Archived decisions

    Executive Summary

    1 Introduction

    Changes in treatment of Heart Attacks within South Central will deliver faster more affective treatments recognised to deliver better outcomes with lower mortality and longer term outcome compared to current practice within the current financial allocation. Primary Percutaneous Coronary Intervention (PPCI) will be the main or first treatment for patients suffering a heart attack (STEMI).

    2 Project Aims

    Investment in training, together with proposed changes to treatments and patient pathways will achieve the following objectives;

    Key Objectives

    Deliver PPCI 24 hours per day 7 days per week within South Central by late autumn 2011

    Achieve an overall call to balloon time of less than 120 minutes

    Ensure that all PPCI centres meet recommended standards and guidelines

    Ensure equitable access to PPCI and cardiac rehabilitation services

    3 Key Activity Assumptions

    The Network has based its activity assumptions on actual numbers of patients during 2008/09 (MINAP), current and proposed patient pathways. Modelling has taken in to account the numbers of inter-hospital admissions for the same spell of treatment and does not include patients who were initially admitted for STEMI but diagnosed differently after investigation.

Cluster

Provider

Unit

STEMI

nSTEMI

Total MI

Northern

ORH

JRH

203

328

531

Horton

51

109

160

BHT

WGH

115

161

276

SMH

79

104

183

MKGH

111

124

235

Central

HWHFT

Heatherwood

20

21

41

Wexham

75

76

151

RBFT

174

214

388

Southern

BNHFT

59

12

71

PHT

Queen Alexandra

339

480

819

IoW

St Marys Hospital

106

147

253

SUHT

401

331

732

RHCH

111

238

349

    4 Future Service Model

    Clinicians and commissioners at a meeting in October 2008 identified the following four options:

      · 24/7 PPCI in 2 centres

      · 24/7 PPCI in 2 centres & Monday to Friday 8am - 6pm (excluding weekends and bank holidays) in 5 centres

      · 27/7 PPCI in 4 centres & Monday to Friday 8am - 6pm (excluding weekends and bank holidays) in 3 centres

      · 24/7 in 4 centres

    In South Central seven providers wish to provide PPCI: one wishes to continue providing daytime service Monday to Friday excluding weekends and bank holidays; a second currently provides daytime services but is willing to move to 24/7 should the commissioners wish them to and the remaining five wish to provide 24/7 PPCI services.

    5 Access to services

    Equality Impact Assessment identifies local factors affecting equality of access to services are as follows:

      · Portsmouth, Milton Keynes and the Isle of Wight will have the largest growth in population between 2006 and 2031.

      · Milton Keynes, Southampton City and the Isle of Wight will have the largest growth in males aged 40-74.

      · Milton Keynes, Portsmouth and Southampton will leave the largest growth in females aged 40-74.

      · Berkshire East will have the third lowest overall population growth during the same period but will have a significantly higher percentage and population growth of Asian or British Asian residents.

      · All areas within South Central have lower than national mortality rates with the exception of Berkshire West PCT who has a mortality rate higher than the national average.

    Please note that at the time of publication of this report the network and commissioners are in the process of revising the EIA to ensure the changes in PPCI services are reflective of each option.

    6 Experienced Interventional Cardiologists

    British Cardiovascular Intervention Society (BCIS) recommends a minimum of 4 and ideally 6 interventionists per PPCI centre. Five of the seven interested providers will have confirmed within this financial year have a minimum of 4 interventionists.

    Provider

    Current Service

    Operator numbers

    BNHFT

    24/7

    2 (soon to appoint a 3rd )

    BHT

    Daytime

    3

    HWPFT

    Daytime

    3 (soon to appoint a 4th)

    ORH

    24/7

    7

    PHT

    Daytime

    3 (soon to appoint a 4th)

    RBFT

    24/7

    4

    SUHT

    24/7

    5

    Totals

    27 + 3

    7 Process to Date

    Date

    Designation

    Outcome

    Oct 2008

    Joint provider, commissioner conference at Newbury

    Four options identified

    Oct-Nov 2008

    Options detailed and Criteria developed by Network

    Appendix A:PPCI Criteria

    Nov 2008

    Option A recommended to Board of Commissioners (BoC) preferred option

    Network asked to develop option C with the Directors of commissioning (DoC).

    Dec 2008

    Paper to DoC requesting implementation of formal procurement route for PPCI

    Network asked to develop proposals within the parameters of world class commissioning.

    Feb 2009

    Next steps meeting

    Panel meeting arranged for the 1st April to allow providers to respond to network criteria in line with the 4 options (Appendix B: Panel Meeting).

    April 2009

    Panel meeting Newbury

    The panel reviewed the provider presentations and submissions against the previously agreed criteria and agreed a further 3 criteria should be included (Appendix C: Additional PPCI Criteria)

    Panel recommends:

      · Option D is presented to BoC based on available information.

      · To work with patient groups to develop options

      · Meet with Health Overview and Scrutiny Committees representatives and panels to develop options

    April 2009

    The following providers did not meet the additional criteria Basingstoke and North Hampshire NHS Foundation Trust (BNHFT), Heatherwood and Wexham Park NHS Foundation Trust (HWPFT) and Buckinghamshire Hospital NHS Trust (BHT) Meetings were offered to discuss additional criteria added by the panel.

    HWPFT - response to additional criteria

      · Currently undertake more than 50 PPCI per annum.

      · Shortly will have both a cath lab and a pacing lab at cath lab standards

      · Will provide 24/7 following public engagement and consultation if the commissioners would like them to.

    BNHFT - response to additional options

      · Currently undertake more than 50 PPCI per annum

      · They have 2 cath lab

      · Currently providing 24/7 PPCI services with 2 consultants are in the process of appointing a third and will have a visiting interventionist shortly.

    BHT did not respond

    June 2009

    Board of Commissioners

    The Board supported the next stage of the project - Engagement.

    8 Value for Money

    The financial analysis and value for money calculations have been based on current patient pathways, MINAP data for the period of 2008/09 and Health Resource Groups (HRG) 3.5, 2007/08.

    The model is inclusive of readmission for same HRG procedures (nationally 12%). Direct discharge from the heart attack centres is assumed within all of the options. No costs have been included for transfer to local hospitals post procedure.

Financial Summary

Option

PCT

Additional SCAS

Prescribing

Total

D

£8,382,600

£ 14,236

£ 11,964

£8,408,800

C

£8,382,600

£ 13,430

£ 11,964

£8,407,994

A

£8,385,695

£ 20,564

£ 11,964

£8,418,223

Current

£8,820,857

£8,820,857

    9 Outline Timetable to Commissioning

    Date

    Key Milestone

    June 09

    BoC approval

    _ Commence Engagement phase on options A, C and D

    _ Engagement Strategy and Plan (Appendix E with amendments)

    _ Return to BoC with engagement report and recommendations for consultation phase

    July to Oct 09

    Engagement phase of engagement and consultation

    Nov 09

    Engagement review and report to BoC

    Dec 09 to Feb 10

    Formal Consultation

    Preparation for PPCI implementation

    · To develop service specifications to guide the SHA, commissioners and other stakeholders, based on clinical consensus and high quality data.

    · To develop and implement evidence based, uniform clinical standards, guidelines and protocols across the network where these do not exist.

    · Maintain strong clinical engagement to enable improvements in practice and co-operation along patient pathways.

    · To act as a consultancy and educational resource for clinical and service quality improvement work in PCI

    · Working with the SHA, to understand and support commissioning clusters for quality by contributing to network wide comparative benchmarking, audit and clinical quality indicators and outcomes.

    · Provide clinically based advice to inform workforce planning, inputting to the education and training strategy for relevant professional groups.

    · Provide a detailed implementation plan

    March 2010

    Final report to BoC for decision

    April 2010

    Commence Implementation process

    Nov 11

    PPCI implementation complete

    10 Support and Approval

    The Network have appointed a consultancy firm: Communications Management: Building Reputations to undertake a period of engagement and consultation with all stakeholders including commissioners, providers, patients and the public and have gained approval from the Board of Commissioners to commence the engagement program for a period completing late autumn 2009.

