Planned maintenance

Operation Resilience is a long term strategy to make Hampshire's roads more resilient to the effects of extreme weather and heavy traffic

Operation Resilience is a long term strategy to make Hampshire's roads more resilient to the effects of extreme weather and heavy traffic.

Planned maintenance is a better way to maintain roads for the future because it is more cost effective and the work lasts longer.

The table shows the upcoming planned works pending some final decisions based on current network condition. Please be aware that the proposed dates of work can change for various reasons, such as emergencies, utility works, inclement weather, etc. With this in mind, Roadworks.org has up to date information on all road works.

Scheme reference Road name Treatment Type Quarter District
B730 Bushywarren Lane Carriageway structural repairs October - March Basingstoke
B735 Lower Wyke Drainage July - September Basingstoke
B851 Brighton Way/Sullivan Way Carriageway resurfacing Completed Basingstoke
SD-B18001 Timberlake Road Carriageway surface treatment Completed Basingstoke
SD-B18001A Summer Down Lane Carriageway surface treatment July - September Basingstoke
SD-B18002 Heather Way Carriageway surface treatment Completed Basingstoke
SD-B18002A Wolverton Road Carriageway surface treatment July - September Basingstoke
SD-B18003 A340 Ringway West (southbound c'way only) Carriageway surface treatment Completed Basingstoke
SD-B18003A Sherfield Road Carriageway surface treatment July - September Basingstoke
SD-B18004 Garlic Lane Carriageway surface treatment Completed Basingstoke
SD-B18004A Pinkerton (S Spur) Carriageway surface treatment July - September Basingstoke
SD-B18005 Rowan Road Carriageway surface treatment Completed Basingstoke
SD-B18005A St Peters Road (N Spur) Carriageway surface treatment July - September Basingstoke
SD-B18006 Reading Road Carriageway surface treatment Completed Basingstoke
SD-B18008 Hanmore Road Carriageway surface treatment Completed Basingstoke
SD-B18009 Bowman Road Carriageway surface treatment Completed Basingstoke
SD-B18010 Thornhill Way Carriageway surface treatment Completed Basingstoke
SD-B18011 Old Reading Road Carriageway surface treatment Completed Basingstoke
SD-B18013 Kingsclere Road Carriageway surface treatment Completed Basingstoke
SD-B18015 London Road Carriageway surface treatment Completed Basingstoke
SD-B18018 High Drive Carriageway surface treatment Completed Basingstoke
SD-B18019 Ash Lane Carriageway surface treatment Completed Basingstoke
SD-B18020 Frog Lane Carriageway surface treatment Completed Basingstoke
SD-B18021 Church Lane Carriageway surface treatment Completed Basingstoke
SD-B18022 Hook Lane Carriageway surface treatment Completed Basingstoke
SD-B18023 Ibworth Lane Carriageway surface treatment Completed Basingstoke
SD-B18024 Poveys Mead Carriageway surface treatment Completed Basingstoke
SD-B18025 Yew Close Carriageway surface treatment Completed Basingstoke
SD-B18026 Queens Road Carriageway surface treatment Completed Basingstoke
SD-B18027 Sandford Close Carriageway surface treatment Completed Basingstoke
SD-B18028 Hook Road Carriageway surface treatment Completed Basingstoke
SD-B18029 Hackwood Lane Carriageway surface treatment Completed Basingstoke
SD-B18030 Down Farm Lane Carriageway surface treatment Completed Basingstoke
SD-B18031 Village Road Carriageway surface treatment Completed Basingstoke
SD-B18032 Tunworth Road Carriageway surface treatment Completed Basingstoke
SD-B18033 Longbridge Close Carriageway surface treatment Completed Basingstoke
SD-B18034 Aghemund Close (Spine and Spurs) Carriageway surface treatment Completed Basingstoke
SD-B18035 Meadowlands Carriageway surface treatment Completed Basingstoke
SD-B18037 Sydmonton Road Carriageway surface treatment Completed Basingstoke
SD-B18038 A30 London Road (EB CW) Carriageway surface treatment Completed Basingstoke
SD-B18039 Laverstoke Lane Carriageway surface treatment Completed Basingstoke
SD-B18040 Steventon Warren Lane Carriageway surface treatment Completed Basingstoke
SD-B18041 Steventon Road Carriageway surface treatment Completed Basingstoke
SD-B18042 Stubbs Hill Carriageway surface treatment Completed Basingstoke
SD-B18043 White Hill Road Carriageway surface treatment Completed Basingstoke
SD-B18044 A30 London Road Carriageway surface treatment Completed Basingstoke
SD-E18001 Chestnut Avenue Carriageway surface treatment Completed East Hants
SD-E18001A Stroudwood Road Carriageway surface treatment July - September Eastleigh
SD-E18002 Grange Road Carriageway surface treatment July - September Eastleigh
SD-E18002A Salwey Road Carriageway surface treatment July - September Eastleigh
SD-E18003A Ambleside Carriageway surface treatment July - September Eastleigh
SD-E18004A Tickner Close (inc spurs) Carriageway surface treatment July - September Eastleigh
SD-E18005 Winchester Road Carriageway surface treatment Completed Eastleigh
SD-E18005A Paxton Close Carriageway surface treatment July - September Eastleigh
SD-E18006 Nichol Road Carriageway surface treatment July - September Eastleigh
SD-E18006A Orchard Avenue Carriageway surface treatment July - September Eastleigh
SD-E18007 Heathfield Road Carriageway surface treatment July - September Eastleigh
SD-E18007A Patricia Close Carriageway surface treatment July - September Eastleigh
SD-E18008 Sycamore Avenue (inc spur) Carriageway surface treatment July - September Eastleigh
SD-E18008A Rusland Close Carriageway surface treatment July - September Eastleigh
SD-E18009 Ashdown Road Carriageway surface treatment July - September Eastleigh
SD-E18010 Charnwood Crescent Carriageway surface treatment July - September Eastleigh
SD-E18012 Alexandra Road Carriageway surface treatment July - September Eastleigh
SD-E18013 Albert Road Carriageway surface treatment July - September Eastleigh
SD-E18014 Upper St Helens Road Carriageway surface treatment July - September Eastleigh
SD-E18015 Lower St Helens Road Carriageway surface treatment July - September Eastleigh
SD-E18016 Charnwood Close Carriageway surface treatment July - September Eastleigh
