    HAMPSHIRE COUNTY COUNCIL

    Executive Decision Record

Decision Maker:

Executive Member - Environment

Date of Decision:

12 January 2010

Decision Title:

Approach to Local Transport Plan 3

Decision Reference:

1185

Report From:

Director of Environment

Contact name:

Geoff Hobbs

Tel:

01962 846811

Email:

[email protected]

    1. The following decision was made:

      That the proposed timetable for Local Transport Plan 3 development set out in Appendix D be approved (as amended).

    2. Reasons for the decision:

    2.1. To facilitate the timely development and preparation of a Hampshire Local Transport Plan 3 (LTP3) that is ready to come into force on 1 April 2011, when the current LTP2 expires.

    2.2. To agree a timetable of key milestones that will be used as the basis for future decision making by the County Council regarding preparation and formal adoption of a Hampshire LTP3.

    3. Other options considered and rejected:

    3.1. Not to produce an LTP3. This option was rejected because Hampshire County Council has a statutory duty to produce an LTP. The current LTP expires on 31 March 2011.

    4. Conflicts of interest:

    4.1. Conflicts of interest declared by the decision-maker: none.

    4.2. Conflicts of interest declared by other Executive Members consulted: none.

    5. Dispensation granted by the Standards Committee: none.

    6. Reason(s) for the matter being dealt with if urgent: not applicable.

    7. Statement from the Decision Maker:

Approved by:

--------------------------------------------------

Date:

12 January 2010

Executive Member for Environment

Councillor M J Kendal

 

    2143Decn/1185/GH

Appendix D:

Outline of principal stages in development of Hampshire LTP3 from Autumn 2009 to Spring 2011

 

Key Milestone

 
     
 

Workshops with County Councillors on goals, problems and challenges

October/November 2009

 

Initial consultation on goals, problems and challenges to help inform development of a draft strategy

November/December 2009

     
 

Seek formal approval of programme for LTP3 development from Hampshire County Council Executive Member for Environment

January 2010

 

Use feedback from initial consultation to write draft Hampshire LTP3 Strategy

January to April 2010

     
 

Engagement with County Councillors on draft LTP3 Strategy

March 2010

     
 

Executive Member for Environment approves consultation draft of LTP3 Strategy

April 2010

     
 

Full public consultation on draft LTP3 Strategy

May to August 2010

 

Agree prioritised list of schemes for delivery during three year Implementation Plan period based on a range of estimates of likely funding levels

August to September 2010

 

Approval of Draft LTP3 Strategy and Implementation Plan by Cabinet

Approval of Final LTP3 Strategy and Implementation Plan by Cabinet

October 2010


January 2011

 

Approval of Final LTP3 Strategy and Implementation Plan by Full Council

Full Council meeting after Cabinet approval

     
 

Submit to DfT (and relevant bodies)

31 March 2011

 

Hampshire Local Transport Plan 3 comes into force

1 April 2011