Archived decisions
HAMPSHIRE COUNTY COUNCIL
Decision Report:
Decision Maker: |
Executive Lead Member for Children's Services |
Date of Decision: |
17 December 2009 |
Decision Title: |
Major Projects Status Report |
Decision Reference: |
980 |
Report From: |
Director of Property, Business and Regulatory Services |
Contact name: |
Steve Clow | ||
Tel: |
01962 847858 |
Email: |
steve. [email protected] |
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Lead Member for Children's Services and the Executive Member for Policy and Resources.
1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Children's Services Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
1.3 The schemes within this report generally reflect the priorities in the Corporate Strategy by providing excellent school facilities which enhance the quality of place, providing safer and more accessible facilities and maximising well-being, thus benefiting all users of the premises.
2. Completed Schemes
2.1 Since the last meeting of the Executive Lead Member for Children's Services schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Bentley Primary School (extension) November 09
Crestwood College, Eastleigh (internal refurbs) July 09
Crestwood College, Eastleigh (landscape) August 09
Fordingbridge Junior School (extension) September 09
Henry Beaufort Secondary School, Winchester (STP) October 09
Knights Enham Schools, Andover (extension) August 09
Park Gate Primary School (extension) September 09
Roman Way Primary School (extension) November 09
Thornden School, Chandler's Ford (extension) December 09
3. Additional Works and Funding Added Post Contract
The following schemes have had further funding added to the contract for specific additional works.
3.1 Sopley Primary School, Christchurch - classroom extension
The following additional Landlord contributions have been made:
P&R 2009/10 (engineering) - water main upgrade 7,000
P&R 2009/10 (electrical) - electrical upgrade 10,000
P&R 2009/10 (electrical) - electrical mains upgrade 10,000
The School has made an additional contribution to the
scheme to cover the cost of additional works to fit out
the first floor to form a multi-purpose space
School (devolved capital) 65,000
3.2 Wyvern Technology College, Eastleigh - J-track
The School has contributed a further £11,000 of devolved capital towards the cost of additional fencing and footpath works requested by them.
A contribution of £76,000 P&R funding has been made to cover drainage works and regrading of existing pitches.
4. Additional Works and Funding added at Pre Contract Stage
Appendix 1 and 2 provide detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' for Children's Services and Policy and Resources.
Additional funding has come from various sources including increased Children's Services Capital Programme allocations, and inflation and tolerance adjustments; additional school funding for specific additional requested works, and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
4.1 Dove House School, Basingstoke - covered sports pitch
Following a review of this project, the school has increased their level of funding to complement the scale and scope of proposals they have asked the Director of PBRSIT to design. The proposals can now progress to planning stage and engagement of a main contractor through a mini-competition. The final programme of works and completion date is currently being assessed and will be updated in the next Major Projects report.
A contribution of £50,000 from Policy and Resources NDS Capital Repairs has been made to replace and upgrade failing services infrastructure which have also reached capacity.
4.2 Wildern Secondary School, Hedge End - New Theatre
Following a successful bid to the DCSF for Colocation Funding, an additional £700,000 (including fees) has been added to the scheme to ensure its viability. The increased funding is being used to ensure that the theatre has a full suite of specialist technical equipment at completion.
The additional money will also cover the costs of gaining a BREEAM `very good' rating, and increasing the quality and robustness of finishes in the building.
5. Programme updates
5.1 Crofton School, Stubbington - extension to form resource for autistic pupils
Start on site has been delayed due both to ecology issues (which have now been resolved) and the need for a redesign of the proposed foundations due to poor ground conditions.
The scheme is currently being tendered and it is now anticipated that works will commence on site during January 2010 and complete during September 2010.
5.2 Noadswood School, Dibden Purlieu - Mini STP/tennis court
The scheme was originally programmed to commence on site during September 2009 and the works have been negotiated with a Framework Contractor. However, the scope of the works is currently being reassessed in order to ensure that the cost stays within the available budget. It is now anticipated that works will commence on site during November 2009 and be completed during December 2010.
5.3 Wyvern Technology College, Eastleigh - J-track
The scheme commenced on site during February 2009 but due to the presence of a protected reptile species on an adjacent site, the programme has been delayed by approximately three months and is now scheduled to complete during January 2010.
6. East Anton Primary School, Andover - enabling works
6.1 Following reports to the Buildings Land and Procurement Panel on 2 October 2009 and the Executive Lead Member for Children's Services on 15 October 2009 outlining proposals for a temporary school at East Anton, approval is now sought to enabling works at a total estimated cost of £658,000 (including fees).
6.2 The four-classroom temporary school will be sited on the northern primary school site reserved for a new, permanent school to serve the major housing development at East Anton, Andover. The temporary school, comprising of four classrooms and associated teaching and admin spaces, is required to accommodate the predicted numbers of children arising from the early dwelling completions of the wider residential development. The temporary school is required to be operational for the summer term 2010. Should it be required, a further three temporary classrooms can be accommodated on site taking the capacity of the temporary school to one form of entry. The works will also include the formation of the formal sports pitch that will service the permanent school, together with an area of formal hard play which will also be utilised by the permanent school.