SD-E18017 Charnwood Gardens Carriageway surface treatment July - September Eastleigh
SD-E18018 Shamblehurst Lane North Carriageway surface treatment July - September Eastleigh
SD-E18019 Fir Tree Lane Carriageway surface treatment July - September Eastleigh
SD-E18020 Witt Road Carriageway surface treatment July - September Eastleigh
SD-E18022 Downland Place Carriageway surface treatment July - September Eastleigh
SD-E18023 Coultas Road Carriageway surface treatment July - September Eastleigh
SD-EH18001 A325 Farnham Road Carriageway surface treatment Completed East Hants
SD-EH18001A Mill Lane Carriageway surface treatment July - September East Hants
SD-EH18002 Medstead Road Carriageway surface treatment Completed East Hants
SD-EH18002A Hollywater Road Carriageway surface treatment July - September East Hants
SD-EH18005 Selborne Road Carriageway surface treatment Completed East Hants
SD-EH18006 Fareham Road Carriageway surface treatment Completed East Hants
SD-EH18007 Farnham Road Carriageway surface treatment Completed East Hants
SD-EH18008 Viking Way Carriageway surface treatment Completed East Hants
SD-EH18009 First Avenue Carriageway surface treatment Completed East Hants
SD-EH18010 Five Heads Road Carriageway surface treatment Completed East Hants
SD-EH18012 Dell Piece East Carriageway surface treatment Completed East Hants
SD-EH18013 Winkfield Row Carriageway surface treatment Completed East Hants
SD-EH18014 Blenheim Road (Spur and Spine) Carriageway surface treatment Completed East Hants
SD-EH18015 Woodstock Avenue (Spine & loop) Carriageway surface treatment Completed East Hants
SD-EH18016 Keydell Avenue Carriageway surface treatment Completed East Hants
SD-EH18017 Keydell Close Carriageway surface treatment Completed East Hants
SD-EH18018 Cross Lane Carriageway surface treatment Completed East Hants
SD-EH18021 Isnage Farm Lane Carriageway surface treatment Completed East Hants
SD-EH18022 Brockham Hill Lane Carriageway surface treatment Completed East Hants
SD-EH18023 Church Lane Carriageway surface treatment Completed East Hants
SD-EH18024 Howard's Lane (Part & Spur) Carriageway surface treatment Completed East Hants
SD-EH18025 Upper Anstey Lane Carriageway surface treatment July - September East Hants
SD-EH18026 Gilbert White Way Carriageway surface treatment Completed East Hants
SD-EH18027 Slant Hill Carriageway surface treatment July - September East Hants
SD-EH18028 Crabden Lane Carriageway surface treatment Completed East Hants
SD-EH18029 Blendworth Lane Carriageway surface treatment Completed East Hants
SD-EH18030 Patersons Lane Carriageway surface treatment July - September East Hants
SD-EH18031 Boyes Lane Carriageway surface treatment Completed East Hants
SD-EH18032 White Horse Lane Carriageway surface treatment July - September East Hants
SD-EH18033 Duckstile Lane Carriageway surface treatment Completed East Hants
SD-EH18036 Goodyers Carriageway surface treatment Completed East Hants
SD-EH18038 Court Lane Carriageway surface treatment Completed East Hants
SD-EH18039 Shirnall Hill Carriageway surface treatment July - September East Hants
SD-EH18040 The Street Carriageway surface treatment July - September East Hants
SD-EH18041 Church Road Carriageway surface treatment Completed East Hants
SD-EH18042 Bacon Lane Carriageway surface treatment Completed East Hants
SD-EH18043 Rehill Road Footway surface treatment October - December East Hants
SD-EH18044 A3 Slip Road Carriageway surface treatment Completed East Hants
SD-EH18045 Glebe Close Carriageway surface treatment Completed East Hants
B775 Down Street Drainage July - September Basingstoke
B817 A30 London Road Carriageway resurfacing July - September Basingstoke
B862 A30 London Road Drainage October - December Basingstoke
B849 A30 Winchester Road/Wallop Drive Carriageway resurfacing July - September Basingstoke
B509 Olivers Lane Carriageway resurfacing July - September Basingstoke
B727 Weston Road Drainage October - December Basingstoke
B761 Station Road Drainage January - March Basingstoke
B778 Woodbury Road Carriageway resurfacing Completed Basingstoke
B779 A339 Newbury Road Carriageway structural repairs July - September Basingstoke
B786 Church Street rbt Carriageway structural repairs October - December Basingstoke
B789 Roentgen Road Drainage July - September Basingstoke
B804 A340 Ringway West Carriageway resurfacing July - September Basingstoke
B819 Waltham Lane Carriageway resurfacing July - September Basingstoke
B824 Oak Tree Farm Road Carriageway resurfacing July - September Basingstoke
B825 The Knowlings Carriageway resurfacing July - September Basingstoke
B827 Shothanger Lane Carriageway resurfacing July - September Basingstoke
B828 Malshanger Lane Carriageway structural repairs October - March Basingstoke
B838 Bourne Valley Flood Alleviation R6, R18, R31 Drainage July - September Basingstoke
B839 Mapledurwell Drainage October - December Basingstoke
B841 A339 Ringway North - A340 Ringway West rbt Carriageway resurfacing July - September Basingstoke
B847 Milkingpen Lane Drainage October - December Basingstoke
B850 Victoria Road/New Street Carriageway resurfacing July - September Basingstoke
B852 Buckskin Lane Carriageway resurfacing July - September Basingstoke
B858 Brunel Road (On slip) Carriageway resurfacing July - September Basingstoke
B859 The Harrow Way - Viables rbt Drainage October - December Basingstoke
B860 The Baredown Carriageway resurfacing July - September Basingstoke
B861 Homesteads Road Carriageway resurfacing July - September Basingstoke
B865 Ball Hill Road Carriageway structural repairs July - September Basingstoke
B869 Gresley Road Carriageway structural repairs July - September Basingstoke
B871 Old Chapel Lane Carriageway structural repairs July - September Basingstoke
B872 Poyntz Road Carriageway structural repairs October - December Basingstoke
B875 Poyntz Road Footway resurfacing October - December Basingstoke
B886W Vyne Road Carriageway structural repairs October - March Basingstoke
B891W Bottle Lane Carriageway structural repairs October - March Basingstoke