Primary Percutaneous Coronary Intervention

     

South Central Cardiovascular Network

   

June 2009

Contents

 

Page

1

   

Introduction

1

2

   

Treatment of Heart Attack in South Central

4

 

2.1

 

Current Service provision

4

 

2.2

 

Existing Patient Flows

6

3

   

Recommended patient pathway

9

 

3.1

 

New Patient Pathway

9

 

3.2

 

Options

9

   

3.2.1

Option A

9

   

3.2.2

Option B

10

   

3.2.3

Option C

11

   

3.2.4

Option D

12

   

3.2.5

Benefits and Risks

12

   

3.2.6

South Central Ambulance Service response to new PPCI service model

14

 

3.3

 

Criteria affecting option

14

   

3.3.1

Quality

14

   

3.3.2

Location

15

   

3.3.3

Capacity

17

   

3.3.4

Access to services should be equal for everyone in need

20

   

3.3.5

Preferred Option

22

4

   

Area which do not fall within the 40 minute isochrones

23

 

4.1

 

M4 Corridor

23

 

4.2

 

Milton Keynes

23

 

4.3

 

Isle of Wight

24

 

4.4

 

Buckinghamshire

25

5

   

Finance

26

 

5.1

 

PPCI costs based on actual numbers of patients during 2008/09 (MINAP)

27

 

5.2

 

HRG Version 4

27

 

5.3

 

Conclusion

28

6

   

PPCI Implementation

29

 

6.1

 

Engagement and Consultation

29

 

6.2

 

Timescales

30

7

   

Conclusion

31

Figures & Tables

Page

Figure

1

Patient Map - Buckinghamshire Hospitals NHS Trust

6

2

Patient Map - Milton Keynes General Hospital

6

3

Patient Map - Oxford Radcliffe Hospitals NHS Trust

6

4

Patient Map - Royal Berkshire NHS Foundation Trust

7

5

Patient Map - Heatherwood and Wexham park Hospitals NHS Foundation Trust

7

6

Patient Map - Basingstoke and North Hampshire Hospitals NHS Foundation Trust

7

7

Patient Map - Southampton University Hospital NHS Trust

7

8

Patient Map - Queen Alexandra Hospital

8

9

Patient Map - Royal Hampshire County Hospital

8

10

Patient Map - St Marys Hospital

8

11

PPCI patient pathway

9

12

One year mortality

15

13

Call to door mortality

16

14

PPCI timescale

16

15

Call-to-door times

16

16

SCAS Map: 40 minute isochrones of ORH and SUHT

17

17

Isle of Wight - call to balloon

24

Table

1

Process to Date

2

2

South Central Population

4

3

Current Service Provision

5

4

Option A

10

5

Option B

10

6

Option C

11

7

Option D

12

8

Benefits and Risk

13

9

Locations

14

10

BCIS Mortality Audit

18

11

BCIS Guidelines

18

12

Provider Total PCI

19

13

Provider Operator Numbers

19

14

Hospital Mortality

20

15

Mortality

23

16

Population - Milton Keynes

23

17

Population - Isle of Wight

24

18

MINAP 2007/08

26

19

HRG 2007/08

26

20

Financial Summary

27

21

HRG 2008/09

28

22

Timetable

30

    1.0 Introduction

    Coronary angioplasty is a technique used to reopen an artery supplying heart muscle which has occluded causing a heart attack. A small balloon at the tip of a catheter tube is inserted via an artery in the groin or arm and guided to the blocked heart artery. It is briefly inflated and then removed, leaving in place a 'stent' - a rigid support which holds the artery widely open, allows blood to flow more easily. Primary angioplasty (or PPCI) is the use of this technique as the initial treatment of patients suffering more severe forms of heart attack (STEMI).

    The key to improving outcomes after heart attack is to re-establish coronary artery flow as quickly as possible and limit damage to the heart muscle.

    There have been numerous studies addressing the relative benefits of primary angioplasty as against thrombolysis in the treatment of heart attack. Evidence for the longer-term benefits of primary angioplasty has been steadily growing and the main conclusions are:

      · Primary angioplasty reduces mortality, and improves longer-term outcome compared to thrombolysis when both treatments can be undertaken within a similar time frame1.

      · The advantage of primary angioplasty over thrombolysis decreases with increasing delay in undertaking the procedure. Whilst much debate still surrounds this issue it is thought that the benefit of primary angioplasty may be lost, or considerably reduced, if it takes more than 90 minutes longer to undertake the procedure than it would to administer thrombolysis

      · More patients are potentially suitable for primary angioplasty than thrombolysis, and primary angioplasty is associated with fewer strokes and recurrent heart attacks during the hospital admission2.

    The National Infarct Angioplasty project (NIAP3) report suggests PPCI improves patient outcomes provided the balloon is inflated within 120 minutes of call for help and at a cost which is considerably lower than the benefits delivered. (Cost per QALY £4,500)

    The South Central Darzi Acute Care clinical pathway group review referred to the NIAP work as an example of the benefits which could be achieved for patients by organising services on the basis of more specialised centres of excellence.

    Professor Boyle (December 2006) produced Mending Hearts and Brains, a report which made the clinical case for reconfiguration in terms of delivering better urgent case for myocardial infarction. This stressed the need for myocardial infarction services to be delivered by personnel with an appropriate level of experience and training in settings with sophisticated diagnostic and monitoring facilities on a 24 hours a day, seven days a week, immediate-access basis.

    The following Table 1: Process to Date lists the process undertaken by the South Central Cardiovascular Network since the publication of the NIAP report in October 2008.

    Table 1: Process to Date

Date

Designation

Outcome

Oct 2008

Joint provider, commissioner conference at Newbury

Four options identified

Oct-Nov 2008

Options detailed and Criteria developed by Network

Appendix A:PPCI Criteria

Nov 2008

Option A recommended to Board of Commissioners (BoC) preferred option

Network asked to develop option C with the Directors of commissioning (DoC).

Dec 2008

Paper to DoC requesting implementation of formal procurement route for PPCI

Network asked to develop proposals within the parameters of world class commissioning.

Feb 2009

Next steps meeting

Panel meeting arranged for the 1st April to allow providers to respond to network criteria in line with the 4 options (Appendix B: Panel Meeting).

April 2009

Panel meeting Newbury

The panel reviewed the provider presentations and submissions against the previously agreed criteria and agreed a further 3 criteria should be included (Appendix C: Additional PPCI Criteria)

Panel recommends:

    · Option D is presented to BoC based on available information.

    · To work with patient groups to develop options

    · Meet with Health Overview and Scrutiny Committees representatives and panels to develop options

April 2009

The following providers did not meet the additional criteria Basingstoke and North Hampshire NHS Foundation Trust (BNHFT), Heatherwood and Wexham Park NHS Foundation Trust (HWPFT) and Buckinghamshire Hospital NHS Trust (BHT) Meetings were offered to discuss additional criteria added by the panel.

HWPFT - response to additional criteria

    · Currently undertake more than 50 PPCI per annum.

    · Shortly will have both a cath lab and a pacing lab at cath lab standards

    · Will provide 24/7 following public engagement and consultation if the commissioners would like them to.

BNHFT - response to additional options

    · Currently undertake more than 50 PPCI per annum

    · They have 2 cath lab

    · Currently providing 24/7 PPCI services with 2 consultants are in the process of appointing a third and will have a visiting interventionist shortly.

BHT did not respond

June 2009

Board of Commissioners

The Board supported the next stage of the project - Engagement.

    May 2009 to March 2010

    During this time a period of engagement will consider the following three options4;

    A: 24/7 PPCI would be provided in 2 centre's; Oxford Radcliffe Hospitals NHS Trust (ORH) and Southampton University Hospitals NHS Trust (SUHT).

    C: 24/7 PPCI would be provided in four centres: ORH, SUHT, Royal Berkshire NHS Foundation Trust (RBFT) and Portsmouth Hospital Trust (PHT).

    In addition to these centres there will be a further three centres: Basingstoke and North Hampshire Hospitals NHS Foundation Trust (BNHFT), Buckinghamshire Hospitals NHS Trust (BHT) and Heatherwood and Wexham Park Hospitals NHS Foundation Trust (HWPFT) on a Monday to Friday 8am - 6pm basis (excluding weekends and bank holidays).

    D: 24/7 PPCI would be provided in four centres: ORH, SUHT, RBFT and PHT.

    The next section will describe the current PPCI services within the south central area.

    2.0 Treatment of Heart Attack in South Central

    2.1 Current Service Provision

    There are four providers currently undertaking PPCI 24/7 for treatment of STEMI. There are three hospitals that receive patients with thrombolysis but transfer their patients to other providers for PCI and three who provide 8am - 6pm angiography/thrombolysis or PPCI with thrombolysis out of hours. Table 1: PCT population shows that there is a marked variation between the PCTs, the Isle of Wight being the smallest with a population of 138,500 and Hampshire the largest with 1,250,0005.

