M27 Junction 10 improvement scheme news
News and updates from the M27 Junction 10 improvement scheme
Showing 1 - 7 of 7 results found
-
22/04/2025
Travel Alert: BT Cable Diversion Works on A32 near M27 Junction 10, Fareham
Night Works on 29 April for four nights
-
22/04/2025
April 2025 - Scheme Progress
April 2025 - Scheme Progress. read ( words). Apr 22 2025. As part of the improvement works, the installation of sheet piles adjacent to junction 10 of the M27 will take place from Wednesday 9 April to Friday 25 April. The permitted working hours for
-
22/04/2025
Christmas 2025 - Closure of M27 J9-J11
The pre-constructed underpass will be “slid” into position between the Christmas 2025 and New Year period over the school holidays, whilst traffic volumes are lower
-
09/04/2025
M27 Junction 10 Eastbound & Westbound Slip Roads Closure
Night work on Friday 11 April 2025.
-
03/04/2025
M27 Junction 9-10 eastbound and Junction 11-9 westbound overnight road closures
M27 Junction 9-10 eastbound and Junction 11-9 westbound overnight road closures. read ( words). Apr 3 2025. As part of the ongoing M27 Junction 10 improvement works to support the Welborne Garden Village development near Fareham, some full and
-
03/04/2025
Full overnight closures
Full overnight closures. read ( words). Apr 3 2025. Night Works Completed. Eastbound. M27 eastbound full overnight closure between junctions 9 and 11 (between Whiteley and Fareham) will take place:. Sunday 30 March between 9pm and 6am (Monday 31
-
18/03/2025
National Highway M27 junctions 11 and 12 near Fareham - Repair Works
National Highways will be repairing a section of the central reservation concrete safety barrier on the M27 near Fareham