B896W Red Lane Carriageway resurfacing Completed Basingstoke
E627 Brownhill Road Carriageway resurfacing October - December Eastleigh
E654 Winchester Road Carriageway structural repairs July - September Eastleigh
E656 Bubb Lane Carriageway structural repairs October - March Eastleigh
E658 Winchester Road Drainage July - September Eastleigh
E659 Leigh Road Carriageway resurfacing July - September Eastleigh
E662 Chestnut Close Carriageway structural repairs October - December Eastleigh
E667 Carthage Close Carriageway structural repairs October - December Eastleigh
E664 The Recess Carriageway structural repairs January - March Eastleigh
E665 Trevose Close (Loop) Carriageway structural repairs October - December Eastleigh
E666 Sydney Avenue Carriageway resurfacing October - December Eastleigh
E667 Campbell Road Carriageway resurfacing October - December Eastleigh
E668 Brownhill Road Footway resurfacing October - December Eastleigh
E671 Woodside Road Carriageway resurfacing October - December Eastleigh
E672 Navigators Way / Rose Close Footway resurfacing July - September Eastleigh
E673 Hursley Road Carriageway resurfacing July - September Eastleigh
EH559 Tunbridge Lane Drainage July - September East Hants
E694 The Avenue (Spine) Carriageway resurfacing July - September East Hants
EH714 Tunbridge Lane Carriageway structural repairs July - September East Hants
EH723W The Avenue Carriageway structural repairs October - March East Hants
EH556 Stonehill Road Carriageway resurfacing Completed East Hants
EH605 Stonehill Road Drainage July - September East Hants
EH639 Kenley Road Carriageway resurfacing Completed East Hants
EH658 A272 / A32 crossroads Carriageway resurfacing Completed East Hants
EH693 A31 Winchester Road (Lymington Bottom Jct) Carriageway structural repairs July - September East Hants
EH664 A325 Farnham Road - Buckhorn Oak Crossroads Carriageway resurfacing July - September East Hants
EH588 Whichers Gate Road Drainage October - December East Hants
EH640 School Road Drainage July - September East Hants
EH656 Yarhams Lane Carriageway structural repairs October - March East Hants
EH661 West Lane Carriageway resurfacing Completed East Hants
EH666 South Lane Carriageway resurfacing July - September East Hants
EH667 St Marys Road (part) Carriageway structural repairs October - December East Hants
EH670 Murray Road (South Spine) Carriageway structural repairs July - September East Hants
EH673 St Marys Road (part) Footway resurfacing July - September East Hants
EH681 Collywater Lane Carriageway resurfacing July - September East Hants
EH684 Wyck Lane Carriageway structural repairs January - March East Hants
EH685 Ramsdean Lane Carriageway resurfacing July - September East Hants
EH689 Village Street Carriageway resurfacing January - March East Hants
EH692 Brislands Lane Carriageway resurfacing Completed East Hants
EH706 Firgrove Road Carriageway resurfacing July - September East Hants
EH709 Middle Oakshott Farm Lane Carriageway resurfacing July - September East Hants
EH713 Petersfield Road Carriageway resurfacing July - September East Hants
EH724W Woodberry Lane Carriageway structural repairs October - March East Hants
EH733W Gravel Hill Road Carriageway structural repairs October - March East Hants
EH740 Fir Grove Carriageway resurfacing October - December East Hants
EH741 Fir Grove Footway resurfacing October - December East Hants
F673 Gudge Heath Lane Footway resurfacing July - September Fareham
SD-F18003 Burridge Road Carriageway surface treatment July - September Fareham
SD-F18004 Locks Heath Park Road Carriageway surface treatment July - September Fareham
SD-F18005 Ashwood Carriageway surface treatment July - September Fareham
SD-F18006 Peters Road East Carriageway surface treatment July - September Fareham
SD-F18007 Heath Road Carriageway surface treatment July - September Fareham
SD-F18008 Crescent Road Carriageway surface treatment July - September Fareham
SD-F18009 Raley Road Carriageway surface treatment July - September Fareham
SD-F18010 Fleet End Road North Carriageway surface treatment July - September Fareham
SD-F18011 Common Lane Carriageway surface treatment July - September Fareham
SD-F18013 Colinton Avenue Carriageway surface treatment July - September Fareham
SD-F18014 Morningside Avenue Carriageway surface treatment July - September Fareham
SD-F18015 Leith Avenue Carriageway surface treatment July - September Fareham
SD-F18016 Pentland Rise (Spine) Carriageway surface treatment July - September Fareham
SD-F18017 Pentland Rise (Loop Spur) Carriageway surface treatment July - September Fareham
SD-F18018 Carlton Road Carriageway surface treatment July - September Fareham
SD-F18019 A27 Bridge Road Carriageway surface treatment July - September Fareham
SD-F18020 Coach Hill Carriageway surface treatment July - September Fareham
F668 Trinity Street Carriageway resurfacing January - March Fareham
F670 Warsash Road Carriageway structural repairs October - March Fareham
F679 Titchfield Road Carriageway structural repairs October - March Fareham
F680 Hunts Pond Road Carriageway resurfacing July - September Fareham
F681 Church Road Carriageway structural repairs October - December Fareham
F684 West Street Carriageway structural repairs October - December Fareham
F690 Barnes Lane Carriageway structural repairs July - September Fareham
F691 East Street Carriageway resurfacing October - December Fareham
F692 Crescent Road Carriageway structural repairs January - March Fareham
F693 Fareham Park Road Carriageway structural repairs July - September Fareham
F702 Redlands Lane Carriageway resurfacing July - September Fareham
F703 Newtown Road Footway resurfacing July - September Fareham
F717 Broadcut Carriageway structural repairs July - September Fareham
G501 Albemarie Avenue Carriageway structural repairs January - March Gosport
G521 Grange Lane Footway resurfacing July - September Gosport
G525 A32 Fareham Road Carriageway resurfacing January - March Gosport
G528 Rowner Road Carriageway structural repairs October - March Gosport
G529 Linden Grove Carriageway resurfacing January - March Gosport