    The total volume of PCI activity (unplanned and elective) in the UK was 1,269 per million populations (PMP) from Jan to Dec 2008. In 2003 the British Coronary Intervention Society (BCIS) target was 1,400 PMP with expectations that the level might in the future need to be 2-3,000 PMP6, these predictions are now under review. Table 2: South Central Population provides an estimated level of PCI within each PCT population for current UK populations and an estimated PMP up to 3,000.

    Table 2: South Central Population

Population

Estimated total PCI based on

Per Million Population

1,269

PMP

1,400

PMP

1,600

PMP

1,800

PMP

2,000

PMP

3,000

PMP

Buckinghamshire PCT

500,000

635

700

800

900

1000

1,500

Milton Keynes PCT

230,300

292

322

368

415

461

691

Oxfordshire PCT

635,000

806

889

1,016

1,143

1,270

1,905

Total Northern Cluster population

1,365,300

1,733

1,911

2,184

2,458

2,731

4,096

Berkshire East PCT

376,000

477

526

602

677

752

1,128

Berkshire West PCT

450,000

571

630

720

810

900

1,350

Total Central Cluster population

826,000

1,048

1,156

1,322

1,487

1,652

2,478

Hampshire PCT

1,250,000

1,586

1,750

2,000

2,250

2,500

3,750

Isle of Wight PCT

138,500

176

194

222

249

277

416

Portsmouth City Teaching PCT

230,710

293

323

369

415

461

692

Southampton City PCT

257,000

326

360

411

463

514

771

Total Southern Cluster population

1,876,210

2,381

2,627

3,002

3,377

3,752

5,629

Total SHA Population

3,929,010

4,986

5,501

6,286

7,072

7,858

11,787

    Actual PMP data is not available by PCT, not all patients admitted with suspected STEMI have a final diagnosis of STEMI.

    Treatment of Heart attacks within South Central is dependant on the geographical location of the patient as demonstrated in section 2.2: patient flows.

    The seven centres in South Central provide a mix of 8am - 6pm and 24/7 PPCI and thrombolysis services.

    In addition Harefield Hospitals provide out of hours (OOH) thrombolysis services for Berkshire East PCT and Buckinghamshire PCT, Table 3: Current Service Provision;

    Table 3: Current Service Provision (by provider)

Provider

Current Service

Current activity

Operator numbers

No of labs

Total PCI

Suspected STEMI

2008/09

2007/08

First Presentation

Final Destination

Buckinghamshire Hospitals NHS Trust (High Wycombe) (BHT)

Daytime service

473

194

194

3

2

OOH eligible PPCI patients transferred out of hours to Oxford or Harefield

(all London activity is currently funded through specialist commissioning)

Milton Keynes

(MKGH)

111 patients of which eligible PPCI patients transferred from Milton Keynes General Hospital (MKGH)to ORH (101 pts)

No PPCI service

111

10

Oxford Radcliffe Hospital NHS Trust (ORH)

24/7

1,670

149

250

7

3

Northern Cluster provider totals

2,082

454

454

10

5

Heatherwood and Wexham Park Hospitals NHS Foundation Trust (HWPFT)

Daytime service

447

95

95

3

appointing a 4th

1 + 1

OOH eligible PPCI patients transferred to Harefield or RBFT

Royal Berkshire NHS Foundation Trust (RBFT)

24/7

582

174

174

4

2

Central Cluster provider totals

1,029

269

269

7 + 1

4

Basingstoke and North Hampshire Hospitals NHS Foundation Trust (BNHFT)

24/7

412

59

59

2

appointing a 3rd

1

When 24/7 not available all eligible PPCI patients transferred to RBFT- service not yet implemented

Isle of Wight

(StMH)

106 patients of which eligible PPCI patients transferred from St. Marys Hospital (StMH) to PHT (101 pts)

No PPCI service

106

6

Portsmouth Hospitals NHS Trust (PHT)

Daytime service

706

239

322

3

appointing a 4th

2

5% PHT thrombolysed patients transfer to SUHT for rescue PPCI (-17)

Southampton University Hospitals NHS Trust (SUHT)

24/7

1,144

284

401

5

4

Winchester

(RHCH)

111 patients of which eligible PPCI patients transferred from The Royal Hampshire County Hospital (RHCH) to SUHT (100 pts)

No PPCI service

111

11

Southern Cluster provider totals

2,262

799

799

10 + 3

8

Totals

5,434

1,535

1,535

27 (+4)

14 + 1

The total numbers within table 2 have been adjusted to allow for inter-hospital transfers;

· Of the 111 patients presenting at RHCH, 100 are transferred to SUHT for PPCI/other treatments and are already included within SUHT figures (+11).

· Of the 106 patients presenting at StMH 101 are transferred to PHT for PPCI/other treatments and are already included within PHT figures (+5)

· 5% of total PPCI patients presenting at PHT transfer to SUHT for rescue PPCI, these are already included within SUHTs numbers (-17)

· The 111 patients presenting at MKGH 101 are transferred to ORH for PPCI/other treatments and are already included within ORH figures (+10).

· An additional 50 East Berkshire patients who present at Harefield hospital have been included within HWPFT numbers.

· Patients transferring to Harefield Hospital OOH are already included within BHT.

2.2 Existing Patient Flows

The following figures (1-10) demonstrate current patient flows within South Central by provider figure 10 shows the current service with additional air ambulance support.

    Figure 1: Buckinghamshire Hospitals NHS Trust

    2.2.1 Northern Cluster

    Buckinghamshire Hospitals NHS Trust (BHT)

    Oxford Radcliffe Hospital NHS Trust (ORH)

    Milton Keynes General Hospital (MKGH)

    NSTEMI - 2,143

    STEMI - 365

    Clinicians - 10

    Catheter Laboratories - 5

    Figure 2: Milton Keynes Hospital NHS Foundation Trust

    Figure 3: Oxford Radcliffe Hospitals NHS Trust

    2.2.2 Central Cluster

    Royal Berkshire NHS Foundation Trust (RBFT)

    Heatherwood and Wexham Park Hospitals NHS Foundation Trust (HWPFT)

    NSTEMI - 1,029

    STEMI - 216

    Clinicians - 7 + 1

    Catheter Laboratories - 4

    Figure 5: Heatherwood and Wexham Park Hospitals NHS Foundation Trust

    2.2.3 Southern Cluster

    Basingstoke and North Hampshire Hospitals NHS Foundation Trust (BNHFT)

    Portsmouth Hospitals NHS Trust (PHT)

    Southampton University Hospital NHS Trust (SUHT)

    The Royal Hampshire County Hospital - Winchester

    St Marys Hospital - Isle of Wight

    NSTEMI - 1,262

    STEMI - 710

    Clinicians - 10 + 3

    Catheter Laboratories - 8

     The following section, section 3 will describe the recommended patient pathway and associated risks and benefits for options a, b, c and d (see page 10):

    a. 24/7 PPCI in 2 centres, John Radcliffe Hospital (JRH), Oxford and Southampton University Hospital Trust (SUHT).

    b. 24/7 PPCI in 2 centres, JRH and SUHT. Plus Monday to Friday 8am to 6pm services (excluding weekends and bank holidays) 5 centres, Buckinghamshire NHS Hospital Trust (BHT), Basingstoke and North Hampshire NHS Foundation Trust (BNHFT), Royal Berkshire NHS Foundation Trust (RBFT), Portsmouth Hospital Trust (PHT) & Heatherwood and Wexham Park Hospital NHS Foundation Trust (HWPFT).

    c. 24/7 PPCI in 4 centres, JRH, SUHT, PHT and RBFT & Monday to Friday 8am - 6pm services (excluding weekends and bank holidays) 3 centres, BHT, BNHFT & HWPFT

    d. 24/7 in 4 centres, JRH, SUHT, PHT and RBFT.

    Figure 10: St Marys Hospital - Isle of Wight

    3 Recommended patient pathway

    The treatment of heart attack national guidance Final Report of the National Infarct Angioplasty Project (NIAP) was published on the 20th October 2008. South Central Cardiovascular Network hosted a meeting in Newbury on the 22nd October 2008, providers and commissioners were in attendance as was national leads for PPCI. At this meeting the new PPCI patient pathway was endorsed by all clinicians present (Figure 11: PPCI Patient Pathway). Attendees at the meeting formulated four options as described within section 3.2: options.

