Archived decisions

HAMPSHIRE COUNTY COUNCIL

Executive Decision Record:

Decision Maker:

Executive Member for Policy and Resources

Date of Decision:

23 July 2009

Decision Title:

Norman Gate School, Andover

Decision Reference:

723

Report From:

Director of Property, Business and Regulatory Services

Contact name:

Steve Clow

Tel:

01962 847858

Email:

steve. [email protected]

1. The Decision:

 

    That the design for the proposed extension and internal reconfiguration/ refurbishment at Norman Gate School, Andover, at an estimated total cost of £726,000 (including fees of £96,000) be approved.

 

2. Reasons for the decision

    The proposed scheme will maximise wellbeing and enhance the quality of place by providing extended and refurbished accommodation.

3. Conflicts of Interest:

    3.1. Conflicts of interest declared by the decision-maker:

    None

 

    3.2. Conflicts of interest declared by other Executive Members consulted:

    The Executive Member for Education declared a personal prejudicial interest in this proposal as he is a Governor at Norman Gate School. Accordingly, the executive decision making was referred to the Executive Member for Policy and Resources.

 

4. Other options considered and rejected:

    The need for the works has been identified as a priority and the works set out in the report are considered to be the most appropriate and cost-effective way of meeting that need.

 
 

5. Dispensation granted by the Standards Committee: None

 

6. Any reasons for the matter being dealt with if urgent : Not applicable

 

7. Statement from the Decision Maker:

 

Approved by:

--------------------------------------------------

23 July 2009

Executive Member for Policy and Resources

Councillor T K Thornber, CBE