G530 A32 Mumby Road Carriageway structural repairs October - December Gosport
G532 Military Road Carriageway structural repairs July - September Gosport
G534 Dorrien Road Carriageway resurfacing January - March Gosport
G536 Petrie Road Carriageway resurfacing January - March Gosport
G537 Tukes Avenue (Spine) Carriageway resurfacing July - September Gosport
G539 Repton Close Footway resurfacing October - December Gosport
G541 Fairthorne Gardens Footway resurfacing October - December Gosport
H584 Emsworth Common Road Drainage October - December Havant
H637 Hambledon Road Carriageway structural repairs October - March Havant
H641 Dunsbury Way Carriageway structural repairs July - September Havant
H643 Langstone Road Carriageway structural repairs January - March Havant
H653 Stanbridge Road Carriageway resurfacing October - December Havant
H654 Inhurst Avenue Footway resurfacing October - December Havant
H668W St Georges Walk Carriageway structural repairs October - March Havant
SD-G18001 Gregson Close Carriageway surface treatment Completed Gosport
SD-G18003 Monckton Road Carriageway surface treatment July - September Gosport
SD-G18004 Pepys Close Carriageway surface treatment July - September Gosport
SD-G18005 Nepean Close Carriageway surface treatment July - September Gosport
SD-G18006 Fort Road Carriageway surface treatment July - September Gosport
SD-G18007 Clayhall Road Carriageway surface treatment July - September Gosport
SD-G18008 Waterloo Road Carriageway surface treatment July - September Gosport
SD-G18009 Jellicoe Avenue Carriageway surface treatment July - September Gosport
SD-G18011 Manor Way Carriageway surface treatment July - September Gosport
SD-G18012 Court Road Carriageway surface treatment July - September Gosport
SD-G18013 Newton Place Carriageway surface treatment July - September Gosport
SD-G18014 Nottingham Place Carriageway surface treatment July - September Gosport
SD-G18015 Swanage Road (Part) Carriageway surface treatment July - September Gosport
SD-G18016 Swanage Road (Part) Carriageway surface treatment July - September Gosport
SD-G18017 Queens Road Carriageway surface treatment July - September Gosport
SD-G18018 Sydney Road Carriageway surface treatment July - September Gosport
SD-H18001 Eastleigh Road Carriageway surface treatment July - September Havant
SD-H18005 Sea Front Carriageway surface treatment July - September Havant
SD-H18006 Sea Front Carriageway surface treatment July - September Havant
SD-H18007 Daw Lane Carriageway surface treatment July - September Havant
SD-H18008 Castlemans Lane Carriageway surface treatment July - September Havant
SD-H18009 Northwood Lane Carriageway surface treatment July - September Havant
SD-H18010 Pook Lane Carriageway surface treatment July - September Havant
SD-H18011 Church Lane Carriageway surface treatment July - September Havant
SD-H18012 Church Lane (Spur) Carriageway surface treatment July - September Havant
SD-H18013 Silvester Road Carriageway surface treatment Completed Havant
SD-H18014 Ash Close Carriageway surface treatment Completed Havant
SD-H18015 Hart Plain Avenue Carriageway surface treatment July - September Havant
SD-H18016 Wallis Road Carriageway surface treatment Completed Havant
SD-H18018 Gladys Avenue Carriageway surface treatment Completed Havant
SD-H18018 Dorrita Avenue Carriageway surface treatment Completed Havant
SD-H18019 Maylands Road Carriageway surface treatment July - September Havant
SD-H18022 Jubilee Road Carriageway surface treatment Completed Havant
SD-H18023 Muriel Road Carriageway surface treatment Completed Havant
SD-H18024 Winifred Road Carriageway surface treatment Completed Havant
SD-H18025 Salterns Close Carriageway surface treatment Completed Havant
SD-H18026 Blenheim Gardens (Spur) Footway surface treatment October - December Havant
HR600 A3013 Cove Road Drainage October - December Hart
SD-HR18001 A287 Odiham Bypass Carriageway surface treatment Completed Hart
SD-HR18001A Rushmoor Close Carriageway surface treatment July - September Hart
SD-HR18002 Roke Lane Carriageway surface treatment Completed Hart
SD-HR18003 Hollybush Lane Carriageway surface treatment Completed Hart
SD-HR18004 Sherlock Lea Carriageway surface treatment Completed Hart
SD-HR18005 Broad Oak Lane Carriageway surface treatment Completed Hart
SD-HR18006 Chequers Lane (Part) Carriageway surface treatment Completed Hart
SD-HR18007 Arrow Lane Carriageway surface treatment Completed Hart
SD-HR18008 Grange Road (Spur) Carriageway surface treatment Completed Hart
SD-HR18009 Grange Road Carriageway surface treatment Completed Hart
SD-HR18010 Sprats Hatch Lane Carriageway surface treatment Completed Hart
SD-HR18011 Broad Oak Lane Carriageway surface treatment Completed Hart
SD-HR18012 Poland Lane Carriageway surface treatment Completed Hart
SD-HR18013 Gypsy Lane Carriageway surface treatment Completed Hart
SD-HR18014 Little Dean Lane Carriageway surface treatment Completed Hart
SD-HR18015 Gaston Lane Carriageway surface treatment Completed Hart
SD-HR18016 Tigwells Field Carriageway surface treatment Completed Hart
SD-HR18017 Wingate Lane Carriageway surface treatment Completed Hart
SD-HR18018 Woodhill Lane Carriageway surface treatment Completed Hart
SD-HR18019 Stapley Farm Lane Carriageway surface treatment Completed Hart
SD-HR18020 Newnham Park Carriageway surface treatment Completed Hart
SD-HR18021 Seton Drive Carriageway surface treatment Completed Hart
SD-HR18022 Ively Road Carriageway surface treatment Completed Hart
SD-HR18023 Reading Road Carriageway surface treatment Completed Hart
SD-HR18024 Reading Road North Carriageway surface treatment Completed Hart
SD-HR18025 Pond Croft Carriageway surface treatment Completed Hart
HR626 Weybridge Mead Drainage Completed Hart
HR627 A30 London Road (westbound, lanes 1 & 2) Carriageway resurfacing July - September Hart
HR505 The Street Drainage October - December Hart
HR599 Dipley Road Drainage October - December Hart
HR618 Gables Road Drainage October - December Hart
HR625 Dinorben Avenue Drainage October - December Hart
HR639 Well House Lane Carriageway structural repairs October - March Hart