    3.1 New Patient Pathway

    All patients experiencing STEMI within South Central should have access to 24/7 to PPCI centres7,8,9. Currently 95% of these patient treatments involve a stent insertion3, the remaining 5% decline treatment, go on to have different treatments such as CABG or do not survive. Figure 11: PPCI Patient pathway10 represents patient pathway for STEMI patients with the exception of the Isle of Wight for all options.

    Figure 11: PPCI Patient pathway

    3.2 Options

    World class commissioning is about delivering better health and wellbeing for the population, improving health outcomes and reducing health inequalities. To allow effective implementation of PPCI within South Central the commissioners will decide the optimum number of and locations of PPCI centre's and how patients will flow across the system.

    3.2.1 Option A

    24/7 PPCI would be provided in two centres: Oxford Radcliffe Hospitals NHS Trust (ORH) and Southampton University Hospitals NHS Trust (Table 4: Option A).

    Table 4: Option A

Northern Cluster:

· ORH will receive all patients from the northern cluster.

Central Cluster:

· PPCI services will be commissioned through Oxford and Southampton

Southern Cluster:

· SUHT will receive all patients from the southern cluster and excluding 50% BNHFT which will attend RBFT as above.

    3.2.2 Option B

    24/7 PPCI would be provided in two centres: ORH, SUHT.

    In addition to these centres there will be a further five centres: BNHFT, BHT, HWPFT, RBFT and PHT on a Monday to Friday 8am - 6pm basis (excluding weekends and bank holidays) (Table 5: Option B).

    Table 5: Option B

Northern Cluster:

· ORH will receive patients from its current catchment and Milton Keynes (MKFT) 24/7. OOH they will also receive 75% patients from BHT, 75% from HWPFT and 100% from RBFT.

· BHT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH 25% of patients will go to Harefield Hospital and the remaining 75% will go to ORH as above.

· In this model Milton Keynes Foundation Trust will not provide PPCI, all MK patients will go to ORH, however options for MK and neighbouring areas will be reviewed later this year (2009).

Central Cluster:

· RBFT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH patients will go to Oxford

· HWPFT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH 25% patients will go to Harefield Hospitals and 75% to Oxford.

Southern Cluster:

· SUHT will receive all patients from its current catchment and The Royal Hampshire County Hospital (RHCH) - Winchester 24/7. Thrombolysed patients from the IoW (unless air lifted the PPCI) . OOH all patients from BNHFT and PHT.

· PHT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH patients will go to SUHT

· BNHFT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH patients will go to SUHT.

· RHCH will not provide PPCI, all Winchester patients will go to SUHT.

· IoW will not provide PPCI all patients will have thrombolysis and be transferred to SUHT within 48hours unless airlifted than they will have PPCI at SUHT.

Harefield

· OOH 25% each from BHT and HWPFT

3.2.3 Option C

    24/7 PPCI would be provided in four centres: ORH, SUHT, Royal Berkshire NHS Foundation Trust (RBFT) and Portsmouth Hospital Trust (PHT).

    In addition to these centres there will be a further three centres: Basingstoke and North Hampshire Hospitals NHS Foundation Trust (BNHFT), Buckinghamshire Hospitals NHS Trust (BHT) and Heatherwood and Wexham Park Hospitals NHS Foundation Trust (HWPFT) on a Monday to Friday 8am - 6pm basis (excluding weekends and bank holidays) (Table 6: Option C).

    Table 6: Option C

Northern Cluster:

· ORH will receive patients from its current catchment and Milton Keynes (MKGH) 24/7. OOH they will also receive 75% patients from BHT.

· BHT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH 25% of patients will go to Harefield Hospital and the remaining 75% will go to ORH as above.

· In this model Milton Keynes General Hospital will not provide PPCI, all MK patients will go to ORH, however options for MK and neighbouring areas will be reviewed later this year (2009).

Central Cluster:

· RBFT will receive patients from its current catchment 24/7. OOH they will receive patients from BNHFT and 75% from HWPFT.

· HWPFT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH 25% patients will go to Harefield Hospital and 75% to RBFT.

Southern Cluster:

· SUHT will receive all patients from its current catchment and The Royal Hampshire County Hospital (RHCH) - Winchester24/7.

· PHT will receive patients from its current catchment, the Isle of Wight and an anticipated 72 patients from the Chichester area 24/7.

· BNHFT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH patients will go to RBFT.

· RHCH will not provide PPCI, all Winchester patients will go to SUHT.

· IoW will not provide PPCI during daylight hours patients where possible will be air lifted to PHT. At all other times patients will have thrombolysis therapy and be transferred to PHT within 24 hours.

Harefield

· OOH 25% of BHT and 25% HWPFT will go to Harefield

3.2.4 Option D

    24/7 PPCI would be provided in four centres: ORH, SUHT, RBFT and PHT (Table 7: Option D).

    Table 7: Option D

Northern Cluster:

· ORH will receive patients from its current catchment, MKGH 24/7 75% patients from BHT 24/7.

· BHT 25% patients will go to Harefield Hospital and 75% to ORH.

· In this model Milton Keynes General Hospital will not provide PPCI, all MK patients will go to ORH. However options for MK and neighbouring areas will be reviewed later this year (2009).

Central Cluster:

· RBFT will receive patients from its current catchment, all patients from BNHFT and 75% from HWPFT

· HWPFT 25% patients will go to Harefield Hospital and 75% to RBFT.

Southern Cluster:

· SUHT will receive all patients from its current catchment and The Royal Hampshire County Hospital (RHCH) - Winchester and 25% from BNHFT 24/7.

· PHT will receive patients from its current catchment, the Isle of Wight and an estimated 72 patients from the Chichester area 24/7.

· BNHFT all patients will go to RBFT.

· RHCH will not provide PPCI, all Winchester patients will go to SUHT.

· IoW will not provide PPCI during daylight hours. Patients where possible will be air lifted to PHT. At all other times patients will have thrombolysis therapy and be transferred to PHT within 24 hours.

Harefield

· 25% BHT and 25% HWPH will go to Harefield

    The geographical proximity of both the Isle of Wight to the nearest 24/7 PPCI centre for all options, PPCI is not achievable within the designated timescale of 120 call-to-balloon time within any of the options. Parts of Milton Keynes and East Buckinghamshire also fall within the 120 minute timescale the network, commissioners and ambulance services are meeting in July to revisit possible options for Milton Keynes residents. Both the Isle of Wight and Milton Keynes will be dealt with separately in section 4.

    3.2.5 Benefits and Risks

    Benefits and Risks associated with the three options listed above can be found in Table 8: Benefits and Risks

Table 8: Benefits and Risks

    Option

    Benefits

    Risks

    Probability

    Impact

    Mitigation

A

Clearer pathways with fewer high volume centres, developing clinical expertise and potentially faster door to balloon times.

Potential impact on the services in the remaining four 8am - 6pm PCI centres with possible knock on effects to elective services for their local residents

Patients who present at a local DGH who do not provide PPCI would have to be transferred to a PPCI centre introducing delay and potential for not achieving treatment within 120 minutes of call for help.

Medium

High

Further investment in SCAS, additional vehicles training and service improvement

Decreased risk of ambulance crew aborted journeys and associated risk to patients

Longer travel journeys out of the traditional ambulance station locations could leave some geographical locations uncovered by paramedic crews.

High

High

C

Care close to home

Maintenance of existing service capacity

8am - 6pm PCI centres that sign up to this model may not adhere to the service specification identified by the network and as such the model may be unsustainable in the medium to long term. Specifically the need for all centres to meet with EU working time directives and the increasing national drive towards all centres having two cardiac catheter labs.

Patients who present at a local DGH who do not provide PPCI would have to be transferred to a PPCI centre introducing delay and potential for not achieving treatment within 120 minutes of call for help.

Medium

Medium

6 monthly review by commissioners and network

Risk of ambulance crew aborted journeys and associated risk to patients

High

High

D

24/7 access for majority of residents with the exception of the Isle of Wight parts of Milton Keynes and East Buckinghamshire.

Clear pathway that achieves the 120 minute call to balloon time

Pairing of centres North and South provides potential for back up centres close by.

Decreased risk of ambulance crew aborted journeys and associated risk to patients.

IMpact on the cardiac services in remaining 3 8am - 6pm PCI centres with potential knock on effects to elective services for their local residents.

Medium

High

Communications campaign to encourage a 999 call for heart attack symptoms.