6.3 A planning application for the temporary school was submitted in October 2009. This application will presented to Hampshire County Council's Regulatory Committee on 13 January 2010 for determination. It is anticipated the works will commence on site in February 2010 and complete in April 2010.
6.4 A project appraisal for the proposed new school will be submitted to the Buildings, Land and Procurement Panel and Executive Member for Policy and Resources in the New Year.
Recommendations
1. That progress on the major capital projects being undertaken by the Director of Property, Business and Regulatory Services be noted.
2. That approval is given to the enabling works at East Anton Primary School, Andover, at a total value of £658,000.
Links to the Corporate Strategy
Hampshire safer and more secure for all: |
yes |
Corporate Business plan link number (if appropriate): | |
Maximising well-being: |
yes |
Corporate Business plan link number (if appropriate): | |
Enhancing our quality of place: |
yes |
Corporate Business plan link number (if appropriate): | |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
Published works.
Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules Project Appraisal
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Abbott's Ann C of E Primary School Andover - New School |
On site |
April 09 |
March 2010 |
* 3,313,603 |
Capital Prog 08/09 3,293,000 School devolved capital 62,000 P&R 2008/09 contribution 25,000 3,380,000 Capital Prog 08/09 31,000 3,411,000 |
Bentley Primary School - extension to provide new hall |
Complete |
April 09 |
Nov 09 |
*566,000 |
Capital Prog 08/09 258,000 School devolved capital 308,000 566,000 |
The Bridge Education Centre, Eastleigh - extension, refurbishment, reclad, reroof |
On site |
April 09 |
March 10 |
*2,526,885 |
Capital Programme 07/08 1,415,000 P&R Capital Repairs 07/08 322,000 Devolved capital budget 134,000 CAMHS 455,000 2,326,000 |
Brookfield Community School and Language College Sarisbury Green - Adult Safe Learning facility |
On site |
Oct 09 |
March 10 |
405,000 |
Capital Programme 08/09 43,000 Learning & Skills Council 362,000 405,000 |
Brune Park Community College Gosport - swimming pool refurbishment
|
Design |
Jan 2010 |
June 2010 |
689,000 |
Capital Prog 09/10 163,000 School devolved capital 270,000 P&R Capital Repairs 09/10 256,000 689,000 |
Crestwood College for Business and Enterprise Eastleigh - landscape improvements |
Complete |
Jan 09 |
August 09 |
*450,000 |
Capital Prog 08/09 450,000 |
Crestwood College for Business and Enterprise Eastleigh - internal refurbishment (food catering) |
Complete |
April 09 |
July 09 |
*222,921 |
14-19 funding (2007/08) 110,000 NDS Modernisation (2007/08) 15,000 School devolved capital 105,000 P&R Landscape fund (2008/09) 30,000 260,000 |
Crofton School Stubbington - extension to form resource for Autistic pupils |
Tender |
Jan 10 |
Sept 10 |
830,000 |
Capital Prog 09/10 830,000 |
Dove House, Basingstoke - covered sports pitch |
Design |
TBC |
TBC |
660,000 |
Capital Programme 09/10 50,000 Policy & Resources NDS 50,000 School devolved capital 560,000 660,000 |
East New Forest CLD School - new school |
Enabling works - Complete Phase 1 - main works Phase 2 - demolition/ landscaping |
Aug 09 Jan 2010 March 2011 |
Nov 09 Jan 2011 June 2011 |
9,838,000 |
Capital Programme 09/10 9,838,000 |
Fordingbridge Junior School Fordingbridge - extension and refurbishment |
Complete |
June 09 |
Sept 09 |
275,000 |
Capital Programme 09/10 70,000 L/L P&R Cap Repairs 75,000 School 130,000 275,000 |
Hamble Sixth Form College - new LSC building |
On site |
April 09 |
March 10 |
6,837,000 |
Capital Programme 07/08 (LSC) 6,837,000 |
Hamble Community Sports College Hamble - sports pavilion |
On site |
Nov 09 |
July 2010 |
650,000 |
School devolved capital 382,000 School LMS 268,000 650,000 |
Henry Beaufort School, Winchester - provision of Synthetic Turf Pitch (STP)
|
Complete |
Summer 09 |
Oct 09 |
550,000 |
School Funding (community funds/ devolved capital) 110,000 Winchester City Council 103,000 Football Foundation Grant funding 337,000 556,000 |
Henry Beaufort School, Winchester - Hearing Impaired Unit refurbishment |
On site |
Aug 09 |
Dec 09 |
407,000 |
Capital Programme 09/10 SAI 407,000 |