HR646 Bourley Road Carriageway resurfacing Complete Hart
HR652 Dunleys Hill Carriageway resurfacing January - March Hart
HR654 Marsh Lane Carriageway structural repairs October - March Hart
HR660 B3272 Reading Road Carriageway resurfacing July - September Hart
HR664 Mill Lane/Bowenhurst Lane Carriageway resurfacing January - March Hart
HR667 Old School Road Carriageway resurfacing July - September Hart
HR677 Ewshot Lane Drainage October - December Hart
HR678W Bramshill Road Carriageway structural repairs October - March Hart
HR680W Taplins Farm Lane Carriageway structural repairs October - March Hart
HR684W Hares Lane Carriageway structural repairs October - March Hart
NF860 Christchurch Road Drainage July - September New Forest
NF914 A36 Salisbury Road Carriageway resurfacing January - March New Forest
NF955 Ashley Common Road Carriageway structural repairs July - September New Forest
NF844 Bridge Street Carriageway resurfacing January - March New Forest
NF910 Christchurch Road Carriageway resurfacing Completed New Forest
NF951 Hampston Close Footway resurfacing October - December New Forest
NF953 Calmore Farm Drainage October - December New Forest
NF962 Calmore Drive Carriageway resurfacing October - December New Forest
NF967 Everton Road Footway resurfacing July - September New Forest
NF968 Everton Road Carriageway resurfacing July - September New Forest
NF845 Kings Road Carriageway resurfacing October - December New Forest
NF887 Road through Fritham Carriageway structural repairs October - March New Forest
NF909 Road through Linwood (Broomy Plain) Carriageway resurfacing January - March New Forest
NF913 A35 Redbridge Eastbound Carriageway resurfacing Completed New Forest
NF921 Southampton Road Carriageway resurfacing July - September New Forest
NF923 The Rise Carriageway resurfacing October - December New Forest
NF925 Jordans Lane Carriageway resurfacing October - December New Forest
NF926 Mill Lane Carriageway structural repairs October - December New Forest
NF927 Lakeside (Spine) Carriageway resurfacing October - December New Forest
NF928 Picket Close (Spine) Carriageway resurfacing October - December New Forest
NF929 Newgrounds Carriageway resurfacing October - December New Forest
NF933 Seafield Close (Spine) Carriageway structural repairs October - December New Forest
NF934 Highlands Road Carriageway resurfacing January - March New Forest
NF936 New Street Carriageway resurfacing January - March New Forest
NF944 Woodvale Gardens Footway resurfacing October - December New Forest
NF952 B3054 High Street Carriageway resurfacing October - December New Forest
NF954 B3054 Palace Lane Carriageway resurfacing October - December New Forest
NF956 High Street Carriageway resurfacing Completed New Forest
NF963 Marsh Lane Carriageway structural repairs July - September New Forest
NF964 Salisbury Street Drainage July - September New Forest
NF969 Butts Ash Gardens (Phase 2) Drainage July - September New Forest
SD-NF18001 Nash Road Footway surface treatment October - December New Forest
SD-NF18001A Pound Road (Spine) Carriageway surface treatment July - September New Forest
SD-NF18002 Nash Close Footway surface treatment October - December New Forest
SD-NF18002A Pound Road (Loop) Carriageway surface treatment July - September New Forest
SD-NF18003 Lower Ashley Road Carriageway surface treatment Completed New Forest
SD-NF18003A Mead Road Carriageway surface treatment July - September New Forest
SD-NF18004 Oakwood Avenue Footway surface treatment October - December New Forest
SD-NF18004A Howards Mead Carriageway surface treatment July - September New Forest
SD-NF18005 South Street Carriageway surface treatment Completed New Forest
SD-NF18005A Corbin Road Carriageway surface treatment July - September New Forest
SD-NF18006 Yeomans Way Carriageway surface treatment Completed New Forest
SD-NF18006A Meadow Road Carriageway surface treatment July - September New Forest
SD-NF18007 Wykeham Place Footway surface treatment October - December New Forest
SD-NF18007A Forest Road, Bramshaw Carriageway surface treatment July - September New Forest
SD-NF18008 Powlett Road Footway surface treatment October - December New Forest
SD-NF18008A Beaulieu Road, Lymington Carriageway surface treatment July - September New Forest
SD-NF18009 Undershore Road Carriageway surface treatment Completed New Forest
SD-NF18009A Dibden Bottom Road Carriageway surface treatment July - September New Forest
SD-NF18010 Noulae Lane Carriageway surface treatment Completed New Forest
SD-NF18010A Highfield Close Carriageway surface treatment July - September New Forest
SD-NF18011 Hightown Road Carriageway surface treatment Completed New Forest
SD-NF18011A Highfield Gardens Carriageway surface treatment July - September New Forest
SD-NF18012 Cliffe Road (inc spur) Carriageway surface treatment Completed New Forest
SD-NF18012A Little Burn Carriageway surface treatment July - September New Forest
SD-NF18013 Hobart Road Carriageway surface treatment Completed New Forest
SD-NF18013A Mallard Close Carriageway surface treatment July - September New Forest
SD-NF18014 Waverley Road Carriageway surface treatment Completed New Forest
SD-NF18015 Chapel Lane Footway surface treatment October - December New Forest
SD-NF18016 Haysoms Close Footway surface treatment October - December New Forest
SD-NF18017 Appletree Close Footway surface treatment October - December New Forest
SD-NF18018 Orchard Grove Footway surface treatment October - December New Forest
SD-NF18019 Cowper Avenue Footway surface treatment October - December New Forest
SD-NF18020 Milford Road Footway surface treatment October - December New Forest
SD-NF18021 Waterford Road Footway surface treatment October - December New Forest
SD-NF18022 Litchfield Road Footway surface treatment October - December New Forest
SD-NF18023 Oak Road Footway surface treatment October - December New Forest
SD-NF18024 Seacroft Avenue Footway surface treatment October - December New Forest
SD-NF18025 Pine Close Footway surface treatment October - December New Forest
SD-NF18026 Bishops Close Carriageway surface treatment Completed New Forest