Opportunity for cardiologists from other centres to join the rotas in the 24/7 centres to maintain their skills.

Patients who present at a local DGH who do not provide PPCI would have to be transferred to a PPCI centre introducing delay and potential for not achieving treatment within 120 minutes of call for help.

Patients will normally be discharged home within three days of their admission. There is a risk that capacity issues within larger units will cause patients to be discharged to district hospitals resulting in a poorer quality in service and increase financial costs.

High

High

    3.2.6 South Central Ambulance Service response to PPCI services.

    South Central Ambulance Services (SCAS) were asked to respond to changes in treatment of STEMI patients with PPCI centres (see Appendix F: SCAS Response).

    "SCAS are committed to support the provision of a 24/7 PPCI services working with the acute providers to achieve the standards set where the times allow a call to door time of 80 minutes. The Trust would aim to improve on the Call to depart scene time working with providers and the south central vascular network.....

    SCAS would prefer that all PPCI centres where 24/7 as apposed to 8am - 6pm hours to alleviate the potential for patients to arrive at a day centre and not treated." SCAS recognise the criteria governing restricted opening hours should reduce the likelihood of this occurring "but it would create a governance issue should it arise"

    3.3 Criteria affecting option

    To determine the best option is it important to understand the interdependencies to deliver PPCI. The network developed a list of criteria in accordance with national guidance, research evidence, BCIS recommendations and local requirements (Appendix A: PPCI Criteria), covering three areas; Quality; Location; Capacity.

    3.3.1 Quality

    Initial engagement with heart attack patients within the cardiac rehabilitation setting (Table 9: Locations) took place during April and May 2009 as follows;

    Table 9: Locations)

Date

Location

20th April 2009

Horton Hospital, Banbury

1st May 2009

Basingstoke and Alton Cardiac Rehab Charity Group Alton

11th May 2009

Milton Keynes General Hospital

    Cardiac Rehabilitation groups were targeted because they comprised of patients who had recently had a heart attack.

    In Banbury and Milton Keynes the Network representative was invited to talk to patients at the rehabilitation groups in a formal seating arrangement. Treatment of Heart Attacks by PPCI was discussed at both of these meetings. The group felt that the patient experiences could be improved by speediness of treatment and being treated at the hospital at which they first presented. A number of patients had been admitted to one hospital, transferred to another for either rescue PCI or PCI and then transferred back to the original hospital.

    The patients felt increase anxiety during this period not only for themselves but also for their relatives and said their anxiety would have been greatly reduced if the proposed PPCI model had been in place for them.

    One patient reported about being admitted to one unit having thrombolysis and then being transferred to a second provider where he sat for a week before having a angiogram and insertion of 2 stents.

    The Network recommends;

    a) Patients without complications will be discharged direct from CCU or cardiac high care facility home.

    b) Arrangements for the provision of phase 1 cardiac rehabilitation prior to discharge and activation of phases 2 & 3 rehabilitation covered by cardiac rehabilitation specialists in nurse led clinics

    c) Final discharge information to primary care within 24 hours of discharge for 100% of all cases (yr 1).

    A second patient asked who made the decision about which provider the patients are taken to.

    The network recommends:

    · Centres will agree that the ambulance service paramedic determines the diagnosis and destination of the patient, without recourse to telemetry as per network agreed critical care transfer policy

    · Prior notice will be given by the SCAS as soon as a decision to transfer is made and preferably Clopidogrel should be administered to the patient in preparation for the PPCI procedure

    The network meeting at Alton was with individual patients while they undertook their Gym activities. A description of PPCI was offered to all those spoken to and all agreed it would be a good thing to have, echoing the sentiments of the other groups.

    All groups had differing views as to the location of the PPCI centres; most felt they would like to attend a large centre even if it meant passing their local hospital, where as other patients felt they should have a PPCI centre at their local hospital.

    3.3.2 Location

    In the treatment of STEMI speed is of the essence because delays increase the risk of patients not surviving the heart attack7.

    Figure 12: One Year Mortality

     One of the key driving forces for successful PCI is initiating PPCI within 120 minutes of call to emergency services.

    deLuca et al Circ 2004: 109;1223-25 graph (Figure 12: One year mortality) demonstrates increased one year mortality with treatment delay.

     The October 2008 NIAP report call to Figure 13: Call to door mortality

    door time (CTD) graph (Figure 13: Call to door time mortality) supports this showing the patients with a short CTD of less than 60 minutes experience better outcomes. The 60 minute CTD within NIAP allows a 90 minute door to balloon time total 150 minutes in accordance with NHS Improvements a guide to implementing primary angioplasty11.

The European Society of Cardiology continues to recommend a total call to balloon time of 120 minute.

    BoC wish to commission for excellence rather than average performance and asked the network to consider options which did not stray outside a 40 minute travel time (Figure 14: PPCI call to balloon time in South Central).

    Figure 14: PPCI call to balloon time in South Central.

    Timing of each stage must be flexible enough to adapt to the individual patient needs and meet the 120 minutes call to balloon time. The network acknowledges that, prior warning to centre by the ambulance service may facilitate savings in door to balloon time, because catheter laboratory staff will have longer to prepare.

    Figure 15: Call to Door Times  Rathore et al 200912 found Door to balloon time is associated with mortality in patients undergoing PPCI. A review of call to door times for the south central ambulance service for the calendar year 2008 revealed the following performance (Figure 15: Call to Door Times):

    Following public engagement, identification of and approval of a preferred option the Network will work with each centre and SCAS to ensure by autumn 2011 a robust PPCI service within South Central.

    The Network is aiming for 75% (yr 1) and 90% (yr 3) of all cases to achieve a call to balloon time of 120 minutes or less.

    Centres should aim for the following door to balloon time targets:

    · Less than 60 minutes, 75% of the time (yr 1)

    · Median of less than 40 minutes (yr 3) and

    · Report quarterly performance to the commissioning cluster.

     Analysis of the isochrones provided by South Central Ambulance Services suggests to commission options within a travel time of 40 minutes (as requested by BoC) for Option A, this leaves large area exposed namely Milton Keynes, East Buckinghamshire, the Isle of Wight and the area known as the M4 corridor.

    Solutions for Milton Keynes and the Isle of Wight will be discussed in section 4.

    Figure 16: SCAS Map: 40 Minute Isochrones of ORH and SUHT

    3.3.3 Capacity

This section reviews each provider in relation to numbers of; patients, clinical teams and facilities.

Activity

    Providers have found cardiac catheterisation laboratories are expensive to set up, incur substantial running costs and must be staffed 24 hour a day and seven days a week for a robust PPCI service to be viable. Approximately 20-30 patients experiencing STEMI present out of hours each week (MINAP, 2007). Magid 2002 suggest patient numbers within smaller units, will be insufficient to justify such an investment, especially as it is necessary for PCI centres to operate at high volume simply to provide the staff with the necessary experience to develop and maintain their expertise.13,14

    The Network recommends each centre models their finances accordingly; section 5 finance demonstrates current costs and costs based on the same activity for each model by centre. The complication rate and the volume of procedures performed in an institution per annum are clearly related: morbidity and mortality in high volume centres are lower than in low volume centres15 it is also recognised that there are increased delays associated with PPCI performed at night compared with during the day16.

    Primary PCI for STEMI is completely different from other forms of PCI. The patients are much sicker and demand high level clinical involvement. The British Cardiovascular Intervention Society (BCIS) national PCI audit from 2007 has just been published. (Table 10: BCIS Mortality Audit)

    Table 10: BCIS Mortality Audit

Mortality from primary PCI

4.8%

Mortality for unstable angina PCI

0.61%

Mortality for elective PCI

0.14%

    PPCI mortality is eight times that of unstable angina PCI mortality and more that thirty times that of elective PCI mortality.

    BCIS published guidelines in 2000 in accord with the American College of Cardiology and American Heart Association guidelines 2001 for institutions suggest 200 PCI procedures per annum while encouraging PPCI centre to increase to a minimum of 400 procedures per annum17 (Table 11: BCIS Guidelines).

    Table 11: BCIS guidelines

British Cardiovascular Intervention Society

Service

Minimum total PCI per centre

PCI centers

200 - 400

Tertiary centers

500 - 800

    NIAP and the Department of Health recommend procedures should be carried out in a centre with a sufficiently high volume of cases to maintain and develop skills.

