Progress gallery

Images of work being carried out as part of the scheme

Box Structure Construction – Time-Lapse Video

Box Structure Progress

Photograph of Box construction progress

Box construction progress June 2025

Roundabouts

Aerial View of the box construction

Aerial View of the box construction June 2025

Progress of the four roundabouts June 2025

Progress of the four roundabouts June 2025

Photograph of the construction of Broadway roundabout

Construction of the Broadway roundabout, taking place in the field to the west of the A32.

Photograph of the construction of Broadway roundabout

Construction of the Welborne approach roundabout.

Workers air testing within a manhole; constructed as part of the scheme to facilitate drainage.

Workers air testing within a manhole; constructed as part of the scheme to facilitate drainage.

Construction progress on Broadway Roundabout

Construction progress on Broadway Roundabout.

Guide slab

February 2025 - Progress on the Guide Slab

February 2025 - Progress on the Guide Slab

Guide slab drone image

Guide slab drone image.

Applying polythene and grease to the guide slab

Applying polythene and grease to the guide slab makes the moving the box structure easier when it is pushed into its final position.

Reinforcement bars (rebar) being hoisted by a crane onto the guide slab

The reinforcement bars (rebar) are manufactured off-site and then hoisted by a crane onto the guide slab for the operatives to fix them together in place on-site.

The reinforcement bars (rebar) are affixed by hand

The reinforcement bars (rebar) are affixed by hand. It acts like a skeleton within the structure. Once the concrete is poured it will give extra support for the box structure to stay strong and stable.

Installation of the cables for pushing the box slide into position

Progress of the guide slab with installation of the cables for pushing the box slide into position.

Photograph of ongoing box slide construction

Ongoing guide slab construction.

Preparation of the guide slab for the box slide. This guide slab is crucial because it provides a stable and level surface on which the box structure will be built and eventually moved.

Preparation of the guide slab for the box slide. This guide slab is crucial because it provides a stable and level surface on which the box structure will be built and eventually moved.

Photograph of construction of the guide slab.

Construction of the guide slab. The slab will play a critical role in ensuring the underpass can slide accurately into its final position. Construction of the underpass box will begin once the slab is in place.

Photograph of ongoing box slide construction

Ongoing box slide construction.

Preparatory works of the guide slab - drone image

Preparatory works of the guide slab - drone image.

Artist's impression of the completed box slide.

Artist's impression of the guide slab.

Ecology

Sleeping dormouse

December 2024 - The licensed ecologist inspected the dormouse nest boxes, removed old nesting material, and ensured the boxes were ready for the next breeding season.

Image of snake and reptile fencing south of M27

February 2025 - Repaired reptile fencing south of the M27 and installed new sections north of the M27. Vegetation clearance in selected areas of the embankment to prepare for slip road construction.

Dormouse in nesting box

March 2025 - New dormouse boxes were installed to comply with ‘European Protected Species Dormouse’ licences.