SD-NF18027 Northlands Close Carriageway surface treatment Completed New Forest
SD-NF18028 Hammonds Close Carriageway surface treatment Completed New Forest
SD-NF18029 No Name Carriageway surface treatment Completed New Forest
SD-NF18030 Whipps Hill Carriageway surface treatment Completed New Forest
SD-NF18031 Linford Road Carriageway surface treatment Completed New Forest
SD-NF18032 Hangersley Hill Carriageway surface treatment Completed New Forest
SD-NF18033 Christmas Tree Farm Road Carriageway surface treatment Completed New Forest
SD-NF18034 Highwood Lane Carriageway surface treatment Completed New Forest
SD-NF18035 Marine Drive West Carriageway surface treatment Completed New Forest
SD-NF18036 Vectis Road Carriageway surface treatment Completed New Forest
SD-NF18037 Compton Road Carriageway surface treatment Completed New Forest
SD-NF18038 Old Milton Road Carriageway surface treatment Completed New Forest
SD-NF18039 Loperwood Lane Carriageway surface treatment Completed New Forest
SD-NF18040 Tatchbury Lane Carriageway surface treatment Completed New Forest
SD-NF18042 Holly Road Carriageway surface treatment Completed New Forest
SD-NF18043 Fir Road Carriageway surface treatment Completed New Forest
SD-NF18044 Beech Road Carriageway surface treatment Completed New Forest
SD-NF18045 Green Lane Carriageway surface treatment Completed New Forest
SD-NF18046 Main Road Carriageway surface treatment Completed New Forest
SD-NF18047 Silver Street Carriageway surface treatment July - September New Forest
SD-NF18048 Morland Avenue Footway surface treatment October - December New Forest
SD-NF18049 Princess Road Carriageway surface treatment Completed New Forest
R494 Queens Road Drainage July - September Rushmoor
R492 North Lane Carriageway resurfacing July - September Rushmoor
R524 Farnborough Street Footway resurfacing October - December Rushmoor
R528 Cranmore Lane/Ayling Hill Carriageway resurfacing July - September Rushmoor
R531 Victoria Road Footway resurfacing October - December Rushmoor
SD-R18001 Cranleigh Court Footway surface treatment October - December Rushmoor
SD-R18001A Coleville Road Carriageway surface treatment July - September Rushmoor
SD-R18002A Watts Road Carriageway surface treatment July - September Rushmoor
SD-R18003 Pennine Way Carriageway surface treatment Completed Rushmoor
SD-R18003A Yeomans Close Carriageway surface treatment July - September Rushmoor
SD-R18004 Rowans Close Carriageway surface treatment Completed Rushmoor
SD-R18004A Highfield Path Carriageway surface treatment July - September Rushmoor
SD-R18005 Perring Avenue Carriageway surface treatment Completed Rushmoor
SD-R18005A Highfield Close Carriageway surface treatment July - September Rushmoor
SD-R18006 Derry Road Carriageway surface treatment Completed Rushmoor
SD-R18006A Holly Road Carriageway surface treatment July - September Rushmoor
SD-R18007 Salisbury Road Carriageway surface treatment Completed Rushmoor
SD-R18007A Holly Close Carriageway surface treatment July - September Rushmoor
SD-R18008 Church Avenue Carriageway surface treatment Completed Rushmoor
SD-R18008A Kingsway Carriageway surface treatment July - September Rushmoor
SD-R18009 Oak Road Carriageway surface treatment Completed Rushmoor
SD-R18009A Larch Way (inc Spurs) Carriageway surface treatment July - September Rushmoor
SD-R18010 The Crescent (Part) Carriageway surface treatment Completed Rushmoor
SD-R18010A Moselle Close Carriageway surface treatment July - September Rushmoor
SD-R18011 The Crescent (Part) Carriageway surface treatment Completed Rushmoor
SD-R18011A York Hill Carriageway surface treatment July - September Rushmoor
SD-R18012 Old Farnborough Road (inc parking areas) Carriageway surface treatment Completed Rushmoor
SD-R18013 Cedar Road (Part) Carriageway surface treatment Completed Rushmoor
SD-R18014 Cedar Road (Part) Carriageway surface treatment Completed Rushmoor
SD-R18015 Sycamore Road (Part) Carriageway surface treatment Completed Rushmoor
SD-R18016 St Joseph's Road (Part) Carriageway surface treatment Completed Rushmoor
SD-R18017 St Joseph's Road (Part) Carriageway surface treatment Completed Rushmoor
SD-R18018 St George's Road Carriageway surface treatment Completed Rushmoor
SD-R18019 St Michael's Road Carriageway surface treatment Completed Rushmoor
SD-R18020 East Station Road Carriageway surface treatment Completed Rushmoor
SD-R18021 Manor Walk Carriageway surface treatment Completed Rushmoor
SD-R18023 Elles Road Carriageway surface treatment Completed Rushmoor
SD-TV18001 Braishfield Road Carriageway surface treatment Completed Test Valley
SD-TV18001A Roman Road, Amport (Green Lane) Carriageway surface treatment July - September Test Valley
SD-TV18002A Deacon Road (Water Lane and Kimpton Lane) Carriageway surface treatment July - September Test Valley
SD-TV18002A Norris Close Carriageway surface treatment July - September Test Valley
SD-TV18003A Toledo Grove Carriageway surface treatment July - September Test Valley
SD-TV18003A Anderson Close Carriageway surface treatment July - September Test Valley
SD-TV18004A Footner Close Carriageway surface treatment July - September Test Valley
SD-TV18004A Seville Crescent Carriageway surface treatment July - September Test Valley
SD-TV18005A North Close Carriageway surface treatment July - September Test Valley
SD-TV18006A Peel Close Carriageway surface treatment July - September Test Valley
SD-TV18007A South Close Carriageway surface treatment July - September Test Valley
SD-TV18008A Short Hill Carriageway surface treatment July - September Test Valley
SD-TV18009A Ganger Farm Lane (inc laybys) Carriageway surface treatment July - September Test Valley
SD-TV18010A Ganger Road (inc laybys) Carriageway surface treatment July - September Test Valley
SD-TV18011A Hunters Crescent (inc laybys) Carriageway surface treatment July - September Test Valley
SD-TV18014 Wiremead Lane Carriageway surface treatment Completed Test Valley
SD-TV18015 Bishops Way Footway surface treatment October - December Test Valley
SD-TV18016 The Avenue Footway surface treatment October - December Test Valley
