privett Road between Military Road and Grange Road |
Conversion of footway to a shared footway/cycleway |
£10,000 |
Broom Way east side, south of Cherque Way, between Cheltenham Crescent to Fieldhouse Drive* |
Conversion of footway to shared footway/cycleway |
£15,000 |
*combined with Broom Way Accessibility Scheme in main capital programme.
Havant District £25,000
Scheme name |
Description |
Allocation |
West Street, Havant |
Provide footway |
£8,000 |
Sea Front, Hayling Island |
Provide pedestrian refuge |
£7,000 |
High Lawn Way, Leigh Park |
Widen carriageway |
£10,000 |
Area West £68,000
New Forest District £43,000
Scheme name |
Description |
Allocation |
Rhinefield Road, Brockenhurst |
New footway |
£23,000 |
The Bickerley, Ringwood |
Safe pedestrian route - implementation, subject to completion of CPO process |
£10,000 |
(Reserve) C129 Loperwood |
Pedestrian link to Tatchbury Mount |
£10,000 |
Test Valley District £25,000
Scheme name |
Description |
Allocation |
Awbridge |
New footway |
£12,000 |
Valley Park* |
New footway |
£20,000 |
U388 Wellesley Road, Andover |
Parent parking near school |
£13,000 |
Sub programme |
Allocation |
West Street, Fareham* Regeneration of Older Urban Area |
£100,000 |
Grayshott Square - Country Town Initiative |
£100,000 |
Buriton - Hampshire Village Initiative |
£10,000 |
Finchdean- Hampshire Village Initiative |
£14,000 |
Burley Village Centre- Hampshire Village Initiative |
£23,000 |
Areas of Outstanding Natural Beauty, and Schools Landscape Initiative |
£52,000 |
Carry forward to 2010/11 for Areas of Outstanding Natural Beauty and Schools Landscape Initiative |
£88,000 |
Total |
£387,000 |
*Fareham Borough Council - A decision will be made by early April 2009 on a contribution of £250,000.
Appendix 7
Proposed 2009/10 Quality Bus Partnership Programme
Name of QBP |
Details |
Allocation |
Basingstoke QBP |
To complete bus stop improvements works where previous QBP funds have not permitted. This will entail a combination of raised boarding kerbs, bus stop clearways, new bus shelters, new bus stop poles and improved passenger information at stops. |
£20,000 |
Havant QBP |
To upgrade bus stop facilities (as above) on Hayling Island and along the 700 coastal route from Havant towards Chichester. Also to include examination of minor highway measures to improve bus punctuality. |
£60,000 |
QBPs countywide |
To upgrade bus stop facilities (as above) on QBP routes where previous funding has not permitted. To include Winchester, Rushmoor and Test Valley. |
£20,000 |
Total |
£100,000 |
Appendix 8
Proposed 2009/10 Waste Management Programme
2009/10 Approval £000 | |
Andover HWRC |
200 |
Casbrook HWRC |
300 |
Gosport HWRC |
600 |
Waterlooville HWRC |
900 |
Marchwood Transfer Station / HWRC |
2,000 |
Havant HWRC / Other Infrastructure |
1,000 |
Closed landfill sites |
66 |
Total Programme |
5,066 |
Resources available
£000 | |
Forecast unused approvals carried forward |
2,490 |
DEFRA contribution carried forward |
606 |
2009/10 capital allocation |
4,860 |
Total resources for 2009/10 |
7,956 |
Less programme approved |
-5,066 |
Unallocated resources 2009/10 |
2,890 |
2010/11 capital allocation |
840 |
Total unallocated resources 2009/10 - 2010/11 |
3,730 |