November 2025 - Progress Update

Nov 26 2025

Work is progressing well on the construction of the new slip roads at Junction 10. These are a key part of the junction upgrade, designed to enhance connectivity and reduce congestion for traffic joining and leaving the motorway. Once complete, the new slip roads will provide improved access for westbound and eastbound traffic.

Current construction works:
  • Westbound on-slip - final road surfacing, communications equipment and acoustic/safety fencing
  • Westbound off-slip - adding topsoil to the verges and installing drainage
  • Eastbound off-slip - installing the foundations for the overhead gantry sign and installing drainage and ducting (these are underground protective tubes that house data and signal cables for traffic management and safety systems). Final road surfacing, communications equipment and acoustic/safety fencing.

M27 J10, new westbound off-slip,  new westbound on-slip and new eastbound off-slip

Raising a cup for a worthy cause 

The project team recently donated sweet treats and cakes for colleagues to enjoy over a cuppa and raised over £200 for Macmillan Cancer Support. A big thank you to everyone who took part and contributed to this meaningful cause.

Macmillan Cancer Support - Coffee Morning