SD-TV18017 Bulford Road Footway surface treatment October - December Test Valley
SD-TV18018 Gardeners Green Footway surface treatment October - December Test Valley
SD-TV18019 Gardeners Green Footpath Footway surface treatment October - December Test Valley
SD-TV18020 Gilberts Green Footway surface treatment October - December Test Valley
SD-TV18021 Goodwyns Close Footway surface treatment October - December Test Valley
SD-TV18022 Hedges Close Footway surface treatment October - December Test Valley
SD-TV18023 High Street Footway surface treatment October - December Test Valley
SD-TV18024 Kingfishers Footway surface treatment October - December Test Valley
SD-TV18025 Manor Close Footway surface treatment October - December Test Valley
SD-TV18026 Mayfield Close Footway surface treatment October - December Test Valley
SD-TV18027 Muscott Close (Link) Footway surface treatment October - December Test Valley
SD-TV18028 Muscott Close (Spine and Spurs) Footway surface treatment October - December Test Valley
SD-TV18029 Parkhouse Road Footway surface treatment October - December Test Valley
SD-TV18030 Sarum Close (Spine and Head) Footway surface treatment October - December Test Valley
SD-TV18031 A338 Salisbury Road Footway surface treatment October - December Test Valley
SD-TV18032 St Peters Close Footway surface treatment October - December Test Valley
SD-TV18033 The Orchard Footway surface treatment October - December Test Valley
SD-TV18034 Threadgill Way Footway surface treatment October - December Test Valley
SD-TV18035 Aerodrome Road Carriageway surface treatment Completed Test Valley
SD-TV18036 Village Street Carriageway surface treatment Completed Test Valley
SD-TV18037 Stanbury Road Carriageway surface treatment Completed Test Valley
SD-TV18038 Privett Lane Carriageway surface treatment Completed Test Valley
SD-TV18039 Halcyon Drive Carriageway surface treatment Completed Test Valley
SD-TV18040 Beech Close Carriageway surface treatment Completed Test Valley
SD-TV18041 Norman Court Lane Carriageway surface treatment Completed Test Valley
SD-TV18042 Cowdon Lane Carriageway surface treatment Completed Test Valley
SD-TV18043 Micheldever Road Carriageway surface treatment Completed Test Valley
SD-TV18044 Little Drove Road Carriageway surface treatment Completed Test Valley
SD-TV18045 Little Drove Road Carriageway surface treatment Completed Test Valley
SD-TV18046 River View Close (Spine and Spurs) Carriageway surface treatment Completed Test Valley
SD-TV18047 Canada Road Carriageway surface treatment Completed Test Valley
SD-TV18048 Plantation Road Carriageway surface treatment Completed Test Valley
SD-TV18049 Slab Lane Carriageway surface treatment Completed Test Valley
SD-TV18050 Dandys Ford Lane Carriageway surface treatment Completed Test Valley
SD-TV18051 Lockerley Road Carriageway surface treatment Completed Test Valley
SD-TV18052 East Dean Road Carriageway surface treatment Completed Test Valley
SD-TV18054 Flexford Close Carriageway surface treatment Completed Test Valley
R503 A323 Wellington Avenue Carriageway resurfacing Completed Rushmoor
R505 Kingsley Road Footway resurfacing July - September Rushmoor
R521 A331 Blackwater Valley Route (Pond R8) Drainage October - December Rushmoor
R522 A325 Farnborough Road, Aldershot 1 (on-off slip roads) Carriageway resurfacing Completed Rushmoor
R523 A325 Farnborough Road, Aldershot 2 (Wellington Rd, rbt) Carriageway resurfacing Completed Rushmoor
TV589 Botley Road Carriageway resurfacing Completed Test Valley
TV603 Station Road Carriageway structural repairs Completed Test Valley
TV574 The Crescent Drainage October - December Test Valley
TV577 Romsey Road Carriageway structural repairs October - March Test Valley
TV578 Romsey Road Carriageway structural repairs October - March Test Valley
TV583 Stockbridge Road Carriageway structural repairs October - March Test Valley
TV584 Romsey Road Carriageway structural repairs October - March Test Valley
TV600 A330 Salisbury Road Carriageway resurfacing July - September Test Valley
TV602 Salisbury Road Carriageway structural repairs October - March Test Valley
TV608 Braishfield Road (North) Carriageway structural repairs October - March Test Valley
TV609 Church Lane Carriageway resurfacing July - September Test Valley
TV612 Newbury Road Carriageway resurfacing July - September Test Valley
TV615 Southampton Road Carriageway resurfacing Completed Test Valley
TV617 Standing Hill Carriageway resurfacing Completed Test Valley
TV619 Pound Road Carriageway structural repairs October - December Test Valley
TV620 Wills Way (Spine) Carriageway resurfacing Completed Test Valley
TV623 Greensey Carriageway structural repairs October - December Test Valley
TV624 Misslebrook Lane Carriageway structural repairs October - March Test Valley
TV626 Chilworth Old Village Carriageway structural repairs October - March Test Valley
TV628 Toogoods Way Carriageway structural repairs October - December Test Valley
TV633 Knightwood Road rbt Carriageway resurfacing Completed Test Valley
TV636 Bunny Lane Drainage July - September Test Valley
TV638 Amesbury Road Footway resurfacing July - September Test Valley
TV639 Romsey Road Carriageway structural repairs October - March Test Valley
TV640 Braishfield Road Carriageway resurfacing Completed Test Valley
TV643 Winchester Road Carriageway structural repairs July - September Test Valley
TV645 Green Lane Carriageway structural repairs July - September Test Valley
TV646 Romsey Road Carriageway resurfacing October - December Test Valley
TV659W Lockerley Road Carriageway structural repairs October - March Test Valley
TV660W Danes Road Carriageway structural repairs October - March Test Valley
SD-W18001 Farley Close Carriageway surface treatment Completed Winchester
SD-W18001A Hall Close Footway surface treatment October - December Winchester
SD-W18002 Braeside Close Carriageway surface treatment Completed Winchester
SD-W18002A Colville Close Carriageway surface treatment July - September Winchester
SD-W18003 Treble Close Carriageway surface treatment Completed Winchester