    The network recommend centres must undertake a minimum of 32518 ideally aiming for 400 total angioplasty procedures per annum and each operator must perform in excess of 75 angioplasties per year19

    The Network invited all providers within South Central to respond to the south central criteria with the option to support their response by presenting to a panel at meeting on the 1st April 2009. The panel discussed data which show better outcomes in acute / emergency patients (but not in elective patients) that undergo PCI in larger centres. One recent publication deals specifically with the volume of PCI activity as a function of outcome following PPCI for STEMI20. The odds ratio for death was 42% reduction in high volume vs low volume PCI centres, recommending a minimum of 50 procedures per annum.

    Table 12: Provider total PCI shows the numbers of PCIs undertaken in each centre during the year 2008/9 except SUHT whose data is from calendar year 2008. The network has calculated that each provider meets BCIS recommendation a total of 400 PCI per annum based on BCIS recommendations and that, should the commissioners decide to remove PPCI services from any centre the individual provider elective PCI activity would not be compromised.

    The network's sensitivity analysis suggests a possible increase in incidence of 1% per year due to population growth in the 40 -74 age category, or a possible decrease in incidence of 6% per year, if vascular checks are fully implemented and effective. It is likely therefore that commissioners would need to revisit the issue of contracting for elective PCI at a later date.

    Table 12: Provider total PCI

Provider

Current Service

Total PCI

2008/09

Basingstoke and North Hampshire Hospitals NHS Foundation Trust

24/7

412

Buckinghamshire Hospitals NHS Trust

8am - 6pm service

473

Heatherwood and Wexham Park Hospitals NHS Foundation Trust

8am - 6pm service

447

Oxford Radcliffe Hospital NHS Trust

24/7

1,670

Portsmouth Hospitals NHS Trust

8am - 6pm service

706

Royal Berkshire NHS Foundation Trust

24/7

582

Southampton University Hospitals NHS Trust

24/7

1,144

Total

5,434

    Clinical Teams

    The network has not been prescriptive about the composition of the clinical teams providing PPCI services. However; BCIS recommends a minimum number of experienced interventional cardiologists per centre of 4 and ideally 621 to maintain continuous cardiology cover. Table 13: Provider Operator Numbers demonstrates the number of actual and immediate operator numbers by provider.

    Table 13: Provider Operator Numbers

Provider

Current Service

Operator numbers

Basingstoke and North Hampshire NHS Foundation Trust

24/7

2 (soon to appoint a 3rd)

Buckinghamshire Hospital NHS Trust

8am - 6pm

3

Heatherwood & Wexham Park NHS Foundation Trust

8am - 6pm

3 (soon to appoint a 4th)

Oxford Radcliffe Hospital NHS Trust

24/7

7

Portsmouth Hospital NHS Trust

8am - 6pm

3 (soon to appoint a 4th)

Royal Berkshire NHS Foundation Trust

24/7

4

Southampton University Hospital NHS Trust

24/7

5

Totals

 

27 + 3

    All providers except BHT and BNHFT will meet BCIS recommendation within the next 6 months.

    NIAP emphasises the need to learn for other peoples experiences, the benefits of PCI for STEMI have been demonstrated in London, Leeds and Middlesbrough, where the package of care includes consultant cardiology involvement in ward rounds (at least once per day, preferably twice), access to Intensive Care and a consultant cardiology rota. Although not identified within the current criteria the panel supports the national direction of travel and would expect a cardiology rota to be maintained. BHT do not currently have nor plan to provide 24/7 cardiology rota. HWPFT do not currently provide 24/7 cardiology rota but have agreed that following engagement and consultation should the commissioners require this they would be happy to do so.

    Facilities

    Patients having a PPCI who were admitted directly to a catheter laboratory, bypassing accident and emergency departments/wards, had the lower time to treat and lowest mortality rates of all the routes of admission (NIAP 2008). (Table 14: Hospital Mortality). Avoiding admission through A&E would also benefit the A&E 4 hour wait target.

    Table 14: Hospital Mortality

In hospital mortality

18 month mortality

Direct Access to Catheter Lab

3.5%

7.0%

Admission Via Emergency Departments

6.0%

11.8%

    A centre performing PCI requires at least one cardiac catheterisation laboratory along with full resuscitation facilities (BCIS 2005). The BCIS conference June 2009 debated the need for a second laboratory and concluded two labs would allow downtime for maintenance and would improve patient access; BCIS felt this was a matter for local agreement. The Panel meeting on the 1st April 2009 discussed the need to mandate a minimum of 2 laboratories as per West and East Midlands cardiac network proposals. All units meet with current BCIS requirements of one laboratory and HWPFT will shortly have an additional pacing laboratory which would be able to be used for cardiac catheterisation, BNHFT and BHT do not have currently have a second laboratory. (Table 3: Current Service Provision (by provider)).

    3.3.4 Access to services should be equal for everyone with a need.

    The NHS Plan placed a general obligation on the Department to consider equality issues when shaping policy, but there are also legal obligations on the Department, for example to promote race equality. In addition, the Disability Discrimination Act 1995 makes it unlawful to discriminate against disabled people in connection with (among other things) the provision of services. It places a duty on local and other public authorities to change a policy in order to remove anything that would make it impossible for a disabled person to use a service.

    The Act also puts a duty on those authorities to promote disability equality. It requires new policies to be assessed to ensure that they do not disadvantage disabled people and for the methods of assessing a policy's impact to be set out. In addition, the Sex Discrimination Act 1975 (Public Authorities) (Statutory Duties) Order 2006 imposes specific duties on certain public authorities to ensure better performance in their duty to have due regard to the need to eliminate unlawful discrimination and to promote equality of opportunity between men and women22.

    The DoH undertook an Equality Impact Assessment (EIA) for the final report of the NIAP study. South Central has considered this EIA in relation to the possible impact of the new service on their population according to age, disability, race, religion and beliefs, gender and sexual orientation. Appendix G: Equality Impact Assessment identifies local factors affecting equality of access to services are as follows:

    · Portsmouth, Milton Keynes and the Isle of Wight will have the largest growth in population between 2006 and 2031.

    · Milton Keynes, Southampton City and the Isle of Wight will have the largest growth in males aged 40-74.

    · Milton Keynes, Portsmouth and Southampton will leave the largest growth in females aged 40-74.

    · Berkshire East will have the third lowest overall population growth during the same period but will have a significantly higher percentage and population growth of Asian or British Asian residents.

    · All areas within South Central have lower than national mortality rates with the exception of Berkshire West PCT who has a mortality rate higher than the national average.

    Please note at publication of this report the network and commissioners are in the process of rewriting the EIA to ensure the changes in PPCI services are reflective of each option.

    3.3.5 Preferred Options

    In South Central seven providers wish to provide PPCI: one wishes to continue providing 8am - 6pm service Monday to Friday excluding weekends and bank holidays; a second currently provides 8am - 6pm services but is willing to move to 24/7 should the commissioners wish them to and the remaining five wish to provide 24/7 PPCI services.

    Board of Commissioners November 2008

    In November 2008 the Network provided the Board of Commissioners (BoC) with a ranking of options, highest ranking was option A the 2 centers the JRH, Oxford and SUHT, Southampton.

    At the Board after some considerable discussion with members present, option A was rejected by as it did not provide an acceptable level of service across the whole region. It was agreed that on balance option C offered the basis of a way forward but some reworking to reflect the views expressed in the meeting would be needed prior to final approval.

    Board of Commissioners June 2009

    The Network presented the revised PPCI business case to BoC at their June meeting in Newbury. The following recommendations where supported:

    · Commencement of the Engagement period

    · Approval of the engagement plan

    · Return to BoC following the engagement period late autumn.

    Directors of Commissioning

    Part of this information gathering exercise included an interview panel on the 1st April 2009, comprising representation for the Directors of Commissioning (Appendix A: Panel Meeting), the panel developed three further criteria (Appendix C: Additional Criteria). Following the commissioner panel on the 1st April and in advance of further consultation with providers, patients and the public, the network with the directors of commissioning, recommend option D the four 24/7 centre option.

    Patient view

    The Network are recommending to BoC a period of engagement and consultation. However discussions with patients (section 3.3.1) suggest:

    · Patient experiences could be improved by speediness of treatment and being treated at the hospital at which they first presented.

    · The patients felt direct admission to a PPCI centre would reduce greatly reduced their anxiety.

    · Patients were confident about paramedics deciding where they should be admitted.

    · Most patients felt they would like to attend a large centre even if it meant passing their local hospital

    · The remaining patients felt they should have a PPCI centre at their local hospital.