The Hurst Community College Tadley - Adult Learning Centre and crèche |
On site |
Oct 09 |
March 10 |
713,000 |
Capital Programme 09/10 57,000 Learning & Skills Council 544,000 P&R L/L NDS 09/10 112,000 713,000 |
Knights Enham Infant and Junior Schools Andover - extension and refurbishment |
Complete |
July 08 |
Aug 09 |
3,638,000 |
Capital Programme 08/09 3,320,000 Schools - devolved capital 213,000 P&R contributions 08/09 77,000 NDS Condition 08/09 28,000 3,638,000 3,638 |
Meadowlands Junior School Waterlooville |
On site |
July 09 |
August 10 |
2,258,000 |
Capital Programme 09/10 2,150,000 School devolved capital 50,000 P&R Capital Repairs 58,000 2,258,000 |
Noadswood School, Dibden Purlieu - Mini Synthetic Turf Pitch and tennis court enhancements |
Design |
Nov 09 |
Dec 10 |
400,000 |
School devolved capital 300,000 DCSF Specialist Schools Grant 100,000 400,000 |
Norman Gate, Andover - Extension and internal refurbishment |
Contract |
Feb 2010 |
Oct 10 |
726,000 Cap |
Capital Programme 09/10 576,000 School - devolved capital 150,000 726,000 |
Park Gate Primary School - two-class extension and internal refurbishments/ alterations |
Complete |
Jan 09 |
Sept 09 |
*710,000 |
Capital Programme 08/09 457,000 School - devolved capital /LMS 204,500 SAI 49,000 710,500 |
Robert May's School, Hook - provision of a Synthetic Turf Pitch (STP) |
Design |
TBC |
TBC |
553,000 |
Children's Services Capital Programme 08/09 146,000 School devolved capital 93,000 Football Foundation grant 314,000 553,000 |
Roman Way Primary School - extension |
Complete |
March 09 |
Nov 09 |
*1,349,000 |
Children's Services Capital Programme 08/09 1,423,000 School (devolved capital) 117,000 P&R 08/09 23,000 1,563,000 |
Sopley Primary School - classroom extension |
On site |
Aug 09 |
Easter 2010 |
*446,000 |
Capital Programme 2009/10 258,000 School (devolved capital) 158,000 P&R Capital Repairs programme 2009/10 (boiler room) 55,000 P&R Capital Repairs programme 2009/10 (cesspool) 20,000 P&R 2009/10 (electrical) 20,000 P&R 2009/10 (engineering) 7,000 Capital Programme 2009/10 (cesspool) 20,000 538,000 446 |
Thornden School, Chandler's Ford - extension/refurbishment |
Complete |
June 09 |
Dec 09 |
School d/c 514,000 School revenue budget (LMS) 82,000 L/L Cap Repairs budget 100,000 696,000 | |
Wildern Secondary School Hedge End - New Theatre |
Tender |
Jan 2010 |
Dec 2010 |
4,500,000 |
Eastleigh Borough Council 3,500,000 School 300,000 3,800,000 DCSF Colocation funding 700,000 4,500,000 |
Wyvern Technology College Eastleigh - J Track
|
On site |
Feb 09 |
Jan 10 |
*404,000 |
Capital Programme 08/09 125,000 107 18 125 School devolved capital 100,000 Eastleigh Borough Council 150,000 SITA Trust (Landfill Tax) 9,000 Capital Programme contingency - (subject to tender return) 20,000 404,000 Additional funding: School devolved capital 11,000 P&R 09/10 76,000 491,000 |
Appendix 2
Other Schemes in the Children's Services Capital Programme
The following schemes are included in the Children's Services 2009/10 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Lead Member for Children's Services or Policy and Resources:
Allocation
School (including fees)
£'000
PRIMARY
Barncroft Primary School, Havant |
tbc |
Bedenham Primary School site (Assessment Observation Unit) |
500 |
Crondall Primary School, Farnham |
300 |
East Anton Primary School, Andover |
7,000 |
Greenfields Junior School, Hartley Wintney |
495 |
Picket Twenty Primary School |
6,000 |
Stanmore Primary |
450 |
Weeke Primary School |
250 |
West of Waterlooville Primary School |
tbc |
Woolton Hill Junior School, Newbury |
tbc |
Wootey Infant School, Alton |
tbc |
Yateley Infant School |
tbc |
SECONDARY
Aldworth Science College, Basingstoke |
1,000 |
Henry Beaufort Secondary School, Winchester |
350 |
Hamble Community Sports College |
565 |
King's School, Winchester |
tbc |
Noadswood Secondary School, Dibden Purlieu |
351 |
Perins Community School, Alresford |
tbc |
Park Community School, Havant |
tbc |
Ringwood Secondary School |
5,000 |
Wildern Secondary School |
3,305 |
SPECIAL
Norman Gate Special School |
494 |
EDUCATION OTHER THAN AT SCHOOLS
Children's Centres Stage III |
9,160 |
Childcare Provision (PVI) |
7,500 |
Runways End (provision of Youth Activities Centre) |
6,097 |