SD-W18003A Butts Farm Lane Carriageway surface treatment July - September Winchester
SD-W18004 Momford Road Carriageway surface treatment Completed Winchester
SD-W18004A Rareridge Lane (part) Carriageway surface treatment July - September Winchester
SD-W18005 Sunnydown Road Carriageway surface treatment Completed Winchester
SD-W18005A Baybridge Lane Carriageway surface treatment July - September Winchester
SD-W18006 Broad View Lane Carriageway surface treatment Completed Winchester
SD-W18006A B3047 Alresford Road (Winchester Road and The Avenue) Footway surface treatment October - December Winchester
SD-W18007 Pine Close Carriageway surface treatment Completed Winchester
SD-W18008 Beech Close Carriageway surface treatment Completed Winchester
SD-W18009 Wedmore Close Carriageway surface treatment Completed Winchester
SD-W18010 Lisle Close Carriageway surface treatment Completed Winchester
SD-W18011 Old Kennels Close Carriageway surface treatment Completed Winchester
SD-W18012 A272 Andover Road Carriageway surface treatment Completed Winchester
SD-W18013 B3047 Alresford Road (Winchester Road and The Avenue) Carriageway surface treatment Completed Winchester
SD-W18014 B3046 Jacklyns Lane Carriageway surface treatment Completed Winchester
SD-W18015 Crawley Road Carriageway surface treatment Completed Winchester
SD-W18016 Malthouse Close Footway surface treatment October - December Winchester
SD-W18019 B2177 Winchester Road Carriageway surface treatment Completed Winchester
SD-W18023 Christmas Hill Carriageway surface treatment Completed Winchester
SD-W18024 Rodfield Lane Carriageway surface treatment Completed Winchester
SD-W18025 Cross Lane Carriageway surface treatment Completed Winchester
SD-W18026 Vernon Hill Lane Carriageway surface treatment Completed Winchester
SD-W18027 Shipcote Lane Carriageway surface treatment Completed Winchester
SD-W18028 Little Ashton Lane Carriageway surface treatment Completed Winchester
SD-W18029 Queens Street Carriageway surface treatment Completed Winchester
SD-W18030 Wrights Close (inc spurs) Carriageway surface treatment Completed Winchester
SD-W18031 Wrights Way (inc spurs) Carriageway surface treatment Completed Winchester
SD-W18032 Keats Close Carriageway surface treatment Completed Winchester
SD-W18033 Burns Close Carriageway surface treatment Completed Winchester
SD-W18034 Chaucer Close Carriageway surface treatment Completed Winchester
SD-W18035 Southdown Road Carriageway surface treatment Completed Winchester
SD-W18037 Fairfield Road Carriageway surface treatment Completed Winchester
SD-W18038 Grove Road Carriageway surface treatment Completed Winchester
SD-W18039 Woodmancott Farm Lane (Local name) Carriageway surface treatment July - September Winchester
SD-W18040 Vicarge Lane Carriageway surface treatment July - September Winchester
SD-W18041 Rownest Wood Lane Carriageway surface treatment July - September Winchester
SD-W18042 Embley Wood Lane Carriageway surface treatment Completed Winchester
SD-W18043 Crawley Down Lane Carriageway surface treatment July - September Winchester
SD-W18045 Alresford Road Carriageway surface treatment Completed Winchester
SD-W18047 Southwick Road Carriageway surface treatment Completed Winchester
SD-W18048 Stoke Charity Road Carriageway surface treatment Completed Winchester
SD-W18049 Millbarrows Carriageway surface treatment Completed Winchester
W784 B2150 Well Hill Road Carriageway structural repairs October - March Winchester
W701 Moorside Road Carriageway resurfacing Completed Winchester
W728 Fontley Road Drainage July - September Winchester
W729 Spring Lane Drainage July - September Winchester
W734 Brook Lane Drainage July - September Winchester
W763 A31 Percy Hobbs Drainage July - September Winchester
W770 A334 Station Hill Drainage July - September Winchester
W771 City Road Crossroads Carriageway resurfacing Completed Winchester
W772 B3330 City Road Carriageway resurfacing Completed Winchester
W819 Avenue Road Carriageway resurfacing July - September Winchester
W782 Bar End Road & Chesil Street Carriageway resurfacing Completed Winchester
W790 Solomons Lane Carriageway resurfacing July - September Winchester
W500 Jewry Street Carriageway resurfacing July - September Winchester
W670 Southwick Road Drainage October - December Winchester
W689 Links Road Carriageway resurfacing July - September Winchester
W730 Cheriton Road Carriageway resurfacing July - September Winchester
W751 Salt Lane Carriageway structural repairs October - March Winchester
W776 Forest Road Carriageway resurfacing July - September Winchester
W783 B3035 Botley Road Carriageway structural repairs October - March Winchester
W786 B2177 - entrances to 3 Oaks Care Home, Southwick Road Carriageway resurfacing October - December Winchester
W797 Hursley Road Drainage October - December Winchester
W813 Pudding Lane Carriageway resurfacing July - September Winchester
W816 Mead Road Carriageway structural repairs July - September Winchester
W820 Stoney Lane Carriageway structural repairs July - September Winchester
W825 Fraser Road, Kingsworthy Carriageway resurfacing July - September Winchester
W827 Easton Lane Carriageway resurfacing July - September Winchester
W829 Andover Road North Footway resurfacing January - March Winchester
W830 A334 Winchester Road Carriageway resurfacing July - September Winchester
W831 Pound Road (part) Carriageway resurfacing October - December Winchester
W841 A272 Andover Road - Three Maids rbt Carriageway structural repairs July - September Winchester
W844 Sheepwash Lane Carriageway resurfacing Completed Winchester
W845 Spring Vale Road Carriageway resurfacing July - September Winchester
W847 Whaddon Lane Drainage October - December Winchester
W858 Garrison Hill & Sheep Pond Lane Carriageway resurfacing July - September Winchester
W859 Hockley Link Drainage January - March Winchester
W860 Winchester Road (1) Drainage October - December Winchester
W861 Winchester Road (2) Drainage October - December Winchester
W864 Boarhunt Road Carriageway resurfacing Completed Winchester
W900W Morestead Road Carriageway structural repairs October - March Winchester