    4 Areas which do not fall within the 40 minutes isochrones.

    4.1 M4 corridor

    PPCI services will not be available locally for residents within the area known as the M4 corridor within option A.

    4.2 Milton Keynes

    The Milton Keynes PCT is responsible for commissioning all the health services for a population of 230,300 (2006). It is responsible for spending more than £300 million each year, including £45 million on the services it directly provides. There were 111 people in Milton Keynes (MINAP 2007) who had a heart attacks benefitting from reperfusion therapy. Nationally, in-hospital mortality for patients treated by PPCI was 5.2% and 7.1% for patients treated with thrombolysis therapy (NIAP 2008). Although not directly comparable the office for national statistics suggests mortality at 18 months for PPCI patients is significantly less than patients treated with thrombolysis (Table 15: Mortality %)23.

    Table15: Mortality%

    Method of treatment

    30 days

    1 year

    18 months

    PPCI

    5.6

    8.7

    9.9

    Thrombolysis

    7.9

    12.4

    14.8

    Source: NIAP 2008

    Unfortunately the geographical location of Milton Keynes and its relationship to proposed PPCI centres described within the option appraisal document presented at the Board of Commissioners in November 2008, means that treatment of heart attack patients with PPCI is not achievable for some Milton Keynes residents within the 120 minute timeframe. The network therefore recommends that every effort should be made to make PPCI available to Milton Keynes residents.

    Population Projections

    Population projects for Milton Keynes for the years 2006 to 2031 suggest an increase of 32.1%. 84.3% of these are within the age group of 40-74 being the age range most likely to have reperfusion treatment. Table 16: Milton Keynes Population shows the population projections for Milton Keynes for the years 2011 to 2031 including projections for males and females aged 40-74 between 2011 and 2031. This age group has been selected as being of particular interest as the age range most likely to have reperfusion treatment. This data are taken from the 2006-based sub-national population projections produced by the Office for National Statistics.

    Table 16: Population projections for Milton Keynes 2011-2031

Milton Keynes

2011

2016

2021

2026

2031

Change %

Total Population

246,800

263,200

278,600

292,300

304,300

32.1

Males aged 40-74

51,200

55,500

58,100

60,600

63,700

40.9

Females aged 40-74

50,200

54,800

58,200

60,600

63,400

43.4

    Source: ONS 2006-based sub-national population projections

    Conclusion

    From population projections and an analysis of nearby populations, Milton Keynes may warrant a local centre in the future. However it is recognised that in the short term the John Radcliffe Hospital, Oxford will provide cover for Milton Keynes as long as the overall call to balloon time remains within a maximum of 120 minutes. In the longer term the network is working with three relevant PCTs, ambulance services and clinical networks from Bedfordshire, Northamptonshire and Milton Keynes to develop a medium to long term solution. A meeting has been arranged for the 21st July 2009.

    4.3 Isle of Wight

    The Isle of Wight NHS Primary Care Trust (PCT) is a unique NHS organisation, being the only one in the country which both commissions and provides such a broad and diverse range of health services for its local population. The Island has some particular health challenges. These include a high proportion of older people, unacceptable variation in life expectancy in different parts of the Island, thousands of residents on low incomes, 26,000 Islanders with life-limiting problems including a very significant prison population. New drugs and technologies, caring for an ageing population and rising patient and public expectations lead to additional challenges.

    Figure 17: Isle of Wight - call to balloon

    The Isle of Wight currently provides thrombolysis only, both in and out of hours Improvements to the care pathway for patients experiencing a heart attack may be limited by the island location (see Figure 17: Isle of Wight - call to balloon)... During severe weather or early hours the ferry is not always available resulting in a further delay transfer to the mainland of up to three hours or more.

    NIAP states `If an acceptable service cannot be established.....pre-hospital thrombolysis as the alternative reperfusion strategy is preferable to in-hospital thrombolysis'.

    Thrombolysis therapy supported by angiography within 24 hours at Portsmouth hospital has been put forward as the model for the residents of the IoW.

    Discussions between the IoW air ambulance Trust, SCAS, the IOW and Portsmouth NHS Trusts, the Air Ambulance Trust have agreed in principle to the helicopter transfer of STEMI patients from the IOW to Queen Alexandra Hospital Portsmouth during daylight hours, weather permitting. The planned new helicopter will have 24/7 capability from 2010 and will be less weather dependent.

    4.4 Buckinghamshire

    Buckinghamshire PCT serves a population of approximately 515,000 and supports 60 GP practices, 84 pharmacies, 85 optometrists and 82 dental practices. The PCT covers the whole of Buckinghamshire (with the exception of Milton Keynes and wards of Great Brickhill and Newton Longville) as well as the Oxfordshire wards of Aston Rowant, Chinnor, Thame North and Thame South. Patients referred to hospital are being seen faster than ever before. No patient has to wait longer than 18 weeks for routine treatment and waiting times for most people are set to fall to just 12 weeks by 2010.

    Seventy-nine people attended Stoke Mandeville and a hundred-fifteen High Wycombe Hospital (MINAP 2007) who had a heart attack benefit from reperfusion therapy Stoke Mandeville Hospital does not provide angiogram (PCI) services. All eligible patients are transferred to High Wycombe for treatments. In addition to this a small number of patients attended Hammersmith Hospitals during weekends, bank holidays and out of hours (OOH).

    Proposals for these areas are as follows:

    Option A: All patients will attend John Radcliffe Hospitals in Oxford.

    Option C: BHT will receive patients from its current catchment during 8am - 6pm hours excluding weekends and bank holidays. OOH approximately 25% of patients will go to Harefield Hospitals and the remaining 75% will go to the John Radcliffe Hospital.

    Option D: Approximately 25% patients will go to Harefield Hospitals and 75% to John Radcliffe Hospital.

    Within each of these options a call to balloon time of 120 minutes is achievable. Patient flows within each option depend on the geographical location of the patient. The paramedic will diagnose and transfer patients to the nearest centre which may result in patients from the East of Buckinghamshire attending Hammersmith Hospital.

    5 Finance

    The finance model consists of two distinct parts: first, the step change from the hybrid model of care of thrombolysis/PPCI to full PPCI implementation and secondly financial impact on the ambulance services. The current model has been costed using the patient flow maps for each provider within the previous section, and the new model has been costed assuming that all eligible patients will have a PPCI regardless of geographical location. The data source for patients who are symptomatic of STEMI is MINAP 2007/08 (Table 18: MINAP 2007/08); figures for 2008/09 will not be available until the beginning of June 2009.

    Table 18: MINAP 2007/08

Cluster

Provider

Unit

STEMI

nSTEMI

Total MI

Northern

ORH

JRH

203

328

531

Horton

51

109

160

BHT

WGH

115

161

276

SMH

79

104

183

MKGH

111

124

235

Central

HWHFT

Heatherwood

20

21

41

Wexham

75

76

151

RBFT

174

214

388

Southern

BNHFT

59

12

71

PHT

Queen Alexandra

339

480

819

IoW

St Marys Hospital

106

147

253

SUHT

401

331

732

RHCH

111

238

349

    Treatments for patients experiencing a STEMI are within Non-elective HRG 3.5 2007/08 Tariff costs (Table 19: HRG 2007/08). The following costs have not been considered within this financial model:

    · Costs for patients admitted with a suspected STEMI but a different diagnosis/ treatment determined on admission (eg Coronary Artery Bypass Graph).

    · Repatriation following procedure.

    · Readmission within 6 months of initial procedure.

    Table 19: HRG 2007/08

HRG code

HRG name

Non-elective spell tariff (£)

E11

Acute Myocardial Infarction with complications (wcc)*

4,787

E12

Acute Myocardial Infarction with out complications (w/o cc)*

3,017

E13

Cardiac Catheter & Angiography w cc*

4,716

E14

Cardiac Catheter & Angiography w/o cc*

3,744

E15

Percutaneous Coronary Intervention

5,010

    In addition to this, to indicate shifts in overall costs, taking into account repeat admissions, the network and directors of commissioning group engaged the Public Health Resource Unit (PHRU) to provide a report. This is a case study of the transition in Oxfordshire from a total thrombolysis service, through a hybrid thrombolysis/PPCI service to a full PPCI service. (Appendix B: Finance).

