The proposed scheme will help to improve pedestrian accessibility and safety by providing the missing link of approximately 50m of new footway linking two existing footways in Long Lane which extends through a residential estate.
Vegetation clearance on the northern side of Long Lane will be carried out to help improve visibility and will allow the extension of the existing footway to a point just east of the Southampton Football Club training ground entrance. An area of grass verge will be in place to segregate the footway from the adjacent fences.
Approval to progress with implementation of the scheme was given at the Executive Member for Environment and Transport Decision Day . The scheme is currently under review.
- Download plan
- Please view the technical plan here.
- Contact us
-
- Name Highways, Engineering and Transport
- Email [email protected]
- Phone 0300 555 1388
Universal Services
Hampshire County Council
The Castle
Winchester
SO23 8UD