    5.1 PPCI costs based on actual numbers of patients during 2008/09 (MINAP)

Table 20: Financial Summary

 

Current

Option A

Option C

Option D

Northern Cluster

 

 

 

 

BHT

£ 894,290

£ 883,860

£ 883,860

£ 883,860

MKFT

£564,441

£ 509,538

£ 509,538

£ 509,538

OHT

£1,015,200

£1,015,200

£1,015,200

£1,015,200

Subtotal

£2,473,931

£2,408,598

£2,408,598

£2,408,598

Central Cluster

 

 

 

 

HWPFT

£ 440,319

£ 433,176

£ 433,176

£ 433,176

RBFT

£ 794,736

£ 794,736

£ 794,736

£ 794,736

Subtotal

£1,235,055

£1,227,912

£1,227,912

£1,227,912

Southern Cluster

 

 

 

 

BNHFT

£ 235,814

£ 224,076

£ 224,076

£ 224,076

RHCH

£ 783,612

£ 525,780

£ 525,780

£ 525,780

PHT

£1,478,484

£1,385,368

£1,385,368

£1,385,368

SUHT

£1,968,830

£1,968,830

£1,968,830

£1,968,830

IoW

£ 645,131

£ 645,131

£ 642,036

£ 642,036

Subtotal

£5,111,871

£4,749,185

£4,746,090

4,746,090

 

 

 

 

 

Sub-Total

£8,820,857

£8,385,695

£8,382,600

£8,382,600

Prescribing Clopidogrel

 

£ 11,964

£ 11,964

£ 11,964

SCAS additional Costs

 

£ 20,564

£ 13,430

£ 14,236

Total

£8,820,857

£8,418,223

£8,407,994

£8,408,800

    5.2 HRG Version 4

    The potential impact of HRG version 4 (Table 21: HRG 2008/09) codes on costs used within this paper are;

    · V4.0 non elective tariffs differentiate between the approximately 90% of straightforward cases requiring up to 2 stents and those which are more complex

    · In nearly all cases in South Central the tariff to apply includes insertion of the stent and catheterisation, which the Payment by Results team advises covers angiogram with possible proceed to PCI. Other codes cover supplementary work (Elieen Robertson, DH PBR, personal communication, 28.4.09)

    · It is safe to assume that the median tariff for a non elective spell including PPCI would be £5441.00  (mean average £5542.00)

    · This would inflate current assumptions by £431.00 per patient for PPCI if HRGs are applied consistently. Commissioners should investigate if the tariff uplift has taken account of this

    · This may be balanced against the removal of the specialist top up for cardiac services. At 18% this would raise the price for HRG version 3.5 E15 to £5912.00

    · The trim points are generous given an average length of stay for PPCI in NIAP of 3 days

    Table 21: HRG 2008/09

HRG code

V4.0 HRG name

Non-elective spell tariff (£)

Long stay trimpoint (days)

EA31Z

PCI (0-2 stents)

4706

10

EA32Z

PCI (0-2 stents) & catheterisation

5441

16

EA33Z

PCI (3 or more stents)

5281

11

EA34Z

PCI (3 or more stents) & catheterisation

6453

17

EA35Z

Other Transluminal Interventions

3643

17

EA36Z

Catheter 19 yrs & over

3303

21

EB10Z

Actual or suspected MI

3662

18

    5.3 Conclusion

    The financial model assumed tariff costs HRG 3.5, modelled activity supplied by MINAP 2007/8 and used current service models and those proposed within each option as follows;

Option

PCT

Additional SCAS

Prescribing

Total

D

£8,382,600

£ 14,236

£ 11,964

£8,408,800

C

£8,382,600

£ 13,430

£ 11,964

£8,407,994

A

£8,385,695

£ 20,564

£ 11,964

£8,418,223

Current

£8,820,857

£8,820,857

    Currently only a small number of patients from Berkshire East and Buckinghamshire attend London hospitals as most OOH patients are treated either at HWWP or BHT with thrombolysis therapy and PCI/angiogram within normal working hours. Patients will in the new options go directly to the nearest 24/7 heart attack centre for PPCI. For Buckinghamshire and Berkshire East this means all OOH patients will attend Harefield Hospital. The change in provider will mean a transfer of costs from PCTs to SCSCG.

    The model is inclusive of readmission for same HRG procedures (nationally 12%24). Direct discharge from the heart attack centres is assumed within all of the options. No costs have been included for transfer to local hospitals post procedure.

    6 PPCI Implementation

    It is anticipated that the proposal subject to formal consultation to implement PPCI across South Central will be made at the June 2009 BoC meeting. To allow effective implementation of services a number of key tasks will be required;

    · Notification of decision to Providers

    · Engagement and Public Consultation

    · Implementation timescales

    · Formation of task and finish groups

    · Post implementation review

    6.1 Engagement and Consultation

    In October 2008 the network hosted a meeting at Newbury racecourse with providers (clinicians and managers), commissioners and associated networks to discuss the provision of PPCI within South Central. The results of which were circulated to all parties. This prompted further dialogue with providers on the 1st April 2009 from which this paper was formulated.

    The network undertook three informal engagement meetings with cardiac rehabilitation patients as reported previously in section 3; they support the concept of PPCI. Patients gave a mixed response to the locations of the PPCI centres. Some patients preferred services at their local DGH and others within tertiary centres.

    In total approximately 40 patients were interviewed. In view of this response and the requirement under section 242 (1B) of the NHS act 2006 - Public involvement and consultation which states

     

    "Each relevant English body must make arrangements, as respects health services for which it is responsible, which secure that users of those services, whether directly or through representatives, are involved in-

     

    a) the planning of the provision of those services,

    b) the development and consideration of proposals for changes in the way those services are provided, and

    c) decisions to be made by that body affecting the operation of those services"

     

    The Network has appointed a consultancy firm: "Communications Management: Building Reputations" to undertake a period of engagement and consultation with all stakeholders including commissioners, providers, patients and the public. The network is seeking approval from the Board of Commissioners to commence an Engagement and Consultation program for a period completing March 2010

    6.2 Timescales

    Table 22: Timescales

    Date

    Key Milestone

    June 09

      · BoC approval

          _ Commence engagement phase for options A, C and D

          _ Engagement Strategy and Plan (Appendix E [currently being rewritten in accordance with BoC criteria])

          _ Return to BoC with a engagement Report and recommendations for the consultation phase

    July to Oct 09

      · Engagement phase of engagement and consultation

    Nov 09

      · Engagement review and report to BoC

    Dec 09 to Feb 10

      · Consultation

    Preparation for PPCI implementation

      · To develop service specifications to guide the SHA, commissioners and other stakeholders, based on clinical consensus and high quality data.

      · To develop and implement evidence based, uniform clinical standards, guidelines and protocols across the network where these do not exist.

      · Maintain strong clinical engagement to enable improvements in practice and co-operation along patient pathways.

      · To act as a consultancy and educational resource for clinical and service quality improvement work in PCI

      · Working with the SHA, to understand and support commissioning clusters for quality by contributing to network wide comparative benchmarking, audit and clinical quality indicators and outcomes.

      · Provide clinically based advice to inform workforce planning, inputting to the education and training strategy for relevant professional groups.

      · Provide a detailed implementation plan

    March 2010

      · Final report to BoC for decision

    April 2010

      · Commence implementation process

    Nov 11

      · PPCI implementation complete

    7 Conclusion

    The options for the implementation of PPCI are;

    · 24/7 PPCI in 2 centres, the John Radcliffe Hospital (JRH), Oxford and Southampton University Hospital NHS Trust (SUHT).

    · 24/7 PPCI in 4 centres, the JRH, SUHT, PHT and RBFT. Plus Monday to Friday 8am - 6pm services (excluding weekends and bank holidays) in 3 centres, BHT, BNHFT & HWPFT

    · 24/7 in 4 centres, the JRH, SUHT, PHT and RBFT.

    Option D has been identified as a potential solution for the following reasons;

    · It is recognised that these four centres meet or are willing to meet the National and Local criteria for the provision of a safe, sustainable and accessible service.

    · SCAS preference supports this model as it delivers clear patient flows and retains the ambulance crews and vehicles near to their base thus reducing the amount of downtime caused by excessive journeys within option A.

    · Financial modelling based on data provided by MINAP 2007/08, current and planned service models, HRG 2008 version 3.5, excluding readmission and inter-hospital transfers, suggests option C will offer best value for money.

    The Network recommends a period of engagement for options A, C and D to bring to light any valuable information which the commissioners can make informed decisions to improve the delivery of PPCI within South Central.